1
Committee:
Date:
Planning Application Sub-Committee
11 June 2024
Subject:
Change of use of existing deep level tunnels (Sui Generis)
to visitor and cultural attraction (Use Class F1(b)(c)),
including bar (Sui Generis); demolition and reconstruction
of existing building at 38-39 Furnival Street; redevelopment
of 40-41 Furnival Street, for the principal visitor attraction
pedestrian entrance at ground floor, with ancillary retail at
first and second floor levels and ancillary offices at third
and fourth levels, excavation of additional basement levels
at 40-41 Furnival Street and 38-39 Furnival Street, and
widening of lift shaft at 38-39 Furnival Street; creation of
new, pedestrian entrance at 31-33 High Holborn, to
provide secondary visitor attraction entrance (including
principal bar entrance), deepening of lift shaft at 31-33
High Holborn; provision of ancillary cycle parking,
substation, servicing and plant, and other associated
works (Duplicate application submitted to the London
Borough of Camden as the site area extends across the
borough boundary). Re-consultation: Due to amended
details (Duplicate application submitted to the London
Borough of Camden as the site area extends across the
borough boundary).
Public
Ward: Farringdon Without
For Decision
Registered No: 23/01322/FULMAJ
Registered on:
01 December 2023
Conservation Area: Chancery Lane
Listed Building: No
2
Summary
Existing site
The site is located in the northwest of the City to the south of High Holborn. It
comprises below and above ground level elements. The underground element of the
application site consists of a network of tunnels (formally named the Kingsway
Tunnels) that run underneath High Holborn and cross the City of London and the
London Borough of Camden boundaries. The tunnels are managed by British Telecom
who are responsible for their maintenance. Above ground, the application site
comprises three buildings. Two buildings are located within the City of London
boundary at 38-39 and 40-41 Furnival Street and the third is located in the London
Borough of Camden at 31-33 High Holborn, accessed via Fulwood Place.
The existing building at 38-39 Furnival Street forms part of the tunnels access, hosting
a goods shaft and various ventilation ducts serving the eastern part of the tunnels and
is currently not in use given the vacant nature of the application site. The building at
40-41 Furnival Street is in office use.
Proposals
The application proposes to change the use of the existing deep-level subterranean
tunnels (Sui Generis) to a visitor and cultural attraction (Use Class F1 (b),(c)) including
a bar (Use Class Sui Generis). The demolition and reconstruction of the existing
vacant building at 38-39 Furnival Street and offices at 40-41 Furnival Street is being
proposed in order to link the two buildings internally and use the ground floor as the
principal entrance to the cultural attraction. The new buildings would also provide
ancillary retail space, including a gift shop at the first and second floor levels and
ancillary office accommodation, at the fourth level, to be used by staff. Public realm
improvements, including a shared surface and widening of the pavement in front of
the principal entrance at Furnival Street are proposed.
A duplicate application has been submitted to the London Borough of Camden as the
site area extends across the borough boundary. A secondary pedestrian entrance to
the deep-level tunnels would be retained at 31-33 High Holborn via Fulwood Place
(falling within LB Camden boundary) and upgraded to form the main entrance to the
proposed bar and an additional emergency exit.
The existing and proposed floorspace for different parts of the site is set out in the
following table:
3
Schedule of Areas
sqm (GIA)
Existing
Proposed
Difference
194
942
+ 748
1,229
1,525
+ 296
329
329
0
7,829
7,829
0
9,581
10,625
+ 1,044
The following table provides the proposed GEA (Gross External Area) and GIA (Gross
Internal Area) figures split between the two Local Planning Authorities. Approximately
71% of the site area created by the proposed development belongs within the City’s
boundaries.
GEA
GIA
Level
m2
m2
COL
(GIA)
Camden(GIA)
38-41 Furnival Street
3,020
2,467
2,467
0
Fulwood Place
386
329
0
329
Tunnel Network
9,828
7,829
5,111
2,718
TOTAL
13,234
10,625
7,578
3,047
Consultations
On the 10
th
January 140 letters were sent to residential properties in addition to site
notices posted on different locations around the proposed main and secondary
entrances to the site. Following some minor updates and amendments to the proposed
scheme a 14 days re-consultation round was carried out in April 2024.
A total of 57 letters of support have been received supporting the efforts of the proposal
to utilise existing infrastructure by embracing and preserving the history of Kingsway
Tunnels, boosting the local economy by bringing footfall in the area, creating new jobs
and overall, creating a benchmark development of national importance.
4
A total of 24 letters of objection have been received, with the key themes of objections
being residential and business amenity, traffic and highways, and the harm to the
conservation area.
Two neutral responses have been received with comments made about noise and
traffic.
A total of 12 statutory responses have been received none of which were objecting to
the proposed development. Given the somewhat unique nature of the site, the
subterranean layout and the long underground distances London Fire Brigade have
indicated various measures that would need to be considered post planning stage.
While there is no formal objection to the scheme under the Planning Act, it has been
considered that further details of the fire strategy would only be known at the
Qualitative Design Review (QDR) processes and therefore the applicant has made
commitments to actively consult with London Fire Brigade and other emergency
services to addresses all matters raised post planning application stage (i.e. under
Building Regulations).
From the above, nine were received during the first round of formal public consultation.
The second round of public consultation was carried out following receipt of
amendments to the proposals, mainly with updates to the transport assessment and
servicing plan. Only one new representation has been received following the proposal
updates from the Transport for London Spatial Planning team which did not raise any
objections to the proposed development.
The representations holding planning material consideration have been addressed in
the report and relevant conditions have been recommended wherever necessary.
Loss of office
The planning application proposes the loss of office space at 40-41 Furnival Street in
order to provide additional ancillary space for the operation of the proposed cultural
use. In addition to the submitted Planning Statement supporting information for the
proposed loss has been provided over the course of the application. While limited
Viability Assessment documentation has been submitted as part of the proposal, the
loss of the modest office has been weighed against the exceptional re-use of the
adjoining heritage asset (38-39 Furnival Street and the existing tunnels), the inherent
requirement of 40-41 Furnival Street for access/ancillary space and the wider
economic benefits the cultural use would bring to the City as a whole. Whilst the Local
Plan generally resists the loss of office floorspace, the scale of the loss on this site
(1,229sqm) would not prejudice the overall supply of office space in the City, nor
prejudice the potential for future site amalgamation or result in the loss of existing stock
for which there is demand or longer-term viable need. The proposed cultural and visitor
use would not compromise the primary business function of the City as it would provide
alternative complementary activities to the City’s business function offering a unique
experience for its workers, residents and visitors, and add a significant cultural supply
5
to the City’s stock meeting Destination City’s aspirations. It is considered that the loss
of office floorspace would therefore be acceptable in this instance.
Cultural Use
The Local Plan and London Plan supports the delivery of cultural uses. The proposal
would include the provision for permanent and temporary cultural exhibition spaces to
bring a new dynamic to the City and facilitate a 7/7 City, increasing footfall and
becoming an inclusive destination. The proposal would assist in achieving the City’s
aspirations for Destination City that focuses on enhancing the leisure and cultural offer
in the Square Mile and increase its appeal to existing audiences by creating fun,
inclusive, innovative, and sustainable ecosystems. The proposed permanent ‘Heritage
Experience’ would directly reference the historic tapestry of the City and the flexible
exhibition spaces, known as ‘The Streets’, would provide a unique and distinctive
space for cultural events within the Square Mile. The proposed bar would further
facilitate a 7/7 City and represent a complimentary use to the City’s main function
although it is noted that this element is located with the London Borough of Camden.
In addition to the above, the development would also bring about a series of social
benefits including the provision of enhanced access for disabled people, free school
trips, discounted tickets for special groups, training programmes, and opportunities to
engage with the local community to shape the design of the exhibitions. Is considered
to be an enhancement to the City's cultural provision and provide significant public
benefit to residents, workers, and visitors.
Design and Heritage
The disposition of the final massing and bulk has followed a design-led approach
considering macro and local townscape impacts with multiple pre-application
negotiations to mitigate adverse impacts on surround heritage assets. In respect of
massing, height and materiality, the distinctive sense of separate buildings, materials,
the celebration of industrial heritage and intended quality would introduce a well-
considered, refined, neighbourly architectural set piece. The bold architectural
expression would reflect the unique cultural use of the buildings and the subterranean
tunnel network.
The proposal would preserve the historic and rarity interest of the Kingsway Tunnels
as a non-designated heritage asset and any harm which arises as a result of the
development would be mitigated by the improvement to the accessibility and visibility
of this currently unknown heritage asset to a wide public audience.
