Photo from iStock-627281636
2021 Cost of Wind Energy
Review
Tyler Stehly and Patrick Duffy
National Renewable Energy Laboratory
December 2022
NREL | 2
Acknowledgments
The authors would like to thank Patrick Gilman (U.S. Department of Energy Office of Energy
Efficiency and Renewable Energy Wind Energy Technologies Office [WETO]) for supporting this
research. Thanks also to Gage Reber (contractor to WETO) and Daniel Beals of Allegheny Science
and Technology (contractor to WETO) for reviewing prior versions of this presentation. Thank you
to Ryan Wiser and Mark Bolinger (Lawrence Berkeley National Laboratory) and Alice Orrell (Pacific
Northwest National Laboratory) for their analysis of wind project market data that informed this
analysis and to Parangat Bhaskar (National Renewable Energy Laboratory) for supporting the
techno-economic analysis. Thanks also to Philipp Beiter and Eric Lantz (National Renewable Energy
Laboratory) for their technical guidance and Amy Brice (National Renewable Energy Laboratory) for
editing the presentation. Any remaining errors or omissions are the sole responsibility of the
authors.
NREL | 3
List of Acronyms
AEP annual energy production
ATB Annual Technology Baseline
BOS balance of system
CapEx capital expenditures
CRF capital recovery factor
CSM Cost and Scaling Model
DOE U.S. Department of Energy
DW distributed wind
FCR fixed charge rate
FY fiscal year
GPRA Government Performance and Results Act
GW gigawatt
IEC International Electrotechnical Commission
kW kilowatt
LandBOSSE Land-based Balance of System Systems Engineering
LCOE levelized cost of energy
m meter
m/s meters per second
MACRS Modified Accelerated Cost Recovery System
MW megawatt
MWh megawatt-hour
NCF net capacity factor
NREL National Renewable Energy Laboratory
O&M operations and maintenance
OpEx operational expenditures
ORCA Offshore Wind Regional Cost Analyzer
PTC production tax credit
USD U.S. dollars
WACC weighted-average cost of capital
WETO Wind Energy Technologies Office
yr year
Executive Summary
NREL | 5
Executive Summary
The 11
th
annual Cost of Wind Energy Review, now presented in slide deck format, uses representative utility-scale and
distributed wind energy projects to estimate the levelized cost of energy (LCOE) for land-based and offshore wind power
plants in the United States.
Data and results are derived from 2021 commissioned plants, representative industry data, and state-of-the-art
modeling capabilities.
The goals of this analysis are to provide insight into current component-level costs and give a basis for understanding
the variability in wind energy LCOE across the country.
The primary elements of this 2021 analysis include:
Estimated LCOE for (1) a representative land-based wind energy project installed in a moderate wind resource in the
United States, (2) a representative fixed-bottom offshore wind energy project installed in the U.S. North Atlantic, and
(3) a representative floating offshore wind energy project installed off the U.S. Pacific Coast
Updated LCOE estimates for representative residential-, commercial-, and large-scale distributed wind projects
installed in a moderate wind resource in the United States
Sensitivity analyses showing the range of effects that basic LCOE variables could have on the cost of wind energy for
land-based and offshore wind projects
Updated Fiscal Year 2022 values for land-based and offshore wind energy used for Government Performance and
Results Act (GPRA) reporting and illustrated progress toward established GPRA targets.
NREL | 6
Key Inputs and Levelized Cost of Energy Results
Note: Unless specifically stated, all cost data are reported in 2021 U.S. dollars (USD).
Land-Based Offshore Distributed
Parameter Unit
Utility-Scale
Land-Based
Utility-Scale
(Fixed-Bottom)
Utility-Scale
(Floating)
Single-
Turbine
(Residential)
Single-
Turbine
(Commercial)
Single-
Turbine
(Large)
Wind turbine rating MW 3 8 8 20 (kW) 100 (kW) 1.5
Capital expenditures (CapEx) $/kW 1,501 3,871 5,577 5,675 4,300 3,540
Fixed charge rate (FCR) [real] % 5.88 5.82 5.82 5.88 5.42 5.42
Operational expenditures
(OpEx)
$/kW/yr 40 111 118 35 35 35
Net annual energy production MWh/MW/yr 3,775 4,295 3,336 2,580 2,846 3,326
Levelized Cost of Energy (LCOE) $/MWh 34 78 133 143 94 68
NREL | 7
Levelized Cost Breakdown for
Reference Land-Based Wind Plant
5.0
8.2
3.3
0.4
0.2
1.2
0.6
0.7
2.1
1.4
0.4
10.7
34
$0
$5
$10
$15
$20
$25
$30
$35
$40
Levelized Cost of Energy (2021 $/MWh)
Turbine CapEx (48%) Balance of System CapEx (15%)
Financial
CapEx (5%)
OpEx (32%)
NREL | 8
Levelized Cost Breakdown for
Reference Fixed-Bottom Offshore Wind Plant
17.6
1.2
0.0*
6.7
9.4
5.5
0.5
0.5
1.6
2.1
5.0
2.4
7.1
18.8
78
$0
$20
$40
$60
$80
Levelized Cost of Energy (2021 $/MWh)
OpEx
(33%)
Financial CapEx (14.6%)
Balance of System CapEx
(29.8%)
Turbine
(22.5%)
* Engineering Management cost small, but nonzero
NREL | 9
Levelized Cost Breakdown for
Reference Floating Offshore Wind Plant
22.7
1.5
0.0*
36.5
13.0
5.5
3.1
0.9
1.8
3.9
7.5
0.9
9.1
26.3
133
$0
$20
$40
$60
$80
$100
$120
$140
Levelized Cost of Energy (2021 $/MWh)
* Engineering Management cost small, but nonzero
Balance of System CapEx (45.0%)
Financial CapEx (11.2%)
OpEx
(26.6%)
Turbine
(17.1%)
NREL | 10
Levelized Cost Breakdown for
Reference Distributed Wind Projects
Single-Turbine Residential
(20 kW)
58.6
70.6
13.6
143
$0
$20
$40
$60
$80
$100
$120
$140
$160
Wind
turbine
CapEx
BOS CapEx OpEx LCOE
Levelized Cost of Energy (2021 $/MWh)
48.1
33.7
12.3
94
$0
$20
$40
$60
$80
$100
$120
$140
$160
Wind
turbine
CapEx
BOS CapEx OpEx LCOE
Levelized Cost of Energy (2021 $/MWh)
42.2
15.5
10.5
68
$0
$20
$40
$60
$80
$100
$120
$140
$160
Wind
turbine
CapEx
BOS CapEx OpEx LCOE
Levelized Cost of Energy (2021 $/MWh)
Single-Turbine Commercial
(100 kW)
Single-Turbine Large
(1,500 kW)
NREL | 11
Key Conclusions
The reference project LCOE for land-based installations is $34/MWh, with a range of land-
based estimates from the single-variable sensitivity analysis covering $28$70/MWh.