Public Access and Inclusivity
The tunnels form an existing infrastructure which the proposed development seeks to
utilise. Accessibility standards were not included in their design at the time of their
construction given the original intent of the structures. The proposal seeks to retain
and restore the infrastructure without any construction works taking place in the tunnel
network other than general fit-out works. Providing a highly accessible environment
6
for the site therefore comes with its own challenges. The proposed cultural use would
offer step-free access along the site and provisions have been made for ground level
accessible cycle space and a parking space for staff arriving on outdoor scooters.
Large passenger lifts would provide access to the cultural space and the gift shop at
the first and second floors and separate lifts would serve the upper levels including the
staff accommodation at level four which is designed with accessible standards. The
arrival to the site has been also considered, with improvements to the public realm
focusing on pedestrian environment and capacity of the street. Details of the
accessibility and inclusivity of the cultural development as well as the operational
details for the site would be secured by conditions and Section 106 obligations to
ensure highest levels of accessibility would be applied.
Public Realm
The proposal aims to deliver public realm works to improve the pedestrian
environment and the capacity of Furnival Street. It sets the building line of No. 40-41
Furnival Street back to provide an inside foyer and increase the footway width of the
main entrance. The original submission has been revised following Transport Officer’s
comments to align with the City’s Healthy Steet scheme, specifically under the Fleet
Street Area, Healthy Steets Plan which incorporates Chancery Lane neighbourhood
improvements including Furnival Street. Improvement works would be subject to a
design scheme by the Highways Authority which should take into consideration a
shared surface along Furnival Street, parking arrangements and cycle lane revisions,
provision of accessible seating available along the approaches to the development,
repair works and greenery. Under the Healthy Streets initiative, the Local Authority
would potentially consider time closures of Furnival Street to restrict vehicle access
and create a more welcome and safer environment for pedestrians as well as
maximising the capacity of the local street for the increased footfall generated by the
proposed development, however this would be subject to further consultation with
residents and local occupiers.
Transport
In term of public transport provision, the site has the highest level of Public Transport
Accessibility Level (PTAL) of 6B. The submitted Transport Assessment (TA) in support
of this application, included details on the trip generation and modal splits. The
proposal aims to mitigate its impacts by including various public realm improvement
works along the Furnival Street, in conjunction with the City of London’s Healthy Street
aspirations for the area, as discussed above. The general aim of the Healthy Street
plan for Furnival Street is to redesign the street and manage access to make streets
more accessible, engaging and providing safe places for people to walk, cycle and
spend time. These highway improvements are to be secured through S278 works and
its scope via the S106 legal agreement.
The proposal includes a compliant number of 12 long stay cycle parking spaces for
the proposed cultural use and an additional 2 spaces for the bar should be provided,
however short stay cycle parking for visitors would have to be provided on the public
7
highway given the constraints of the site. Considering the London Plan and Local
policy, officers consider that for this type of use, short cycle parking spaces standards
are of a provision of 1 space per 100sqm, thus 125 cycle parking spaces would be
required. Due to the constraints of the development located on the Furnival Street and
the large number of spaces required, it is not possible to provide these spaces within
the development itself. Nevertheless, the application includes a S106 legal agreement
to secure the provision of cycle parking spaces on the public highway, including
improvements of the cycle infrastructure in the vicinity of this development. Over the
course of the application, it was agreed to split the visitor cycle parking between the
two LPAs, with LBC agreeing to provide 20% of the total requirement in their highways.
Finally, the Construction Logistics Plans (CLP) and Delivery and Servicing Plans
(DSP) are proposed to be developed in accordance with TfL guidance and the latest
standards and as such both plans would be monitored throughout the demolition and
construction phase and thereafter when the development becomes operational.
Daylight/Sunlight and Lighting Scheme
With regard to daylight sunlight impacts, the surrounding residential and commercial
buildings have been assessed against the existing and proposed massing of the
proposed buildings. In particular 1 to 6 Dyers Buildings, residential properties
immediately to the east of the site, have been assessed with other properties
surrounding properties being given a lesser weight in the assessment due to their non-
domestic nature and windows not orientated within 45 degrees of the uplift of the
proposed development. 1-3 Dyers Building assessment results demonstrate a
moderate to high level of BRE compliance. Where there are technical breaches of the
BRE guidelines, these can be attributed to the low existing levels of daylight currently
received by the neighbouring residential properties assessed, which would be
sensitive to proportionately higher percentage reductions. 4 6 Dyers Buildings have
been included in later responses on daylight sunlight assessments and showed BRE
compliance similar to that of the above.
While the application proposes to demolish the existing buildings at Furnival Street,
the proposal seeks to redevelop the buildings in-line with the existing massing and
height. This has been intentionally designed as such to ensure a limited impact on the
amenity of surrounding neighbours and this is reflected in the very modest alterations
to daylight/sunlight within the submitted assessment.
Overall, the daylight and sunlight available is considered to be sufficient and
appropriate to the context, and acceptable living standards would be maintained. As
such, the overall impact (including the degree and extent of harm) is not considered
to be such that it would conflict with any of the relevant development plan policies.
Sustainability
The Local Plan and London Plan requires development to support environmental,
economic, and social sustainability. The Plans also require that developments are
8
designed to maximise operational efficiency and minimise associated carbon
emissions throughout the buildings’ lifetimes.
The proposed development is a retrofit led proposal to bring a historic and well-storied
asset, currently under-utilised, back into common usage of high cultural value.
Demolition is mostly limited to Furnival Street where the practicalities of construction
and accommodating services required make retention unviable. This proposed
change of use does come with its own challenges. Built as air-raid shelter and
telephone exchange, the tunnels were not designed for ease of access or extended
occupation by large numbers of people. The access, ventilation, and cooling
requirements to facilitate the proposed visitor numbers have been carefully designed
to optimise energy efficiency and minimise waste heat but still come at a high carbon
cost with large amounts of equipment, spanning the full length of the tunnels. The
potential audio-visual equipment associated with the immersive cultural offering has
been demonstrated to increase the carbon impact of the development significantly.
However, the new building at Furnival Street has been designed following circular
principles, with future flexibility, maintenance and disassembly in mind.
CIL and Planning Obligations
The scheme would provide benefits through CIL for improvements to the public realm,
housing and other local facilities and measures. That payment of CIL is a local finance
consideration which weighs in favour of the scheme. In addition to general planning
obligations there would be site specific measures secured in the S106 Agreement.
Conclusion and Recommendation
The proposal has been assessed in accordance with the relevant statutory duties and
having regard to the development plan (i.e., the London Plan and Local Plan) and
relevant policies and guidance, SPDs and SPGs, relevant advice including the NPPF,
the draft Local Plan and considering all other material considerations.
It is almost always the case that where major development proposals come forward
there is at least some degree of non-compliance with planning policies, and in arriving
at a decision, it is necessary to assess all the policies and proposals in the plan and
to come to a view as to whether in the light of the whole plan the proposal does or
does not accord with it.
Paragraph 11 of the NPPF sets out that there is presumption in favour of sustainable
development. For decision taking that means approving development proposals that
accord with an up to date development plan without delay.
In this case, the proposals are considered to be in accordance with the development
plan as a whole. In addition, the Local Planning Authority must determine the
application in accordance with the development plan unless other material
considerations indicate otherwise.
It is the view of officers that as the proposal complies with the Development Plan when
considered as a whole and taking into account all material planning considerations, it
is recommended that planning permission be granted subject to all the relevant
9
conditions being applied and Section 106 obligations being entered into in order to
secure public benefits and minimise the impact of the proposal.
10
Recommendation
1. That, subject to the execution of a planning obligation or obligations in respect
of the matters set out under the heading ‘Planning Obligations’ the Planning
and Development Director be authorised to issue a decision notice granting
planning permission for the above proposal in accordance with the details set
out in the attached schedule;
2. That your officers be instructed to negotiate and execute obligations in respect
of those matters set out in "Planning Obligations" under Section 106 of the
Town and Country Planning Act 1990 and any necessary agreements under
Sections 278 and 38 of the Highway Act 1980 in respect of those matters set
out in the report;
Or;
3. In the event that a legal agreement satisfactorily securing cross boundary
obligations is not completed within 12 months of the date of the resolution
officers be instructed to REFUSE permission for the substantive reason that the
scheme fails to mitigate the adverse impacts noted within the officer report and
is therefore contrary to the policies contained within the Development Plan.
11
12
Image 1: View looking north down Furnival Street
13
Image 2: View looking north across High Holborn towards 31-33 High Holborn
14
Image 3: Existing equipment with in the Kingsway Tunnels
15
Image 4: Existing canteen with in the Kingsway Tunnels
16
Image 5: Visual of proposed development looking south
Image 6: Visual of proposed Furnival Street entrance
17
Image 7: Visual of proposed heritage exhibition
Image 8: Visual of proposed bar
18
APPLICATION COVER SHEET
38-41 Furnival Street
TOPIC
INFORMATION
1. HEIGHT
EXISTING
PROPOSED
AOD Heights:
39 Furnival Street: +32.25
AOD
40 Furnival Street: +43.89
AOD
Fulwood Place: +49.09
AGL Heights:
39 Furnival Street: 12.4m
40 Furnival Street: 24m
Fulwood Place: 27.5m
AOD Heights:
39 Furnival Street: +35.63
40 Furnival Street: +41.75
Fulwood Place: +49.09
AGL Heights:
39 Furnival Street: 15.8m
40 Furnival Street: 21.95m
Fulwood Place: 27.5m
2. FLOORSPACE GIA
(SQM)
USES
EXISTING
PROPOSED
Class F1
(Visitor
Attraction)
0
10,341
Sui Generis
(Bar)
0
248
Sui Generis
(Tunnels)
8,352
0
Class E
(Office)
1,229
0
TOTAL
9,581
TOTAL:
10,625
TOTAL UPLIFT:
1,044
3. OFFICE PROVISION
IN THE CAZ
Existing: 1,229 sqm
Proposed: 0 sqm
Office uplift: -1,229 sqm
4. EMPLOYMENT
NUMBERS
EXISTING
PROPOSED
Circa. 65
Circa. 85
5. VEHICLE/CYCLE
PARKING
EXISTING
PROPOSED
Car parking
spaces
0
Car parking
spaces
0
19
Accessible
car parking
1
Accessible car
parking
1
Cycle long
stay
0
Cycle long stay
14
Cycle short
stay
7
Cycle short stay
125
Lockers
0
Lockers
Staff: 18
small
lockers
Visitors: 9
large
object
lockers / 18
small
lockers
Showers
0
Showers
Staff: 2
Changing
facilities
0
Changing facilities
Staff: 2
Visitors: 1
6. HIGHWAY LOSS /
GAIN
No loss or gain of highway proposed.
7. PUBLIC REALM
S278 agreement to secure improve pedestrian environment and
capacity of Furnival Street, to include a shared surface.
8. STREET TREES
EXISTING
PROPOSED
0
0
9. SERVICING
VEHICLE TRIPS
EXISTING
PROPOSED
N/A
8 deliveries on a typical day and
up to 14 vans during times
when exhibition set up is required.
10. SERVICING HOURS
All delivery activity will take place outside of opening hours and
predominantly between 20:00-22:00.
11. RETAINED FABRIC
90% of total site by area (Furnival St., Tunnels, & Fulwood Place)
0% of Furnival Street by area
14.2 m3 of brick, 1.4m3 of precast louvres (subject to condition)
20
12. OPERATIONAL
CARBON EMISSION
SAVINGS
Improvements against Part L 2021: 41.4% (30.7 tCO2)
GLA requirement: 35 %
13. OPERATIONAL
CARBON
EMISSIONS
B6 & B7 = 1,090 kgCO2e/m2
11,582,588 kgCO2e
Based on medium scenario as set out in Sustainability section
14. EMBODIED
CARBON
EMISSIONS
PROJECT LIFE CYCLE EMISSIONS COMPARED TO GLA
RETAIL BENCHMARKS (No benchmarks available for cultural
buildings)
Total upfront embodied carbon 7,911.8 tonnes CO
2
e /
745 kgCO
2
e per sqm
15. WHOLE LIFE-
CYCLE CARBON
EMISSIONS
Total whole life-cycle carbon emissions: 29,137 tonnes CO
2
Whole life-cycle carbon emissions per square meter: 2.742
tonnes CO
2
/sqm
16. WHOLE LIFE-
CYCLE CARBON
OPTIONS
21
Furnival Street
Options
Option 1
Major
refurb
Option 2
Major
refurb with
extension
Option 3
Redevelop-
ment
1. Gross Internal
area (GIA) m²
1979
2125
2589
2. Increase in GIA
(over existing)
10%
35%
60%
3. Substructure %
retained by mass
100%
100%
0%
4. Superstructure %
retained by area
(frame, upper
floors, roof, stairs,
ramps)
55%
35%
0
5. Upfront Embodied
Carbon (A1-A5)
(kgCOe/m² GIA)
666
616
818
6. In-use & End of
Life Embodied
Carbon (B-C)
(kgCOe/m² GIA)
excl. B6 & B7
464
461
453
7. Life-cycle
Embodied Carbon
(A1-A5, B1-B5,
C1-C4)
(kgCOe/m² GIA)
1,130
1,077
1,271
8. Fuel source
Electricity
Electricity
Electricity
9. Operational
Energy Use (B6) of
the Tunnels +
Furnival St.
(divided by GIAm
2
of Furnival St.
only) (kWh/m²/yr
GIA)
424
395
324
10. Estimated Whole
Building
Operational
Carbon for building
lifetime (B6)
(kgCOe/m² GIA)
883
822
675
11. Total WLC
Intensity (incl. B6 &
pre-demolition)
(kgCOe/m² GIA)
Module B7 is not
considered
2,026
1,918
1,977
22
12. Upfront embodied
carbon (A1-A5)
(tCOe)
1,318
1,309
2,118
13. In-use embodied
carbon (B-C, excl.
B6 & B7) (tCOe)
918
980
1,173
14. Operational carbon
for building lifetime
(B6) Tunnels +
Furnival St.
(tCOe)
1,747
1,748
1,746
15. Total WLC (incl.
B6 and pre-
demolition)
(tCOe) Module B7
is not considered
4,009
4,077
5,117
17. TARGET
BREEAM
RATING
Targeting a high-score “Very Good” BREEAM rating.
18. URBAN
GREENING
FACTOR
0.13
19. AIR QUALITY
As there are no anticipated operational emissions associated with
the Proposed Development it is considered to be Air Quality
Neutral.
23
Main Report
Assessing a cross-boundary planning application
1. The application site straddles the City of London and the London Borough of
Camden boundaries.
2. The National Planning Practice Guidance provides that where a site, which is
the subject of a planning application, straddles one or more local planning
authority boundaries, the applicant must submit identical applications to each
local planning authority.
3. Each planning application falls to be assessed under the Town and Country
Planning Act 1990. S70 provides that in dealing with a planning application the
local planning authority should have regard to the development plan, any local
finance considerations and any other material considerations. Planning and
Compulsory Purchase Act S38 (6) provides that where regard is to be had to
the development plan the determination should be in accordance with the
development plan unless material considerations indicate otherwise.
4. Duplicate planning applications for the proposed Change of use of existing
deep level tunnels (Sui Generis) to visitor and cultural attraction (Use Class
F1(b)(c)), including bar (Sui Generis); demolition and reconstruction of existing
building at 38-39 Furnival Street; redevelopment of 40-41 Furnival Street, for
the principal visitor attraction pedestrian entrance at ground floor, with ancillary
retail at first and second floor levels and ancillary offices at third and fourth
levels, excavation of additional basement levels at 40-41 Furnival Street and
38-39 Furnival Street, and widening of lift shaft at 38-39 Furnival Street;
creation of new, pedestrian entrance at 31-33 High Holborn, to provide
secondary visitor attraction entrance (including principal bar entrance),
deepening of lift shaft at 31-33 High Holborn; provision of ancillary cycle
parking, substation, servicing and plant, and other associated works’ have been
submitted to the London Borough of Camden (LBC) and the City of London
(CoL) Local Planning Authorities (LPA). Each LPA will determine the application
in accordance with the considerations below. Each planning application is
assessed independently by each LPA, with each being entitled to reach its own
decision on the application in the usual way.
5. The majority of the application site would fall within the City of London, with the
northern 31-33 High Holborn site, providing the primary access to the bar and
secondary emergency access to the tunnels, falling within the LBC’s
administrative area. However, the Planning Applications Sub-Committee is
24
required to consider the application as a whole and not just those elements
which are within the City of London.
6. In considering this application the development plan comprises the City Local
Plan 2015, the London Plan 2021 and other policies which apply in the City as
referred to in this report. The emerging draft City Plan 2040 is currently in
consideration. CoL officers have been in continuous liaison with LBC officers
over the course of the application process, having shared the planning material
considerations of the development and the assessment taken by each LPA to
ensure any concerns or objections have been adequately addressed to the
satisfaction of both LPAs. The application submitted to the LBC is due to be
determined by its planning application committee on the 11
th
of July 2024.
7. If both authorities grant planning permission, each authority will grant
permission in so far as it relates to land in their respective administrative area.
Site and Surroundings
8. The application site is 0.9ha in size of which approximately 0.7ha is
subterranean and extends along two Local Planning Authorities, the City of
London Corporation (CoL) and the London Borough of Camden (LBC). The
underground element consists of a network of tunnels (formally named the
Kingsway Tunnels) that run underneath High Holborn and Holborn, parallel and
below the London Underground Central Line, and to the south below Staple Inn
Buildings and Took’s Court.