The fixed-bottom offshore wind estimate is $78/MWh, and the floating substructure
reference project estimate is $133/MWh. These two reference projects give a single-variable
sensitivity range of $53$179/MWh. This range is primarily caused by the large variation in
CapEx ($1,990$6,971/kW) and project design life.
The residential and commercial reference distributed wind system LCOE are estimated at
$143/MWh and $94/MWh, respectively. Single-variable sensitivity analysis for the
representative systems is presented in the 2019 Cost of Wind Energy Review (Stehly, Beiter,
and Duffy 2020). Analysts included the LCOE estimate for a large distributed wind energy
project in this years analysis, estimated at $68/MWh.
1
2
3
4
5
6
7
NREL | 12
Background
U.S. Department of Energy Goals and Reporting Requirements
Land-Based Wind
Offshore Wind
Distributed Wind
References
Appendix
Contents
1. Background
NREL | 14
Background
The 2021 Cost of Wind Energy Review estimates the levelized cost of energy (LCOE) for land-based,
offshore, and distributed wind energy projects in the United States.
LCOE is a metric used to assess the cost of electricity generation and the total power-plant-level
impact from technology design changes and can be used to compare costs of all types of generation.
The specific LCOE method applied in this analysis is described in A Manual for the Economic
Evaluation of Energy Efficiency and Renewable Energy Technologies (Short, Packey, and Holt 1995):
 =
  + 


1,000
LCOE = levelized cost of energy (dollars per megawatt-hour
[$/MWh])
FCR = fixed charge rate (%)
CapEx = capital expenditures (dollars per kilowatt [$/kW])
AEPnet = net average annual energy production (megawatt-hours
per megawatt per year [MWh/MW/yr])
OpEx = operational expenditures ($/kW/yr).
NREL | 15
Background
This review also provides an update to the 2020 Cost of Wind Energy Review (Stehly and Duffy 2021) and examines
wind turbine costs, financing, and market conditions. The analysis includes:
Estimated LCOE for a representative land-based wind energy project installed in a moderate wind resource
(i.e., International Electrotechnical Commission [IEC] wind class IIb [IEC 2020]) in the United States
Estimated LCOE for representative offshore (fixed-bottom and floating) wind energy projects using National
Renewable Energy Laboratory (NREL) models and databases of globally installed projects; the authors
assessed representative sites on the U.S. North Atlantic Coast (fixed bottom) and Pacific Coast (floating)
using current lease and call information, nominations data from the Bureau of Ocean Energy Management,
and various geospatial data sets
LCOE estimates for representative residential, commercial, and large distributed wind energy projects in
the United States
Sensitivity analyses showing the range of effects that basic LCOE variables could have on the cost of wind
energy for land-based and offshore wind power plants
Updates to the national supply curves for land-based and offshore wind energy based on geographically
specific wind resource conditions paired with approximate wind turbine size characteristics
Projected land-based and offshore wind cost trajectories from 2021 through 2030 used for U.S. Department
of Energy (DOE) annual wind power LCOE reporting as required by the Government Performance and Results
Act (GPRA).
2. U.S. Department of
Energy Goals and
Reporting Requirements
NREL | 17
DOE Goals and Reporting Requirements
Every year, the Wind Energy Technologies Office (WETO) reports the LCOE for land-based
wind and fixed-bottom offshore wind to satisfy GPRA reporting requirements.
The official GPRA LCOE end-point targets presented in this report were set in Fiscal Year (FY)
2016 for land-based wind energy and updated in FY 2019 for fixed-bottom offshore wind
energy.
Updates to the LCOE targets are periodically implemented to keep performance measures
current with developments in the market and reduce the impact of inflation on LCOE for
land-based and offshore wind energy projects.
The GPRA targets are based on trajectories for land-based and fixed-bottom offshore wind
projects that span from the current year to FY 2030.
It is required that each year the actual costs for land-based and fixed-bottom wind LCOE be
reported against the GPRA targets.
This work provides the cost data to DOE to meet the annual GPRA reporting requirement.
NREL | 18
*The GPRA baseline and target LCOE are reported in 2015 USD for land-based wind energy because WETO will report land-based wind values in 2015 USD.
Government Performance and Results Act Cost Reduction
Pathway From 2016 to 2030 for Land-Based Wind
The land-based wind GPRA baseline value starts at $56/MWh (in 2015 USD) set in FY 2016, using the 2015 reference project data presented in Moné et al. (2017).
The land-based wind GPRA target is $23/MWh by 2030 (in 2015 USD) and is derived from the analysis conducted in Enabling the SMART Wind Power Plant of the
Future Through Science-Based Innovation (Dykes et al. 2017).
56
23
-8
-20
-4
-1
$0
$10
$20
$30
$40
$50
$60
FY 2016 GPRA CapEx AEP OpEx Financing FY 2030 Target
LCOE (2015 $/MWh)*
Net 31% CapEx
reduction
through wind
plant economies
of scale, turbine
scaling with less
material use, and
efficient
manufacturing
Net 57% increase in
energy production
through turbine
scaling, enhanced
control strategies,
and reducing wind
plant losses
Net 41% OpEx
reduction from
advanced
operations and
maintenance
(O&M) strategies
Net 6% cost of
capital reduction
from increased
certainty of future
plant performance
and reduced risk
NREL | 19
Government Performance and Results Act Cost Reduction
Pathway From 2018 to 2030 for Fixed-Bottom Offshore Wind
The GPRA baseline value starts at $89/MWh (in 2018 USD) set in FY 2019 using 2018 reference project data reported in Stehly and Beiter (2019).
The GPRA target is $51/MWh by 2030 (in 2018 USD) and is derived for a fixed-bottom wind plant with 15 MW at the reference site based on cost
reductions informed by technology innovations considered in the spatial economic analysis by Beiter et al. (2016).
Net 22% CapEx
reduction through wind
plant economies of
scale, turbine scaling,
export/array cables
with less material use,
and optimized
foundation design
Net 19% increase in AEP
through turbine scaling,
enhanced control
strategies, reduced wind
plant losses, and higher
availability due to
improved vessel access
Net 54% OpEx reduction
from advanced O&M
strategies, improved
vessel accessibility, and
remote maintenance
strategies
NREL | 20
Modeled Cost Reduction Pathway From 2018 to 2030
for Floating Offshore Wind Energy
Net 53% OpEx reduction
from advanced O&M
strategies, improved
vessel accessibility, and
remote maintenance
strategies
Net 36% CapEx reduction
through wind plant
economies of scale, turbine
scaling and export/array
cables with less material
use, and optimized
foundation design
Net 28% increase in energy
production through turbine
scaling, enhanced control
strategies, reduced wind
plant losses, and higher
availability due to improved
vessel access
DOE had no official GPRA reporting requirement for floating offshore wind energy costs.
Projected floating offshore wind cost reductions are mapped to $60/MWh in 2030 using similar methodology as fixed-bottom offshore wind.
DOE has established a Floating Offshore Wind Shot
target of $45/MWh by 2035 for a different reference site using a different set of assumptions.