9. The Kingsway Tunnels were built in the early 1940s underneath Chancery Lane
tube station with the purpose of sheltering 10,000 people during WWII. The
original tunnels offered approximately 7,000 sqm of internal floor space
including two 5.1m diameter tunnels known historically as ‘North’ and ‘South’
‘Street’ that run parallel and below the Central Line beneath High Holborn.
While originally constructed and intended to be used as a deep-level shelter,
the tunnels were instead used by the British government as a secret
telecommunications centre, including use by the Special Operations Executive
(SOE). In 1949 the tunnels were given to the General Post Office (GPO). The
two-tunnel shelter was extended by the addition of four tunnels of 7.2m
diameter, known as the ‘Avenues’, at right-angles to the originals and a
perpendicular service avenue of the same diameter connecting to all four. The
additional tunnels were completed by 1954, and in 1956 it became the
termination point for the first transatlantic telephone cable - TAT1. From the
1960s until the early 1980s, Kingsway Trunk Switching Centre (as it became
known) was a trunk switching centre and repeater station with Post Office
engineering staff totalling over 200 at its peak. At that point, the tunnels were
closed following findings of large quantities of blue asbestos on the site. The
25
tunnels are currently not accessible by the public. British Telecom has a
maintenance team accessing the tunnels via Fulwood Place.
Figure 1. Tunnels network light-blue portion in LB Camden, yellow
portion in City of London
10. The original public access to the shelters was from Chancery Lane tube station
and the historical entrance was located at 31-33 High Holborn. When the tube
station moved to its present location, the original connection to the tunnels was
blocked off, leaving only two access points at 38-39 Furnival Street (City) and
at Fulwood Place (Camden) which were not designed for public use.
11. Currently the tunnels include historic elements such as mechanical equipment,
a canteen, a games room, a bar, and other historic remains. Much of the historic
equipment, such as the telecommunications board, are stored elsewhere.
12. Above ground, the site comprises of three buildings. Two buildings are located
in the City of London boundary at No.38-39 and 40-41 Furnival Street and the
third is located in the London Borough of Camden at 31-33 High Holborn,
accessed via Fulwood Place.
13. The buildings at No.38-39 and 40-41 Furnival Street are located approximately
60m to the south of Holborn and they are bounded by Furnival Street to the
west, the building at 36-37 Furnival Street to the south, 1-6 Dyer’s Buildings to
the east and 14-18 Holborn to the north. They are also located in the Chancery
Lane Conservation Area which has a recognisable network of street from the
17
th
century, Southampton Buildings, Furnival Street, Cursitor Street, Took’s
Court and others. Within the north of the Conservation Area a great number of
narrow building plots survive as originally set out in the medieval period, such
as at 38-41 Furnival Street.
26
14. The building at 38-39 Furnival Street comprises of three storeys above ground
and forms the east entrance to the tunnels, which is currently closed. It is seen
to have a positive contribution to the conservation area as it offers a strikingly
industrial aesthetic to the street, contrasting with the refined architecture of
No.10 opposite. It combines concrete tiles at ground level and red brick at the
upper levels. The two sides of the building step away from the neighbouring
buildings creating a sense of a utilitarian brick block sitting on a concrete wall.
Another unique element of the building is the louvred large concrete ventilation
grille section in the middle of the brick ‘block’ on the front elevation. Internally
the building houses a goods shaft and ventilation ducts serving the eastern part
of the tunnels.
15. No.40-41 Furnival Street, is a late ‘90s six-storey office building including a
basement level. It is one of the tallest buildings on Furnival Street and has a
commercial appearance of its time. It has beige bricks at the ground levels, a
glazed section in the middle of the upper levels with red bricks at either side
and it gradually steps in at the uppermost levels. Contrary to No.38-39, the
character of No.40 is out of keeping with the prevailing architectural aesthetic
of Furnival Street due to its large bow front and is not deemed to be a positive
contributor to the conservation area.
16. Together Nos 38-39 and 40-41 offer an area of 1,423 sqm.
17. Furnival Street comprises a mix of residential and commercial occupiers. There
are residential premises near the site, with the closest being the adjoining 36-
37 Furnival Street (Aston House), 34-35 Furnival Street and the Dyer’s
Buildings to the east. The premises across the street and immediately to the
north of 40-41 Furnival Street are in commercial use.
18. Holborn is a prominent broad thoroughfare with a variety of uses and active
frontages at ground level. It has a mix of historic and contemporary building
stock with larger modern offices dominating parts of the street. Holborn serves
a dual carriageway with double lanes for cars and bus routes. It has wide
pavements and regular crossings, near the site, with a central island running
along the street hosting cycle and motorbikes parking at locations towards the
east side of the site. Bike lanes run along the edges of each carriageway
offering east and west connections. Holborn extends to High Towards the west
of Holborn is 31-33 High Holborn, the west entrance to the tunnels, comprising
an area of 364 sqm with a mix of office and residential uses on the upper levels.
19. Chancery Lane Underground Station, Farringdon Station and City Thameslink
are the nearest transport facilities to the site’s entrances. The nearest public
cycle parking spaces are located in High Holborn and Took’s Court.
27
20. The site is located in the Chancery Lane Conservation Area. No.38-39 Furnival
Street building, as an original part of Kingsway Tunnels, is considered to be a
non-designated heritage asset due to its rarity and historic interest. The
development site does not contain any statutory listed buildings. The nearest
listed buildings and scheduled monuments to the site are 32 & 33 Furnival
Street (Grade II listed), 10 Furnival Street and 25 Southampton Buildings (all
Grade II* listed), and Barnard's Inn Mercers' School Hall (Scheduled Ancient
Monument).
Relevant Planning History
21. This section is only relevant to the planning history of the part of the site located
in the City of London.
22. The building at 38-39 Furnival Street is one of the original assets of the
Kingsway Tunnels which was built in the 1950’s to ventilate the tunnels. There
is no planning history linked to this asset.
23. The existing building 40-41 Furnival Street was built by virtue of planning
permission 1205D granted on 2
nd
December 1988 for the demolition of the
previous buildings at 40-41 Furnival Street and construction of a new office (B1)
building.
24. There is no additional relevant planning history to the site.
Proposal
25. Planning permission is sought for:
The use of the Kingsway Tunnels as a visitor and cultural attraction (Use
Class F1(b)(c)), including a bar (Sui Generis);
The demolition of 38-39 Furnival Street and reconstruction of the building
with four-storeys above ground and an outdoor amenity space to the roof
level;
The demolition of 40-41 Furnival Street and erection of a five-storey building
with plant room to the roof level;
Use of the new building at 38-41 Furnival Street as ancillary to the
tunnels/cultural attraction including a principal entrance at the ground floor,
hosting of MEP and plant equipment, ancillary retail (gift shops) and staff
accommodation;
Creation of a secondary entrance at 31-33 High Holborn via Fulwood Place
(only relevant to London Borough of Camden);
Provision of ancillary cycle parking, substation, servicing and plant; and
28
Public Realm works on Furnival Street.
26. The following table provides the proposed GEA (Gross External Area) and GIA
(Gross Internal Area) figures split between the two Local Planning Authorities.
Approximately 71% of the site area created by the proposed development
belongs within the City’s authority boundary.
Table 1. Proposed GEA and GIA figures between CoL and LBC
GEA
GIA
Level
m2
m2
CoL
(GIA)
Camden
(GIA)
38-41 Furnival Street
3,020
2,467
2,467
0
Fulwood Place
386
329
0
329
Tunnel Network
9,828
7,829
5,111
2,718
TOTAL
13,234
10,625
7,578
3,047
27. The overall uplift in space would be 1,044sqm of GIA floorspace created by the
redevelopment works at Furnival Street. There is no other uplift in floorspace in
the tunnels or at the London Borough of Camden entrance.
Table 2. Schedule of Areas
Schedule of Areas
Building
sqm (GIA)
Existing
Proposed
Difference
38-39 Furnival Street (City of London)
194
942
+ 748
40-41 Furnival Street (City of London)
1,229
1,525
+ 296
31-33 High Holborn (Camden)
329
329
0
Tunnels Complex (City of London & Camden)
7,829
7,829
0
Total
9,581
10,625
+ 1,044
29
28. The uses of the proposed development would comprise:
Table 3. Breakdown of proposed areas floorspace
Use
Floorspace (GIA)
Bar (Sui Generis)
284 sqm
Visitor Attraction (F1)
includes tunnels (excl bar), above-ground areas,
and ancillary uses
10,341 sqm
Ancillary Office Staff Office Space (F1)
58.2 sqm
Ancillary Retail Gift Shop, Storage & Stair (F1)
227 sqm
Total Floorspace
10,625 sqm
Camden
3,047 sqm
City of London
7,578 sqm
29. The height of the proposed development would be 41.75m AOD at its highest
part. The demolition of the buildings at 38-41 Furnival Street is being proposed
instead of retention to allow an open excavation and enlargement of the existing
lift shaft at 38-39 Furnival Street. The new buildings would share the same
floorspace but their external appearance would indicate their individuality by
articulating two facades. 40-41 Furnival Street would maintain its commercial
aesthetic by featuring translucent glass bricks on the façade, whilst the brick
façade and concrete louvre at No.38-39 would be reused and/or replicated to
ensure the continuation of the building's historical character.
30. The ground floor elevation at 40-41 Furnival Street will be recessed to allow for
more external space and a sheltered area at the proposed principal entrance.
The ground floor of the combined building would provide step-free access to
the underground cultural spaces via a round lift shaft which follows the form of
the existing historic shaft at the same location. A reception check-in desk would
be located next to the entrance and an X-ray scanner would be placed in the
corridor that leads to the waiting lobby area to securely let people in the building.
31. The tunnels would be split into three different areas. These are described in the
following table and depicted in the plans below.
30
Table 4. Proposed areas in the tunnels
Heritage Exhibition (shared
between CoL and LBC red
area) Permanent exhibition
area focusing on the history
of the tunnels and the people
who occupied them.
Integrates a mix of immersive
experiences with the use of
technology and the exhibition
of historic remains.
Main exhibition area: ‘Streets’
the two longest horizontal
sections of the tunnels.
Cultural Exhibition (solely in
CoL yellow area)
Temporary exhibition area
using cutting-edge
technology that creates fully
immersive environments. To
be adaptive for multiple
cultural events.
Main exhibition area:
Avenues’ the three parallel
avenues that run in the
southern part of the tunnels.
Bar (solely in LBC orange
area) The deepest bar in
the UK. Accessed via
Fulwood Place.
The green area above the
bar has been marked as a
multifunction space which
could be used as an
Orientation/Classroom space
during school trips.
32. The Heritage Exhibition space makes up approximately 53% (1,965sqm of
3,713 sqm) of the total exhibition area (excluding front and back of house,
ancillary uses, toilets, lobbies), and the Cultural Exhibition space makes up
approximately 47% (1,748sqm of 3,713 sqm).
31
33. The Heritage and Cultural Exhibition spaces would be accessed via the new
Furnival building, whereas the secondary entrance via Fulwood Place forms the
main access point to the new deep-level bar. The exhibition spaces in the
tunnels have been designed to accommodate a peak occupancy of 750 visitors
at any given time which is only expected to occur 20 days (the busiest days) of
the year. The typical occupancy is estimated at 490 people per hour in the
tunnels (760pp/hr across the site) who are anticipated to spend one hour and
twenty minutes in the exhibition areas. The technical occupancy of the tunnels
(defined by evacuation, fresh air supply, and fire strategy) has been designed
to exceed the occupancy numbers.
34. At the first and second floor levels of the new Furnival building ancillary retail
space would be provided, to allow for a gift shop (on level one) and a gallery
(on level two mezzanine) in connection with the cultural experience as the last
part of the visitor’s journey. Level three would be used to house mechanical
equipment and would not be accessible to the members of the public. A staff
room would be provided at level four with access to a roof terrace, utilising the
roof of the new 38-39 Furnival Street building. The roof of the new 40-41
Furnival Street would be used as a plant room to host equipment that serves
the tunnels which requires natural ventilation. Most of the plant equipment
would be located above ground to facilitate its maintenance and accessibility.
Two separate lifts would be provided at the rear of the building, one to be used
by the members of the public leaving the gift shop area and the other for staff
and goods transfer across all levels. Evacuation lifts, dedicated Fire-Fighters
lifts, and evacuation stairs would be provided at each shaft (at both Camden
and City entrances).
35. There would be three basement levels mainly used as plant rooms, including
other facilities such as refuse storage and housing the new round lift shaft to
the south side. Visitors would be taken to basement level three from where they
enter the tunnels and begin their tour. The diagram below shows the visitor
route in the exhibition areas.
32
Figure 2. Diagram showing Visitor Heritage Trail & Exhibitions circulation routes
36. A total of 12 long-stay cycle parking has been proposed for the entire cultural
use to be split across the ground floor and basement level, including an
accessible space, accessed through the south side emergency exit. Visitor
cycle parking is proposed off-site. Sperate cycle parking is proposed in Fulwood
Place, Camden.
37. The proposed development would also provide public realm improvements to
mitigate the impact on the public highway from the increased traffic and provide
a safer welcoming pedestrian environment.
Consultations
Statement of Community Involvement
38. The Applicants have submitted a Statement of Community Involvement (SCI)
outlining their public engagement with stakeholders including: a traditional
public exhibition held in October 2023; a consultation website
(www.thelondontunnels.com); special preview events; 4,473 newsletters
posted to local addresses around the site including residents, businesses and
community groups; a social media campaign was held alongside a further
organic promotion to reach international coverage.
39. The public exhibition lasted for a calendar week and was held on Saturday 7
th
,
Tuesday 10
th
, Thursday 12
th
and Saturday 14
th
of October 2023 at St Albans
Centre, Leigh Place, Baldwin’s Gardens, London, EC1N 7AB. The exhibition
invited people to go to St. Alban’s Centre and see the detailed design proposals
33
in person and meet with the team. In total 119 members of the public attended
all six consultation events including key stakeholders and local residents.
40. A Ward Member Preview Event took place on Thursday 5 October 2023 and
the Local Neighbour Preview Event on Saturday 7 October 2023. A list of
stakeholders' names, their organisation and type/day of engagement is
provided in full in the SCI.
41. 222 surveys were completed from the online and in-person engagement of
which 99% were either positive or neutral about the proposal. The social media
and website consultation also generated 48 emails and phone calls which have
helped to inform the proposed development evolution.
42. The main areas of focus on consultation responses were accessibility, historic
value and preservation, art and culture, technology and construction impact.
The applicant sets out that consultees would like to see a highly accessible
development that is inclusive for everyone not only physically but also
financially, specifically ensuring the attraction remains open and accessible to
a wide group of people. The history of the site has intrigued many consultees
who would like to see it preserved and celebrated by retaining its authenticity
and heritage/cultural value. Proposals from consultees to use technology for
sustainability achievements were made that focus on climate change solutions
and renewable energy but also a way to educate people on that field. Concerns
were raised as to the increased footfall to the local area, causing disturbance
and how that would be managed and mitigated by the development. Similarly,
other concerns focused on the construction impacts affecting local traffic and
noise levels along Furnival Street.
Consultation and notification
43. Following receipt of the application, it has been advertised on site on 21
st
December 2023 and in the press on 9
th
January 2024. Residents near the two
entrances were included in consultations. On 10
th
January 2023, 140 letters
were sent to residential properties, in addition to the publicity carried out as set
out above. The relevant statutory consultees have been consulted following the
validation of the application.
44. Following consultation feedback, the applicant made some design and
highways amendments and updates on the accessibility and daylight sunlight
reports. These were received on the 2
nd
April 2024. Accordingly, a 14-day re-
consultation has been undertaken. On 23
rd
April 2024, re-consultation letters
were sent to the same residential properties to inform them on the minor
amendments to the scheme. Copies of all representations are appended in full
and appended to this report at Appendix A. A summary of the representations
received and the consultation responses is set out in the tables below.
34
45. The applicant has provided detailed responses to matters raised in consultee
responses. The applicant’s responses should be referenced as background
papers at Appendix A.
46. The views of other City of London departments have been taken into account
in the preparation of this report and some detailed matters are addressed by
the proposed conditions and the terms of the S106 agreement.
Statutory Consultation
47. A total of 12 statutory responses have been received which are summarised in
the following table.
Table 5. Statutory consultation responses
Consultee
Summary of comments
GLAAS
The comments make reference to the submitted
archaeological desk-based study submitted as part of the
current application. GLASS comments that remains of the late
17
th
Century were excavated on the southern half of the site
which may have removed any evidence for the earlier inn. All
archaeological remains have likely been removed from 40-41
Furnival Street.
In relation to excavation works at 38-39 Furnival Street, it is
likely that some archaeological potential remains and therefore
further archaeological work is recommended in advance of the
excavation of the new basement.
Despite limited works being proposed for the tunnels, GLAAS
notes that the tunnels are of high heritage interest and
recommends that historic building recording for the site is
carried out for them in advance of development. A condition
has been recommended along these lines.
In accordance with NPPF paragraph 205 the applicant should
record the significance of any heritage assets that the
development harms. Applicants should improve knowledge of
assets and make this public.
GLAAS advices that the development could cause harm to
archaeological remains and field evaluation is needed to
determine appropriate mitigation. It is considered a two-stage
archaeological condition comprising firstly of evaluation to
clarify the nature and extent of surviving remains and followed,
if necessary, by a full investigation.