NREL | 21
GPRA Cost Reduction Pathway and Historical Cost Data From
2016 to 2030 for Land-Based Wind Energy
The current and historical LCOE values (labeled as “Actuals”) are tracked against the GPRA trajectory.
The GPRA trajectory and LCOE values are reported in 2015 USD since WETO will report land-based wind energy values in 2015 USD.
The FY 2022 LCOE is reported as $29/MWh instead of $34/MWh, as it was converted from 2021 USD to 2015 USD assuming a −12.5%
cumulative rate of inflation from the Bureau of Labor and Statistics (undated), to compare against the GPRA trajectory.
23
56
52
48
40
34
31
29
0
10
20
30
40
50
60
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
LCOE (2015 $/MWh)
Fiscal Year
GPRA Trajectory Actuals
NREL | 22
GPRA Cost Reduction Pathway and Historical Cost Data From
2016 to 2030 for Fixed-Bottom Offshore Wind Energy
The current and historical LCOE values (labeled as “Actuals”) are tracked against the GPRA trajectory.
The GPRA trajectory and LCOE values are reported in 2018 USD per WETOs congressional reporting requirements.
The FY 2022 LCOE is $73/MWh (2018 USD) after being converted from 2021 USD to compare against the GPRA
trajectory.
3. Land-Based Wind Energy
NREL | 24
Land-Based Wind Turbine Average Nameplate Capacity, Hub
Height, Rotor Diameter, and Assumed Representative Wind Plant
Parameter Value
Wind turbine rating 3.0 MW
Rotor diameter 127 m
Hub height 95 m
Specific power 237 W/m
2
Wind plant capacity 200 MW
Number of turbines 67
Source: Wiser and Bolinger (2022)
Power curve data available on
https://github.com/NREL/turbine-
models.
2021 average wind turbine
characteristics
NREL | 25
Reference Land-Based Wind Site Characteristics and
Performance
Parameter Value
Annual average wind speed
at 50 m above surface level
7.25 m/s
Annual average wind speed
at hub height
7.95 m/s
Weibull k 2.0 (factor)
Shear exponent 0.14
Gross energy capture 4,395
MWh/MW/yr
Gross capacity factor 50.2%
Losses 15%
Availability 98%
Total losses 16.7%
Net energy capture 3,661
MWh/MW/yr
Net capacity factor 41.8%
Wind resource of the United States, annual average wind speed at 100 m above surface level.
Source: NREL (2017)
NREL | 26
Rotor
Nacelle
Tower
Development
Engineering and
Management
Foundation
Site Access and Staging
Assembly and
Installation
Electrical Infrastructure
Contingency
Construction Finance
21.4%
35.0%
14.0%
1.6%
0.7%
5.2%
2.8%
2.8%
9.0%
6.0%
1.5%
Turbine
70.4%
Balance of
System
22.0%
Financial
7.5%
Land-Based Wind Project
Component Cost Breakdown
Parameter Value
($/kW)
Wind Turbine CapEx 1,030
Rotor $313
Nacelle 512
Tower 204
BOS CapEx 322
Engineering 23
Project management 10
Foundation 75
Site access, staging, and facilities 40
Assembly and installation 41
Electrical infrastructure 132
Financial CapEx 113
Construction finance 23
Contingency 90
Total CapEx 1,501
Turbine component cost estimates are derived from the 2015 Cost and Scaling Model, used as an internal reference and not publicly available.
BOS component cost estimates are obtained from the Land-based Balance of System Systems Engineering (LandBOSSE) model (Eberle et al. 2019).
Construction financing was estimated assuming a 3-year construction duration and distributing the capital and interest over the 3 years.
Project contingency assumes 6% of total CapEx.
Total installed project CapEx for U.S. projects in 2021 averaged $1,501/kW (Wiser and Bolinger 2022).
All costs reported in 2021 USD
NREL | 27
Land-Based Wind Plant Operational Expenditures
Estimate and Historical Data
Parameter Value
Estimated OpEx $40/kW-yr
Source: Wiser and Bolinger (2022)
Sample is limited; few projects in sample have complete records of OpEx from 2000 to 2020; OpEx reported here do not include all operating costs.
Data from “Assessing Wind Power Operating Costs in the United States: Results From a Survey of Wind Industry Experts” (Wiser, Bolinger, and Lantz 2019) are used to
estimate all-in project OpEx for a representative project commissioned in 2021.
NREL | 28
Land-Based Wind Project Financial Assumptions
Parameter Nominal Value Real Value
Weighted-average cost of capital 5.37% 2.8%
Capital recovery factor 7.36% 5.62%
Fixed charge rate 7.7% 5.88%
The economic evaluation of wind energy investments in this analysis uses the fixed charge rate (FCR) method
from NRELs Annual Technology Baseline and Standard Scenarios web page: atb.nrel.gov
.
The FCR represents the amount of annual revenue required to pay the carrying charge as applied to the
CapEx on that investment during the expected project economic life and is based on the capital recovery
factor (CRF) but also reflects corporate income taxes and depreciation.
The analysis assumes the reference project operates for 25 years, a 5-year MACRS depreciation schedule,
and an inflation rate of 2.5%.
Additional financial assumption details are displayed in the Appendix.
NREL | 29
LCOE for Representative Land-Based Wind Plant
and Historical Data
Source: Wiser and Bolinger (2022)
Note: Yearly estimates reflect variations in installed cost, capacity factors, operational costs, cost of financing, and project life; includes accelerated depreciation but excludes
production tax credit.
Parameter Value
Wind turbine rating 3 MW
Capital expenditures $1,501/kW
Fixed charge rate (real) 5.88%
Operational expenditures $40/kW/yr
Net annual energy production 3,775
MWh/MW/yr
Calculated levelized cost of energy $34/MWh
NREL | 30
LCOE Breakdown for
Reference Land-Based Wind Plant
5.0
8.2
3.3
0.4
0.2
1.2
0.6
0.7
2.1
1.4
0.4
10.7
34
$0
$5
$10
$15
$20
$25
$30
$35
$40
Levelized Cost of Energy (2021 $/MWh)
Turbine CapEx (48%) Balance of System CapEx (15%)
Financial
CapEx (5%)
OpEx (32%)
NREL | 31
Range of LCOE Parameters for Land-Based Wind
Note: The reference LCOE reflects a representative industry LCOE. Changes in LCOE for a single variable can be understood by moving to the left or right along a specific variable.
Values on the x-axis indicate how the LCOE will change as a given variable is altered and all others are assumed constant (i.e., remain reflective of the reference project).