35
Officer response: The matter is addressed in the Archaeology
section of the report.
Historic England
(Inspector of
Ancient
Monuments)
HE has commented on designated heritage assets only. It has
been noted that the development site sits close to the
scheduled monument of Barnards Inn. The proposed
development does not physically affect the Inn. However,
Barnards Inn is encapsulated within a mass of more recent
buildings, experiencing overshadowing. The proposed
development would not compromise the setting of the Inn any
further, although HE notes that care should be taken to ensure
access to it remains easily navigated and signage is not
impacted. As long as the application would not materially
change, HE would not need to be re-consulted.
Officer response: The proposed buildings' height and mass
remained the same over the course of the application.
Therefore, HE has not been re-consulted.
TfL
(Infrastructure
Protection)
TfL (Infrastructure Protection) has no objection to the proposed
development in principle. The consultee has however set out
a number of potential constraints linked to the proximity of the
development site with London Underground railway
infrastructure. A set of conditions have been recommended
that require consultation with TfL Infrastructure Protection
through submission and approval by the LPA.
Officer response: Conditions are recommended.
TfL (Spatial
Planning)
Pedestrian Comfort
TfL (Spatial Planning) deems the pedestrian comfort levels
submitted acceptable.
PT Impact
TfL suggests that wayfinding measures in the station would
help people exiting the station more easily will help offset this
impact (and improve their experience of the venue), as would
wayfinding on the street to help people find the destination,
and on return raise awareness of proximity to other
destinations and public transport, improving their experience.
Cycle Parking
TfL advises that further work should be carried out to improve
the long-stay cycle parking design and access.
Car Parking
Subject to both LPA’s deeming the location and operation of
the blue-badge bay being acceptable, TfL consider this
36
appropriate. However, the applicant is encouraged to identify
blue badge locations on the Camden access point.
Taxi and Coach Access
TfL requests for more clarity on how or if taxi’s/ private hire
vehicles would be restricted from accessing Furnival Street.
They request a more robust coach management plan is
provided. The TfL Coach team have highlighted that a current
plan could lead to illegal parking on street which in turn would
impact safety and operation of Holborn. It has been suggested
that coaches could use Bedford Row as an official parking bay
or consider the provision of a bay on northbound element of
Kingsway. Further discussion on this element should be
provided and the relevant review mechanisms in the travel
plan and operational strategy should be put in place to allow
amendments where deemed necessary.
Delivery and Servicing
TfL have concerns over the feasible operation of the Delivery
and Servicing Plan particularly on Furnival Street and
clarification is sought on how this will be managed. The final
DSP should be secured by condition and should also consider
when the needs of the occupier may change for special events
etc.
Construction Logistics
TfL acknowledge the Outline Construction Logistics Plan, but
has serious concerns over the proposed management,
operation and feasibility of carrying out this plan. This should
have the earliest engagement in order to provide
suitable mitigation as this may impact pedestrian, bus
operations and London Underground Infrastructure. TfL
recommends that the access proposal is supported by a road
safety audit, also that for pedestrian and cycle routing during
construction, these should subject to detail assessment in
accord with Construction Logistics and Community Safety
standard and appropriate pedestrian comfort levels. The final
Construction Logistics Plan should be provided in accordance
with TfL guidance and discharged in consultation with TfL.
Wayfinding
A Wayfinding Strategy is recommended to be secured by
condition. This should include updates to wider Legible
London Signage and the provision of additional signage where
appropriate on street and potentially within LU Stations.
Travel Plan
37
TfL welcome the provision of the revised travel plan which
includes a range of soft and hard measures. Suggested
additional measures which may form part of their travel plan
could be the provision of a wayfinding strategy which would
encourage people to walk from key transport nodes and to
reduce pedestrian congestion in key locations. Another
measure which could be included as part of the plan and/or
upon review of the plans, could be to incorporate Santander
Cycle Hire with tickets. TfL offer innovative ways to work with
business to provide sustainable transport options such as this.
Given the site is well served via cycle hire and cycling
infrastructure, this could be a suitable option.
Operational Management Strategy
TfL advises that the applicant should provide an operational
management plan which should be secured via condition. This
should provide sufficient mechanisms and proposals which
can be adapted once the venue is operational.
Dockless Bikes
TfL request the City of London and the LB of Camden work
with the dockless bike providers to provide a no parking zone
surrounding the access locations. Whilst this is not within the
control of the future occupier, the reason behind this request
is due to the constraint nature of the access points and
potential implications of the bikes being in these inconvenient
locations.
Cycle Hire
On this occasion TfL are not requesting a cycle hire
contributions given the expect impact of the development will
be outside of peak hours when the system experiences most
pressure. However, measures mentioned above via the Travel
Plan should be secured appropriately.
Officers response: The comments are taken into
consideration the Transport and Highways section of this
report addresses the above matters. Conditions have been
recommended.
Thames Water
Thames Water has raised no objections and has requested
conditions to be included to require a piling method statement.
Thames Water advises that any significant work near their
sewers must minimize the risk of damage. Works should be
guided in accordance with the Thames Water ‘guide working
near or diverting our pipes’.
38
As required by Building regulations part H paragraph 2.36,
Thames Water requests that the Applicant should incorporate
within their proposal, protection to the property to prevent
sewage flooding, by installing a positive pumped device (or
equivalent reflecting technological advances), on the
assumption that the sewerage network may surcharge to
ground level during storm conditions.
If as part of the basement development there is a proposal to
discharge ground water to the public network, this would
require a Groundwater Risk Management Permit from Thames
Water. Any discharge made without a permit is deemed illegal
and may result in prosecution under the provisions of the
Water Industry Act 1991. They would expect the developer to
demonstrate what measures will be undertaken to minimise
groundwater discharges into the public sewer. Permit
enquiries should be directed to Thames Water’s Risk
Management Team by telephoning 02035779483 or by
emailing [email protected] .
With regard to the COMBINED WASTE WATER network
infrastructure capacity, Thames Water would have no
objection based on the information provided.
Thames Water would expect the developer to demonstrate
what measures will be undertaken to minimise groundwater
discharges into the public sewer. Groundwater discharges
typically result from construction site dewatering, deep
excavations, basement infiltration, borehole installation,
testing and site remediation. Any discharge made without a
permit is deemed illegal and may result in prosecution under
the provisions of the Water Industry Act 1991. They have
requested an informative to be included to advise on the
requirement for a Groundwater Risk Management Permit from
Thames Water for discharging groundwater into a public
sewer. Any discharge made without a permit is deemed illegal
and may result in prosecution under the provisions of the
Water Industry Act 1991. They would expect the developer to
demonstrate what measures he will undertake to minimise
groundwater discharges into the public sewer. Permit
enquiries should be directed to Thames Water’s Risk
Management Team by telephoning 020 3577 9483 or by
Thames Water would advise that with regard to water network
infrastructure capacity, they would not have any objection to
the above planning application and have requested to include
an informative to advise that Thames Water will aim to provide
customers with a minimum pressure of 10m head (approx 1
39
bar) and a flow rate of 9 litres/minute at the point where it
leaves Thames Waters pipes. The developer should take
account of this minimum pressure in the design of the
proposed development.
The proposed development is located within 5m of a strategic
water main. Thames Water do NOT permit the building over or
construction within 5m, of strategic water mains and have
requested to include a condition for ‘no construction shall take
place within 5m of the water main.’ The condition requests
details of how the developer intends to divert the asset / align
the development, so as to prevent the potential for damage to
subsurface potable water infrastructure, to be submitted to the
Local Planning Authority in consultation with Thames Water.
Thames Water advises works have the potential to impact on
local underground water utility infrastructure. They would like
the developer to read their guide ‘working near our assets’ to
ensure the works will be in line with the necessary processes
the development needs to follow if considering working above
or near Thames Water pipes or other structures.
There are water mains crossing or close to the development.
Thames Water do NOT permit the building over or construction
within 3m of water mains. If the developer is planning
significant works near Thames Water mains (within 3m),
Thames Water will need to check that the development doesn’t
reduce capacity, limit repair or maintenance activities during
and after construction, or inhibit the services they provide in
any other way. The applicant is advised to read Thames Water
‘guide working near or diverting our pipes.’
Thames Water has requested an informative to be included to
advise that Thames Water will aim to provide customers with
a minimum pressure of 10m head (approx 1 bar) and a flow
rate of 9 litres/minute at the point where it leaves Thames
Waters pipes. The developer should take account of this
minimum pressure in the design of the proposed development.
Officers response: Conditions and informatives are
recommended.
Environmental
Agency
No comments Environmental Agency has advised that the
planning application is consulted upon with the Local
Authority’s Environmental Health department.
Officer response: City of London Environmental Health team
have been consulted on the proposed development.