$20 $25 $30 $35 $40 $45 $50 $55 $60 $65 $70 $75
Project Design Life (years)
Discount Rate (nominal) [%]
Net Capacity Factor (%)
OpEx ($/kW/year)
CapEx ($/kW)
LCOE ($/MWh)
Key Parameters for LCOE Sensitivity Analysis
2,000
1,501 (reference)
1,350
40
60
30
43.1
2152
5.37 (reference)
6.34.46
1535 25
Reference LCOE = $34/MWh
4. Offshore Wind Energy
NREL | 33
2021 Market Average Offshore Wind Turbine and
Representative Wind Plant
Parameter Value
Wind turbine rating 8.0 MW
Rotor diameter 159 m
Hub height 102 m
Specific power 403 W/m
2
Wind plant capacity 600 MW
Number of turbines 75
Global capacity-weighted-average turbine rating
in 2021 was 7.4 MW, down slightly from 7.6 MW
in 2020 (Musial et al. 2022).
Representative wind plant parameters are held
constant with respect to 2020 Cost of Wind
Energy Review (Stehly and Duffy 2022).
Global capacity-weighted-average turbine rating, hub height, and rotor diameter for
offshore wind projects in 2021. Source: Offshore Wind Market Report: 2022 Edition
(Musial et al. 2022)
Representative turbine parameters and power curves
available on GitHub
NREL | 34
Offshore Wind Reference Wind Sites
and Wind Plant Performance
Parameter Fixed-
bottom
Floating Units
Water depth 34 739 m
Export cable length 50 36 km
Annual average wind
speed at 50 meters
8.43 7.67 m/s
Annual average wind
speed at hub height
9.05 8.24 m/s
Weibull k 2.1 2.1 factor
Shear exponent 0.1 0.1 #
Gross energy capture 5,081 4,205 MWh/MW
/yr
Gross capacity factor 58.0 48.0 %
Total losses 15.5 20.7 %
Net energy capture 4,295 3,336 MWh/MW
/yr
Net capacity factor 49.0 38.1 %
Wind resource of the United States, annual average wind speed at 100 meters above surface
level. Source: NREL (2017)
The fixed-bottom offshore wind reference project
represents near-term development in the U.S. Northeast.
The floating offshore wind reference site represents the
first leases in California.
NREL | 35
Turbine
Development and
Project Management
Substructure & Foundation
Electrical Infrastructure
Assembly and
Installation
Lease Price
Plant Commissioning
Decommissioning
Contingency
Construction Finance
Insurance During
Construction
33.6%
2.3%
12.8%
17.9%
10.5%
4.6%
0.9%
3.0%
9.5%
3.9%
0.9%
Turbine
33.6%
Balance of
System
48.2%
Soft Costs
18.2%
Fixed-bottom Offshore Wind System CapEx
Component Cost Breakdown
Parameter Value ($/kW)
Turbine
1,301
BOS
1,866
Development and project
management
91
Substructure and foundation
496
Electrical infrastructure
693
Assembly and installation
408
Lease price
178
Soft Costs
704
Plant commissioning
34
Decommissioning
117
Contingency
366
Construction finance
152
Insurance during construction
34
Total CapEx
3,871
NREL | 36
Turbine
Development and
Project Management
Substructure &
Foundation
Electrical Infrastructure
Assembly and
Installation
Lease Price
Plant Commissioning
Decommissioning
Contingency
Construction Finance
Insurance During
Construction
23.3%
1.6%
37.5%
13.4%
5.7%
3.2%
0.9%
1.8%
7.7%
4.0%
0.9%
Turbine
23.3%
Balance of
System
61.4%
Soft Costs
15.3%
Floating Offshore Wind System CapEx
Component Cost Breakdown
Parameter Value
($/kW)
Turbine
1,301
BOS
3,422
Development and project
management
91
Substructure and foundation
2,089
Electrical infrastructure
747
Assembly and installation
316
Lease price
178
Soft Costs
854
Plant commissioning
52
Decommissioning
101
Contingency
428
Construction finance
221
Insurance during construction
52
Total CapEx
5,577
NREL | 37
Fixed-Bottom and Floating Offshore Wind
OpEx Estimates
Public OpEx data are scarce, and estimates
vary among existing projects in Europe and
Asia.
Estimated fixed-bottom and floating OpEx
values are calculated with NRELs Offshore
Regional Cost Analyzer (ORCA) model
(Beiter et al. 2016) which varies in the
definition of OpEx scope when compared
with more recent trends and analyses.
Continued work to develop and validate
the open-source offshore OpEx model
Windfarm Operations & Maintenance cost-
Benefit Analysis Tool (WOMBAT) is
expected to improve current OpEx
estimating capabilities.
(follow model development on GitHub)
Parameter Fixed Value Floating Value
OpEx
($/kW-yr)
111 118
Projected U.S. offshore wind plant OpEx costs between 2021 and 2035. Source: Musial et al. (2022)
NREL | 38
Fixed-Bottom and Floating Offshore Wind
Project Financial Assumptions
The data used to calculate the weighted-average cost of capital (WACC) are collected by NREL based on
conversations with project developers and industry financiers and provides a basis for WACC assumptions for
the representative wind project in 2021.
The WACC, CRF, and FCR are given in nominal and real terms using the after-tax WACC discount rate of 5.29%
and 2.72%, respectively, a project design lifetime of 25 years, and a net present value depreciation factor of
86.9% (assuming a 5-year MACRS depreciation schedule).
Detailed financial assumptions are displayed in the Appendix.
Parameter Nominal Value Real Value
Weighted-average cost of capital 5.29% 2.72%
Capital recovery factor 7.30% 5.60%
Fixed charge rate 7.64% 5.82%
Note: The calculated weighted-average cost of capital for land-based wind is higher than offshore wind because it considers the influences of the production tax
credit and assumes a lower debt fraction.
NREL | 39
2021 Offshore Wind Reference Plant
LCOE Estimates
The LCOE values for the 2021 representative fixed-bottom and floating offshore
wind plants are estimated at $78/MWh and $133/MWh, respectively.
Calculated with the formulation presented in NRELs Annual Technology Baseline and
presented in Appendix.
Parameter Fixed-bottom 8.0-MW
Offshore Wind Turbine
Floating 8.0-MW
Offshore Wind Turbine
Units
Capital expenditures 3,871 5,577 $/kW
Fixed charge rate (real) 5.82 5.82 %
Operational expenditures 111 118 $/kW/yr
Net annual energy
production
4,295 3,336 MWh/MW/yr
Total LCOE 78 133 $/MWh
NREL | 40
Fixed-Bottom Offshore Wind Reference Plant
LCOE Component Cost Breakdown
17.6
1.2
0.0*
6.7
9.4
5.5
0.5
0.5
1.6
2.1
5.0
2.4
7.1
18.8
78
$0
$20
$40
$60
$80
Levelized Cost of Energy (2021 $/MWh)
OpEx
(33%)
Financial CapEx (14.6%)
Balance of System CapEx
(29.8%)
Turbine
(22.5%)
* Engineering Management cost small, but nonzero
NREL | 41
Floating Offshore Wind Reference Plant
LCOE Component Cost Breakdown
22.7
1.5
0.0*
36.5
13.0
5.5
3.1
0.9
1.8
3.9
7.5
0.9
9.1
26.3
133
$0
$20
$40
$60
$80
$100
$120
$140
Levelized Cost of Energy (2021 $/MWh)
* Engineering Management cost small, but nonzero
Balance of System CapEx (45.0%)
Financial CapEx (11.2%)
OpEx
(26.6%)
Turbine
(17.1%)
NREL | 42
$50 $60 $70 $80 $90 $100 $110 $120 $130 $140 $150 $160 $170 $180
Project Design Life (years)
Discount Rate (nominal) [%]
Net Capacity Factor (%)
OpEx ($/kW/year)
CapEx ($/kW)
Key Parameters for LCOE Sensitivity Analysis
Reference LCOE = $78/MWh
3,871
25
15
35
5.29
3.97
6.61
49.0
5,740
50.0
35.0
111
56
167
6,380
1,990
Range of LCOE Parameters for
Fixed-Bottom Offshore Wind Platform
Note: The reference LCOE reflects a representative industry LCOE. Changes in LCOE for a single variable can be understood by moving to the left or right along a
specific variable. Values on the x-axis indicate how the LCOE will change as a given variable is altered and all others are assumed constant (i.e., remain reflective of
the reference project).