Health &
Wellbeing Policy
No comments to date.
40
Development
Manager
Lead Local Flood
Authority
Conditions are recommended requiring further details of SuDs
system and flood prevention measures.
Officer response: Conditions are recommended.
Counter-
Terrorism
Security Advisor
(CTSA)
CTSA has visited the site and read through the submitted
Security Report. Separate advice has been provided to the
applicant that does not require any planning conditions to be
imposed, however, the applicant is advised to consult CTSA
as the plans evolve. Details of the security measures for the
site are confidential, and not available in the public domain.
Officer response: An informative has been added.
City of London
Police (Design
Out Crime
Officer)
City of London officers have been consulted and commented
on their requirements for the external security of the venue and
recommended alternative options/standards that would be of
their satisfaction if adopted at the more detailed design stage.
A comment was made about the constraint nature of the
existing lifts at Fulwood Place for emergency services access.
It has been clarified that the proposal seeks to enlarge the
existing lifts increasing the capacity of people by 3 times which
has been deemed acceptable at this stage. A point was made
about the ability to close the tunnel system to afterhours
drinkers in reference to the proposed bar in Camden. The
agents have responded that the area outside of the bar will be
physically locked off to prevent bar patrons getting access to
any area outside of the bar space. CoL Police Officer has
found this approach acceptable. They have noted that subject
to any matters that the CTSA’s may raise, they are satisfied
with the response and the fact that other issues can be
resolved at the detailed design stage.
Officer response: An informative has been added to consult
CoL Police at detailed design stage.
Conservation
Area Advisory
Committee
(CAAC)
Officers presented the proposed scheme to the CAAC on the
15
th
of February 2024. No objections were raised with a formal
non-objection letter submitted to the application on 1
st
of March
2024.
London Fire
Brigade
General fire safety design approach and consultation with key
stakeholders
London Fire Brigade (LFB) understands that it is proposed that
the methodology outlined in BS 7974:2019 will be applied and
they support this approach. As part of this methodology, LFB
advises that a Qualitative Design Review (QDR) process
41
should be undertaken and LFB would expect to be involved in
this process as a key stakeholder, both in their capacity as an
emergency response agency for fires and other emergencies
but also as the future enforcing authority for The Order.
However, they emphasise that it cannot be assumed that
following any particular methodology, in and of itself,
automatically leads to acceptable solutions or outcomes. The
detail of any risks identified, and decisions made, may need
revision throughout the design and construction phases as
previously unknown circumstances arise, and may not be
easily or suitably resolved.
LFB advise that caution is taken if applying the
recommendations of BS 9992 to tunnels that do not form part
of railway infrastructure, whilst some of the recommendations
of the code of practice may be applicable, the assumptions
made for sub-surface railway infrastructure in particular are
quite different than those for other types of purpose
group/occupancy. LFB expects subject to the outcome of the
performance-based design process and associated
stakeholder engagement that suitable smoke
ventilation/control systems will be provided, in conjunction with
suitable and compatible automatic fire suppression systems.
Critical fire safety design issues that LFB would expect to be
addressed as the design is developed
LFB wish to highlight a number of fire safety design issues that
we would expect to be addressed as the fire safety design
process progresses. This is not intended to be exhaustive.
- Extended travel distances for occupant means of
escape and firefighter access/intervention;
- Inclusive design and means of escape for persons with
relevant protected characteristics;
- Radio communications coverage for firefighters and
other emergency responders;
- Electric Powered Personal Vehicles;
- Construction phase fire safety.
LFB informs that it is not possible to advise if London Plan
Policies D12 and D5 can be considered to have been met
without assurances being sought that the design will progress
in consultation with LFB and other emergency services.
Officer response: Noted these comments are addressed in
the Fire Statement section of the report.
British
Telecommunicati
ons
No comments to date.
42
City of
Westminster
No objection.
London Borough
of Camden
Duplicate planning applications have been submitted to the
City of London and LB of Camden for the proposed
development. LB of Camden has made no comments
regarding the proposed works taking place within the City of
London, however, their Committee Report recommendations
form material considerations in the report’s assessment.
Letters of Representation
Support
48. A total of 57 letters of support from the public have been received over the
course of the planning application. Among them, there were two Business
Improvement Districts, local residents and business owners, as well as people
from around London, Britain and the globe. The topics of support for the
proposed development have been summarised as follows:
Embracing and preserving the history of the Kingsway Tunnels;
Educational Opportunities providing visitors of all ages with opportunities
to learn and engage through interactive exhibits, guided tours and
educational workshops.
Public-private partnerships, collaboration between public agencies,
private investors and community organisations;
Cultural Enrichment;
Seven-day destination in line with City’s destination vision;
Revitalise/Boost the local economy with positive effect to businesses
and communities;
Facilitates post-pandemic recovery of the local area;
Increase tourism;
Potential to bring growth in the area;
Creation of new jobs;
Repurposing of existing redundant infrastructure;
Provision of accessible spaces;
Design and Sympathetic to its surroundings;
Provision of innovative and attractive environments;
Creation of a benchmark development;
Help London to continue being perceived as a world-class city and adds
to its competitiveness.
43
Central District Alliance
49. Officers received an email from the Central District Alliance (CDA), Business
Improvement District comprising of Holborn, Clerkenwell, Farringdon,
Bloomsbury, and St Gile, which informed they have submitted comments and
a letter of support to Camden Council on the parts of the development which
impact their footprint. CDA is supporting the proposed development coming
forward, which consequently includes City’s application, and the wider
economic benefits it brings ‘rejuvenation of local business, increased tourism,
and educational engagement, projecting an economic uplift of £60-£80 million
annually for the area. The letter of support refers to the proposed development
as a significant opportunity for economic, cultural, and historical enrichment in
our community’ and urges the LPA to recognise the transformative potential of
the development to bring lasting benefits to their district, fostering a vibrant,
culturally rich, and economically robust economy.
50. CDA’s email states: “The area of Holborn is well placed to guide visitors to and
from main transport hubs located on the tri-borough boundary and to cater for
footfall to and from the attraction. We are dedicated to see economic growth in
this particular part of central London and welcome this as a new cultural venue
in the area.”
Fleet Street Quarter
51. A comment was made by a representative of Fleet Street Quarter (FSQ), a BID
with footprint in the western part of the City of London. FSQ recognises the
need for a visitor attraction at this part of the City to create a destination to a
part of London that has been suffering due to lack of competitive offer compared
to other more prestigious attractions in London such as St Paul’s Cathedral and
Covent Garden. FSQ considers that the proposed cultural scheme would
complement and support the needs of workers and along with the Museum of
London they would ‘put the area on the map’. The anticipated number of visitors
is welcomed by FSQ as it would strengthen the retail offer along Holborn and
support other retail businesses in the area and boost the weekend economy to
a much needed business district.
Objections
52. A total of 24 objections have been received over the course of the planning
application including a letter of representation prepared by Daniel Watney
consultants, on behalf of the neighbouring commercial occupiers at 10 Furnival
Street (Chancery Exchange), comprising of transport (by Haskoning DHV) and
daylight and sunlight (by Joel Michaels Reynolds) comments about the
submitted information. Officers have fully reviewed all the objections and
44
selected key themes as summarised below. Some comments are referenced in
full where necessary.
Table 6. List of objections and officer responses
Issues
Number of
objections
relating to
this issue
Officer responses
including paragraph of
report where issues are
addressed
Noise linked to demolition,
construction of the proposed
development (detrimental to
residential and others amenity)
14
Impact on the amenity
Transport and Highways
Noise/Disturbance linked to
operation of the proposed
development (detrimental to
residential and others amenity) -
main sources: increased footfall,
external queuing, anti-social
behaviours, operational
traffic/servicing, hours of operation
16
Impact on the amenity
Transport and Highways
Litter and dirt in the local area caused
by increased footfall
2
Conditions have been
recommended for the
operational management of
the development.
Noise linked to late evening activities
and/or bar (detrimental to residential
and others amenity)
4
Impact on the amenity
Vibration
2
Impact on the amenity
34-35 Furnival Street have flats
extend under the private area of the
pavement with vulnerable pavement
lights
1
This comment is not clear.
The proposed development
shares no boundaries with
No.34-35, flats on this
address will be protected from
works.
Incompatible with area’s Character
(residential/pedestrian character and
Conservation Area)
8
Principle of cultural use
Transport and Highways
Accessibility
Design and Heritage
Design/Visual Appearance &
Heritage (negative impact on the
conservation area and settings of
historical buildings)
4
Design and Heritage
Increased traffic and congestion
generated by the proposed
development. Chancery Lane and
4
Transport and Highways
45
Holborn are characterised as already
congested areas.