NREL | 43
$50 $60 $70 $80 $90 $100 $110 $120 $130 $140 $150 $160 $170 $180
Project Design Life (years)
Discount Rate (nominal) [%]
Net Capacity Factor (%)
OpEx ($/kW/year)
CapEx ($/kW)
Key Parameters for LCOE Sensitivity Analysis
Reference LCOE = $133/MWh
15
5,351
35
25
5.29
6.61
3.97
38.0
50.0
35.0
118
59
177
6,971
4,183
Range of LCOE Parameters for
Floating Offshore Wind Platform
Note: The reference LCOE reflects a representative industry LCOE. Changes in LCOE for a single variable can be understood by moving to the left or right along a
specific variable. Values on the x-axis indicate how the LCOE will change as a given variable is altered and all others are assumed constant (i.e., remain reflective of
the reference project).
5. Distributed Wind Energy
NREL | 45
Distributed Wind Turbine Characteristics for
Residential, Commercial, and Large-Scale Projects
Parameter
Wind Turbine Class
UnitsResidential Commercial Large
Wind turbine rating 20 100 1,500 kW
Rotor diameter 12.4 27.6 77 m
Hub height 30 40 80 m
Specific power 166 167 322 W/m
2
Number of wind
turbines 1 1 1 #
Wind turbine classes are aligned with the Distributed Wind Energy Futures Study (McCabe et al. 2022).
NREL | 46
Distributed Wind Site Characteristics
and Performance
Parameter
Wind Turbine Class
UnitsResidential Commercial Large
Annual average wind speed at 50 m above surface
level
6 6 6 m/s
Annual average wind speed at hub height 5.58 5.81 6.42 m/s
Weibull k 2.0 2.0 2.0 factor
Shear exponent 0.14 0.14 0.14 #
Gross energy capture 2,916 3,217 3,759 MWh/MW/yr
Gross capacity factor 33.3 36.7 42.9 %
Losses 6.9 6.9 6.9 %
Availability 95 95 95 %
Total losses 11.5 11.5 11.5 %
Net energy capture 2,580 2,846 3,326 MWh/MW/yr
Net capacity factor 29.5 32.5 38 %
Residential and commercial wind turbines assume stall-regulated power curves; the large wind turbine assumes pitch-regulated power curve.
Power curve data available on https://github.com/NREL/turbine-models.
NREL | 47
Distributed Wind Project Component Cost Breakdown
and Estimated Operational Expenditures
Residential (20 kW) Commercial (100 kW) Large (1,500 kW)
Parameter
Wind Turbine Class
UnitsResidential Commercial Large
Wind turbine CapEx 2,575 2,530 2,589 $/kW
BOS CapEx 3,100 1,770 951 $/kW
Total CapEx 5,675 4,300 3,540 $/kW
OpEx 35 35 35 $/kW/yr
Turbine component cost estimates are derived from the Distributed Wind Market Report: 2022 Edition (Orrell et al. 2022).
BOS component cost estimates are obtained from the Land-based Balance of System Systems Engineering (LandBOSSE) model (Eberle et al. 2019) and presented in Bhaskar and Stehly (2021).
Because CapEx data are scarce for distributed wind projects, further cost details on the individual system components are not presented.
OpEx market data are not widely available for distributed wind projects; therefore, $35/kW/yr are assumed for each wind class.
58.8%
41.2%
Turbine
Balance of
System
45.4%
54.6%
Turbine
Balance of
System
73.1%
26.9%
Turbine
Balance of
System
NREL | 48
Distributed Wind Project Financial Assumptions
Parameter
Wind Turbine Class
Residential Commercial Large
Nominal Real Nominal Real Nominal Real
Weighted-average cost of capital (%) 4.69 2.13 4.69 2.13 4.69 2.13
Capital recovery factor (%) 6.87 5.2 6.87 5.2 6.87 5.2
Fixed charge rate (%) 7.76 5.88 7.16 5.42 7.16 5.42
The economic evaluation of wind energy investments in this analysis uses the fixed charge rate (FCR) method used in NRELs Annual
Technology Baseline and Standard Scenarios web page: atb.nrel.gov.
The FCR represents the amount of annual revenue required to pay the carrying charge as applied to the CapEx on that investment during
the expected project economic life and is based on the capital recovery factor (CRF) but also reflects corporate income taxes and
depreciation.
The analysis assumes the reference projects operate for 25 years; residential host-owned assumes a 20-year straight-line depreciation
schedule, and the commercial/industrial host-owned project assumes a 5-year MACRS depreciation schedule.
Additional financial assumption details are displayed in the Appendix.
NREL | 49
LCOE Breakdown for Reference
Distributed Wind Projects
Single-Turbine Residential
(20 kW)
Single-Turbine Commercial
(100 kW)
Single-Turbine Large
(1,500 kW)
58.6
70.6
13.6
143
$0
$20
$40
$60
$80
$100
$120
$140
$160
Wind
turbine
CapEx
BOS CapEx OpEx LCOE
Levelized Cost of Energy (2021 $/MWh)
48.1
33.7
12.3
94
$0
$20
$40
$60
$80
$100
$120
$140
$160
Wind
turbine
CapEx
BOS CapEx OpEx LCOE
Levelized Cost of Energy (2021 $/MWh)
42.2
15.5
10.5
68
$0
$20
$40
$60
$80
$100
$120
$140
$160
Wind
turbine
CapEx
BOS CapEx OpEx LCOE
Levelized Cost of Energy (2021 $/MWh)
6. References
NREL | 51
References
Beiter, P., W. Musial, A. Smith, L. Kilcher, R. Damiani, M. Maness, et al. 2016. A Spatial-Economic Cost Reduction Pathway Analysis for U.S. Offshore Wind Energy Development from 2015-2030.
Golden, CO: National Renewable Energy Laboratory. NREL/TP6A20-66579. https://www.nrel.gov/docs/fy16osti/66579.pdf
.
Bhaskar, Parangat, and Tyler Stehly. 2021. Technology Innovation Pathways for Distributed Wind Balance-of-System Cost Reduction. Golden, CO: National Renewable Energy Laboratory. NREL/TP-
5000-77452. https://www.nrel.gov/docs/fy21osti/77452.pdf
.
Bureau of Labor and Statistics. Undated. “CPI Inflation Calculator.” Accessed September 2022. https://www.bls.gov/data/#calculators
.
Dykes, K., M. Hand, T. Stehly, P. Veers, M. Robinson, E. Lantz. 2017. Enabling the SMART Wind Power Plant of the Future Through Science-Based Innovation. Golden, CO: National Renewable
Energy Laboratory. NREL/TP-5000-68123. https://www.nrel.gov/docs/fy17osti/68123.pdf
.
Eberle, Annika, Owen Roberts, Alicia Key, Parangat Bhaskar, and Katherine Dykes. 2019. NREL’s Balance-of-System Cost Model for Land-Based Wind. Golden, CO: National Renewable Energy
Laboratory. NREL/TP-6A20-72201. https://www.nrel.gov/docs/fy19osti/72201.pdf
.
Feldman, D., M. Bolinger, and P. Schwabe. 2020. Current and Future Costs of Renewable Energy Project Finance Across Technologies. Golden, CO: National Renewable Energy Laboratory. NREL/TP-
6A20-76881. https://www.nrel.gov/docs/fy20osti/76881.pdf
.
McCabe, Kevin, Ashreeta Prasanna, Jane Lockshin, Parangat Bhaskar, Thomas Bowen, Ruth Baranowski, Ben Sigrin, Eric Lantz. 2022. Distributed Wind Energy Futures Study. Golden, CO: National
Renewable Energy Laboratory. NREL/TP-7A40-82519. https://www.nrel.gov/docs/fy22osti/82519.pdf
.
Moné, C., M. Hand, M. Bolinger, J. Rand, D. Heimiller, J. Ho. 2017. 2015 Cost of Wind Energy Review. Golden, CO: National Renewable Energy Laboratory. NREL/TP-6A20-66861.
https://www.nrel.gov/docs/fy17osti/66861.pdf
.
Musial, W., P. Spitsen, P. Duffy, P. Beiter, M. Marquis, R. Hammond, and M. Shields. 2022. Offshore Wind Market Report: 2022 Edition. Washington, D.C.: U.S. Department of Energy. DOE/GO-
102022-5765.
https://www.energy.gov/sites/default/files/2022-09/offshore-wind-market-report-2022-v2.pdf.
National Renewable Energy Laboratory (NREL). 2017. “Wind Resource Maps and Data.”
https://www.nrel.gov/gis/wind-resource-maps.html.
National Renewable Energy Laboratory (NREL). (n.d.). “Annual Technology Baseline.” Accessed September 2022. https://atb.nrel.gov/
.
Orrell, A., K. Kazimierczuk, L. Sheridan. 2022. Distributed Wind Market Report: 2022 Edition. Washington, D.C.: U.S. Department of Energy. DOE/GO-102022-5764.
https://www.energy.gov/sites/default/files/2022-08/distributed_wind_market_report_2022.pdf.
NREL | 52
References
Short, W., D. J. Packey, and T. Holt. 1995. A Manual for the Economic Evaluation of Energy Efficiency and Renewable Energy Technologies. Golden, CO: National Renewable Energy Laboratory.
NREL/TP-462-5176. http://www.nrel.gov/docs/legosti/old/5173.pdf
.
Stehly, Tyler and Patrick Duffy. 2022. 2020 Cost of Wind Energy Review. Golden, CO: National Renewable Energy Laboratory. NREL/TP-5000-81209. https://www.nrel.gov/docs/fy22osti/81209.pdf
.
Stehly, T., P. Beiter, P. Duffy. 2020. 2019 Cost of Wind Energy Review. Golden, CO: National Renewable Energy Laboratory. NREL/TP-5000-78471. https://www.nrel.gov/docs/fy21osti/78471.pdf
.
Stehly, Tyler, and Philipp Beiter. 2019. 2018 Cost of Wind Energy Review. Golden, CO: National Renewable Energy Laboratory. NREL/TP-5000-74598.
https://www.nrel.gov/docs/fy20osti/74598.pdf
.
UL Solutions. Undated. “Wind Farm Design Software Developed on More Than 30 Years of Expertise.”
https://aws-dewi.ul.com/software/openwind/.
Wiser, R. and M. Bolinger. 2022. Land-Based Wind Market Report: 2022 Edition. Washington, D.C.: U.S. Department of Energy. DOE/GO-102022-5763.
https://www.energy.gov/sites/default/files/2022-08/land_based_wind_market_report_2202.pdf.
Wiser, R., M. Bolinger, and E. Lantz. 2019. “Assessing Wind Power Operating Costs in the United States: Results From a Survey of Wind Industry Experts.” Renewable Energy Focus 30: 4657.
https://doi.org/10.1016/j.ref.2019.05.003
.
7. Appendix
NREL | 54
Land-Based Wind Reference Project Details
Parameter Units Value Notes
Wind plant and reference site characteristics
Wind plant capacity
MW 200
Representative of commercial-scale projects
Number of turbines
67
Turbine rating
MW 3
"Land-Based Wind Market Report: 2022 Edition" (Wiser and Bolinger 2022)Rotor diameter
m 127
Hub height
m 95
Specific power
W/m2 237 Calculation
Cut-in wind speed
m/s 3
Typical turbine characteristics
Cut-out wind speed
m/s 25
Annual average wind speed at 50 meters
m/s 7.25 Reference site wind speed
Annual average wind speed at hub height
m/s 7.95
Between International Electrotechnical Class (IEC) class III (7.5 m/s) and IEC class II (8.5
m/s)
Weibull k factor
2.0
Shear exponent
0.143 Shear for neutral stability conditions
Altitude above mean sea level
m 450 Altitude at turbine foundation
Losses
% 15%
"Wind Vision" (U.S. Department of Energy 2015)
Availability
% 98%
Net energy capture
MWh/MW/yr 3,775
System Advisor Model (SAM) calculation
Net capacity factor
% 43.1%
NREL | 55
Land-Based Wind System CapEx Breakdown
CapEx
Total CapEx $/kW 1,501 "Land-Based Wind Market Report: 2022 Edition" (Wiser and Bolinger 2022)
Turbine $/kW 1,057
2015 Cost and Scaling Model
Rotor module $/kW 322
Blades $/kW 208
Pitch assembly $/kW 65
Hub assembly $/kW 49
Nacelle module $/kW 526
Nacelle structural assembly $/kW 106
Drivetrain assembly $/kW 210
Nacelle electrical assembly $/kW 170
Yaw assembly $/kW 39
Tower module $/kW 210
Balance of system $/kW 331
Land-based Balance of System Systems Engineering [LandBOSSE] (Eberle
et. al. 2019)
Development $/kW 24
Engineering and project
management
$/kW 10
Foundation $/kW 77
Site access and staging $/kW 41
Assembly and installation $/kW 42
Electrical infrastructure $/kW 136
Soft costs $/kW 113
Construction finance $/kW 23 Project construction over 3 years
Contingency $/kW 90 6% of total CapEx
Parameter Units Value Notes
NREL | 56
Land-Based Wind OpEx and Financing Terms
OpEx
Total OpEx $/kW/year 40 Assessing Wind Power Operating Costs in the United States (Wiser et al. 2019)
Financials
Project design life Years 25 Project life for Government Performance and Reporting Act (GPRA) reporting
Tax Rate (combined state and federal) % 25.7%
2022 Annual Technology Baseline (NREL’s Annual Technology Baseline and
Standard Scenarios web page: atb.nrel.gov)
Inflation rate % 2.5%
Interest during construction (nominal) % 3.11%
Land-Based Wind Market Report: 2022 Edition (Wiser and Bolinger 2022)
Construction finance factor % 102%
Calculation
Debt fraction % 48.5%
Lawrence Berkeley National Laboratory 2021 financial analysis
Debt interest rate (nominal) % 3.11%
Return on equity (nominal) % 8.25%
Weighted-average cost of capital [WACC] (nominal;
after-tax) % 5.37%
Calculation
WACC (real; after-tax) % 2.80%
Capital recovery factor (nominal; after-tax) % 7.36%
Capital recovery factor (real; after-tax) % 5.62%
Depreciable basis % 100% Simplified depreciation schedule
Depreciation schedule 5-year MACRS
Modified Accelerated Cost Recovery System (MACRS) is standard for U.S. wind
projects
Depreciation adjustment (NPV) % 86.6%
Calculation
Project finance factor % 105%
FCR (nominal) % 7.70%
FCR (real) % 5.88%
Levelized cost of energy $/MWh 34 Calculation
Parameter Units Value Notes
NREL | 57
Fixed-Bottom Offshore Wind
Reference Project Details
Parameter Units Value Notes
Wind plant and reference site characteristics
Wind plant capacity
MW 600
Representative of commercial-scale projects
Number of turbines
Number 75
Calculation
Turbine rating
MW 8
Informed by Offshore Wind Market Report: 2022 Edition (Musial et al. 2022)Rotor diameter
m 159
Hub height
m 102.1
Specific power
W/m2 403
Calculation
Water depth
m 34
Representative fixed-bottom offshore site for COE Review
Substructure type
Monopile
Distance from shore
km 50
Cut-in wind speed
m/s 3
Cut-out wind speed
m/s 25
Average annual wind speed at 50 m
m/s 8.4
Average annual wind speed at hub height
m/s 9.0
Shear exponent
0.10
Weibull k
2.1
Total system losses
% 15.5%
Offshore Regional Cost Analyzer (ORCA) (based on Beiter et al. 2016)
Gross energy capture
MWh/MW/year 5,081
Calculation
Net energy capture
MWh/MW/year 4,295
Gross capacity factor
% 58.0%
Offshore Regional Cost Analyzer (ORCA) (based on Beiter et al. 2016)
Net capacity factor
% 49.0%
NREL | 58
Fixed-Bottom Offshore Wind
System CapEx Breakdown
Parameter Units Value Notes
CapEx
Total CapEx
$/kW 3,871
Turbine
$/kW 1,301
Informed by Offshore Wind Market Report: 2022 Edition (Musial et al. 2022)Rotor nacelle assembly
$/kW 1,119
Tower
$/kW 182
Balance of System
$/kW 1,866
BOS Costs computed with ORBIT (Nunemaker et al. 2020)
Development
$/kW 89
Project management
$/kW 2
Substructure and foundation
$/kW 496
Substructure
$/kW 194
Foundation
$/kW 302
Port and staging, logistics, transportation
$/kW 0
Electrical infrastructure
$/kW 693
Array cable system
$/kW 117
Export cable system
$/kW 387
Grid connection
$/kW 188
Assembly and installation
$/kW 408
Turbine installation
$/kW 222
Substructure and foundation installation
$/kW 186
Soft Costs
$/kW 704
Soft Costs computed using same methodology as ORCA (Beiter et al. 2016)
Insurance during construction
$/kW 34
Decommissioning bond
$/kW 117
Construction finance
$/kW 152
Sponsor contingency
$/kW 366
Procurement contingency
$/kW 133
Installation contingency
$/kW 233
Project completions / commissioning
$/kW 34
NREL | 59
Fixed-Bottom Offshore Wind
OpEx and Financing Terms
Parameter Units Value Notes
OpEx
Total OpEx $/kW/year 111
Offshore Regional Cost Analyzer (ORCA) (based on Beiter et al. 2016)
Operations (pretax) $/kW/year 30
Maintenance $/kW/year 81
Financials
Project design life Years 25 Offshore wind project life for GPRA reporting
Tax Rate (combined state and federal) % 26%
Feldman et al. 2020 and NREL's Annual Technology Baseline, updated with data from
industry partners
Inflation rate % 2.5%
Debt fraction % 67%
Debt interest rate (nominal) % 4.0%
Return on equity (nominal) % 10.0%
WACC (nominal; after-tax) % 5.3%
Calculation
WACC (real; after-tax) % 2.7%
Capital recovery factor (nominal; after-tax) % 7.3%
Capital recovery factor (real; after-tax) % 5.6%
Depreciable basis % 100% Simplified depreciation schedule
Depreciation schedule 5-year MACRS Standard for U.S. wind projects
Depreciation adjustment (NPV) % 86.8%
Calculation
Project finance factor % 105%
FCR (nominal) % 7.6%
FCR (real) % 5.8%
NREL | 60
Floating Offshore Wind Reference Project Details
Parameter Units Value Notes
Wind plant and reference site characteristics
Wind plant capacity
MW 600
Representative of commercial-scale projects
Number of turbines
Number 75
Calculation
Turbine rating
MW 8
Informed by Offshore Wind Market Report: 2022 Edition (Musial et al. 2022)Rotor diameter
m 159
Hub height
m 102.1
Specific power
W/m2 403
Calculation
Water depth
m 739
Representative Floating site for Cost of Wind Energy Review
Substructure type
Semisubmersible
Distance from shore
km 36
Cut-in wind speed
m/s 3
Cut-out wind speed
m/s 25
Average annual wind speed at 50 m
m/s 7.7
Average annual wind speed at hub height
m/s 8.2
Shear exponent
0.10
Weibull k
2.1
Total system losses
% 20.7%
Offshore Regional Cost Analyzer (ORCA) (based on Beiter et al. 2016)
Gross energy capture
MWh/MW/year 4,205
Calculation
Net energy capture
MWh/MW/year 3,336
Gross capacity factor
% 48.0%
Offshore Regional Cost Analyzer (ORCA) (based on Beiter et al. 2016)
Net capacity factor
% 38.1%
NREL | 61
Floating Offshore Wind System CapEx Breakdown
Parameter Units Value Notes
CapEx
Total CapEx
$/kW 5,577
Turbine
$/kW 1,301
Informed by Offshore Wind Market Report: 2022 Edition (Musial et al. 2022)Rotor nacelle assembly
$/kW 1,119
Tower
$/kW 182
Balance of System
$/kW 3,422
BOS Costs computed with ORBIT (Nunemaker et al. 2020)
Development
$/kW 89
Project management
$/kW 2
Substructure and foundation
$/kW 2,089
Substructure
$/kW 1,353
Foundation
$/kW 736
Port and staging, logistics, transportation
$/kW 0
Electrical infrastructure
$/kW 747
Array cable system
$/kW 218
Export cable system
$/kW 339
Grid connection
$/kW 191
Assembly and installation
$/kW 316
Turbine installation
$/kW 0
Substructure and foundation installation
$/kW 0
Lease price
$/kW 178
Soft Costs
$/kW 854
Soft Costs computed using same methodology as ORCA (Beiter et al. 2016)
Insurance during construction
$/kW 52
Decommissioning bond
$/kW 101
Construction finance
$/kW 221
Sponsor contingency
$/kW 428
Procurement contingency
$/kW 225
Installation contingency
$/kW 203
Project completions / commissioning
$/kW 52
NREL | 62
Floating Offshore Wind OpEx and Financing Terms
Parameter Units Value Notes
OpEx
Total OpEx $/kW/year 118
Offshore Regional Cost Analyzer (ORCA) (based on Beiter et al. 2016)
Operations (pretax) $/kW/year 30
Maintenance $/kW/year 87
Financials
Project design life Years 25 Offshore wind roject life for GPRA reporting
Tax Rate (combined state and federal) % 26%
Feldman et al. 2020 and NREL's Annual Technology Baseline, updated with
data from industry partners
Federal % 21%
State % 4.7%
Inflation rate % 2.5%
Debt fraction % 67%
Debt interest rate (nominal) % 4.0%
Return on equity (nominal) % 10.0%
WACC (nominal; after-tax) % 5.3%
Calculation
WACC (real; after-tax) % 2.7%
Capital recovery factor (nominal; after-tax) % 7.3%
Capital recovery factor (real; after-tax) % 5.6%
Depreciable basis % 100% Simplified depreciation schedule
Depreciation schedule 5 year MACRS Standard for U.S. wind projects
Depreciation adjustment (NPV) % 86.8%
Calculation
Project finance factor % 105%
FCR (nominal) % 7.6%
FCR (real) % 5.8%
NREL | 63
Distributed Wind Reference Project Details
Parameter Units
20-kW
Value
100-kW
Value
1,500-kW
Value
Notes
Wind plant characteristics
Wind plant capacity
kW 20 100 1500
Representative of residential distributed wind project
Number of turbines
1 1 1
Turbine rating
kW 20 100 1500
"Assessing the Future of Distributed Wind: Opportunities for Behind-the Meter Projects."
(Lantz et. al., 2016)
Rotor diameter
m 12.4 27.6 77
Hub height
m 30 40 80
Specific power
W/m2 166 167 322 Calculation
Cut-in wind speed
m/s 3 3 3
Typical turbine characteristics
Cut-out wind speed
m/s 20 25 25
Annual average wind speed at 50
meters
m/s 6.00 6.00 6.00 Reference site wind speed
Annual average wind speed at
hub height
m/s 5.58 5.81 6.42 International Electrotechnical Commission (IEC) class IV
Weibull k factor
N/a 2.0 2.0 2.0
Shear exponent
N/a 0.143 0.143 0.143 Shear for neutral stability conditions
Altitude above mean sea level
m 0 0 0 Altitude at turbine foundation
Losses
% 7% 7% 7%
Informed by "Competitiveness Improvement Project"
(https://www.nrel.gov/wind/competitiveness-improvement-project.html)
Availability
% 95% 95% 95%
Net energy capture
kWh/kW/yr 2,580 2,846 3,326
Calculation in Openwind (UL website (undated): https://aws-
dewi.ul.com/software/openwind/)
Net capacity factor
% 29.5% 32.5% 38.0%
NREL | 64
Distributed Wind System
CapEx, OpEx, and Financials Breakdown
CapEx
Total CapEx $/kW 5,675 4,300 3,540
Turbine $/kW 2,575 2,530 2,589
"2019 Distributed Wind Data Summary" (Orrell et. al., 2020)
Balance of system $/kW 3,100 1,770 951
"NREL’s Balance-of-System Cost Model for Land-Based Wind" (Eberle et. al., 2019)
OpEx
Total OpEx $/kW/year 35 35 35 "Assessing the Future of Distributed Wind: Opportunities for Behind-the Meter Projects" (Lantz et. al., 2016)
Financials
Project design life Years 25 25 25 Project life for Government Performance and Reporting Act (GPRA) reporting
Tax Rate (combined state and federal) % 25.7% 25.7% 25.7%
2021 Annual Technology Baseline (NREL’s Annual Technology Baseline and Standard Scenarios web page:
atb.nrel.gov)
Inflation rate % 2.5% 2.5% 2.5%
Debt fraction % 60% 60% 60%
"Assessing the Future of Distributed Wind: Opportunities for Behind-the Meter Projects" (Lantz et. al., 2016)
Debt interest rate (nominal) % 3.11% 3.11% 3.11%
Lawrence Berkeley National Laboratory 2021 financial analysis
Return on equity (nominal) % 8.25% 8.25% 8.25%
WACC (nominal; after-tax) % 4.69% 4.69% 4.69%
Calculation
WACC (real; after-tax) % 2.13% 2.13% 2.13%
Capital recovery factor (nominal; after-
tax) % 6.87% 6.87% 6.87%
Capital recovery factor (real; after-tax) % 5.20% 5.20% 5.20%
Depreciable basis % 100% 100% 100% Simplified depreciation schedule
Depreciation schedule N/a
20-year
straight line 5-year MACRS 5-year MACRS
Depreciation adjustment (NPV) % 62.6% 88.2% 88.2%
Calculation
Project finance factor % 113% 104% 104%
FCR (nominal) % 7.76% 7.16% 7.16%
FCR (real) % 5.88% 5.42% 5.42%
Levelized cost of energy $/MWh 143 94 68 Calculation
Parameter Units 20-kW Value 100-kW Value
1,500-kW
Value
Notes
www.nrel.gov
Photo from iStock-627281636
Thank You
This work was authored by the National Renewable Energy Laboratory, operated by Alliance for
Sustainable Energy, LLC, for the U.S. Department of Energy (DOE) under Contract No. DE-AC36-
08GO28308. Funding provided by U.S. Department of Energy Office of Energy Efficiency and Renewable
Energy Wind Energy Technologies Office. The views expressed in the article do not necessarily represent
the views of the DOE or the U.S. Government. The U.S. Government retains and the publisher, by
accepting the article for publication, acknowledges that the U.S. Government retains a nonexclusive,
paid-up, irrevocable, worldwide license to publish or reproduce the published form of this work, or
allow others to do so, for U.S. Government purposes.