Delivery/Servicing and parking,
including taxi drop-offs, would be of
high demand when the proposed
development comes to operation
which would impact traffic flow as
cars would park outside the premises
with long delays blocking the whole
width of the street and causing stress
to local network.
7
Transport and Highways
No provision for vehicle access by
residents and businesses is apparent
in the proposal. Loss of vehicle
access would be a hardship and
detrimental for residents and
businesses who rely on service
deliveries and building maintenance
services.
1
Transport and Highways
Damages to the (conservation) local
area mainly due to construction
works
1
Transport and Highways
Loss of existing cycle lane
1
Transport and Highways
Blue Badge space would be lost with
no additional spaces proposed
3
Transport and Highways
No on-site visitor cycle parking
proposed location at High Holborn
central reserve would increase the
barrier to pedestrian movement
across the street.
1
Transport and Highways
Physical incapacity of Furnival St to
accommodate development
8
Transport and Highways
Accessibility
Impact of the proposed kerb build out
along the site frontage to the
surrounding area.
1
Transport and Highways
Human Safety - issues are
connected with the proposed
evacuation strategy, queuing on the
streets and servicing vehicles at the
same time along Furnival Street; and
asbestos airborne particles
4
Transport and Highways
Accessibility
Proposed contamination
conditions
Emergency services access
3
Transport and Highways
Accessibility
Security and terrorism
2
Security and Statutory
Consultation
46
Structural damage to adjoining
properties
2
Party Wall Agreements do not
fall under the legislative
framework relevant to the
assessment of planning
applications. Nevertheless,
Structural Assessments have
been submitted that address
the issue.
Daylight Sunlight impact on opposite
commercial building at 10 Furnival
Street (Chancery Exchange).
1
Daylight and Sunlight
Light Pollution
1
Light Pollution
Air Quality
3
Air Quality
Drainage and Ventilation
2
Sustainability
Precedent with respect to land use
2
Any future planning
application would be
assessed on its own merits
and against the most up-to-
date national, London and
local plan policies.
Principle of Development: Land Use
(loss of office and provision of
conflicting uses to the local context)
2
Principle of development
Principle of Development: Bar
1
The proposed bar is located
in LB Camden and will be
accessed only via the
secondary entrance in High
Holborn. The relevant Local
Planning Authority would be
assessing the principle of the
bar use against their own
policies, however, pubic
concerns would be shared
with LB Camden officers.
Fire Safety (risk of explosion in
pressurised areas)
2
Fire Statement
Waste Management (provision for
further disposal; plans do not show
access and refuse collection from
below ground levels)
3
Waste Management
The development needs to be
balanced against the interests of
local residents and the preservation
of the conservation area
1
Heritage and Design
Human Rights Act 1998
The Public Sector Equality
Duty (section 149 of the
Equality Act 2010)
47
32 & 33 Furnival Street have listed
cellars that run under the road and
pavement areas along Furnival
Street which could be damaged
1
It is acknowledge there are
listed basements to 32 and
33. Officers would expect
localised vaults under the
pavement and road but would
not expect these to extend
beyond the immediate
context and significantly
along Furnival Street. Please
also refer to Archaeology
section and relevant
conditions.
The proposal fails to convince that
the area would benefit from such
tourist attraction
1
Cultural Use and Cultural
Strategy
The development would have a
negative impact on the local
economy and would be detrimental
to the social fabric of the community.
1
Cultural Use and Cultural
Strategy
Not preserving the historic
environment/tunnels
3
Please refer to the Proposal,
Cultural Use and Cultural
Strategy. The proposed
development seeks to
preserve the heritage
element and make it
accessible.
Impact on keeping or finding new
tenants
1
Not a material planning
consideration.
Compliance with planning policies
2
Please refer to the
assessment part of the report
and the Conclusions. Officers
have assessed the
application against the
adopted and emerging
development plan policies.
53. It is noted that all material planning considerations raised in the representations
above are addressed within this report.
Neutral
54. Three neutral comments have been received including one from a local
businessman who supports the application and requests mitigation measures
to be considered in relation to construction traffic, increase number of visitors
leading to demand for parking and the preservation of the historic features in
the tunnels. The second neutral comment requests to know more about the
48
expected noise levels of the concrete acoustic louvre. In both cases, relevant
assessment has been undertaken and conditions have been recommended for
further details and mitigation measures when deemed appropriate.
Policy Context
55. The Development Plan consists of the London Plan 2021 and the City of
London Local Plan 2015. The London Plan and Local Plan policies that are
most relevant to the consideration of this case are set out in Appendix B to this
report.
56. The City of London (CoL) has prepared a draft plan, the City Plan 2036, which
was published for Regulation 19 consultation in early 2021. The City does not
intend to proceed with this plan and therefore it is of very limited weight and will
not be referred to in this report. The draft City Plan 2040 was published for
Regulation 19 consultation in April 2024 which is expected to end on 17
th
June
2024. It is anticipated that the draft City Plan 2040 will be submitted to the
Secretary of State in Autumn 2024. Emerging policies are considered to be a
material consideration with limited weight with an increasing degree of weight
as the City Plan progresses towards adoption, in accordance with paragraph
48 of the NPPF. The draft City Plan 2040 policies that are most relevant to the
consideration of this case are set out in Appendix B to this report.
57. Government Guidance is contained in the National Planning Policy Framework
(NPPF) September 2023 and the Planning Practice Guidance (PPG) which is
amended from time to time.
58. The National Planning Policy Framework (NPPF) states at paragraph 2 that
“Planning Law requires that applications for planning permission must be
determined in accordance with the development plan unless material
considerations indicate otherwise”.
National Planning Policy Framework (NPPF)
59. The NPPF states at paragraph 8 that achieving sustainable development has
three overarching objectives, being economic, social and environmental.
60. Paragraph 10 of the NPPF states that at the heart of the Framework is a
presumption in favour of sustainable development. That presumption is set out
at paragraph 11. For decision-taking this means:
a) approving development proposals that accord with an up-to-date
development plan without delay; or
b) where there are no relevant development plan policies, or the policies which
are most important for determining the application are out of date, granting
permission unless:
49
the application of policies in this Framework that protect areas or assets
of particular importance provides a clear reason for refusing the
development proposed; or
any adverse impacts of doing so would significantly and demonstrably
outweigh the benefits, when assessed against the policies in this
Framework taken as a whole.
61. Paragraph 48 states that local planning authorities may give weight to relevant
policies in emerging plans according to:
a) the stage of preparation of the emerging plan (the more advanced its
preparation the greater the weight that may be given);
b) the extent to which there are unresolved objections to relevant policies (the
less significant the unresolved objections, the greater the weight that may
be given) and
c) the degree of consistency of the relevant policies in the emerging plan to
this Framework (the closer the policies in the emerging plan to the policies
in the Framework, the greater the weight that may be given).
62. Chapter 8 of the NPPF seeks to promote healthy, inclusive and safe places.
63. Paragraph 96 states that planning decisions should aim to achieve healthy,
inclusive and safe places which promote social interaction, are safe and
accessible and enable and support healthy lifestyles.
64. Paragraph 97 states that planning decision should provide the social,
recreational and cultural facilities and services the community needs.
65. Paragraph 101 states that planning decisions should promote public safety and
should take into account wider security and defence requirements by:
a) anticipating and addressing possible malicious threats and natural hazards,
especially in locations where large numbers of people are expected to
congregate… and the layout and design of developments, should be
informed by the most up-to-date information available from the police and
other agencies about the nature of potential threats and their implications.
This includes appropriate and proportionate steps that can be taken to
reduce vulnerability, increase resilience and ensure public safety and
security; and
b) recognising and supporting development required for operational defence
and security purposes, and ensuring that operational sites are not affected
adversely by the impact of other development proposed in the area.
66. Chapter 9 of the NPPF seeks to promote sustainable transport. Paragraph 105
states that “Significant development should be focused on locations which are
or can be made sustainable, through limiting the need to travel and offering a
50
genuine choice of transport modes. This can help to reduce congestion and
emissions and improve air quality and public health”.
67. Paragraph 116 states that applications for development should give priority first
to pedestrian and cycle movements and second to facilitating access to high
quality public transport; it should address the needs of people with disabilities
and reduced mobility in relation to all modes of transport; it should create places
that are safe, secure and attractive and which minimise the scope for conflicts
between pedestrians, cyclists and vehicles; it should allow for the efficient
delivery of goods and access by service and emergency vehicles.
68. Paragraph 117 states that “All developments that will generate significant
amounts of movement should be required to provide a travel plan, and the
application should be supported by a transport statement or transport
assessment so that the likely impacts of the proposal can be assessed”.
69. Chapter 11 of the NPPF seeks to achieve effective use of the land. Paragraph
123 advises that Planning policies and decisions should promote an effective
use of land in meeting the need for homes and other uses, while safeguarding
and improving the environment and ensuring safe and healthy living
conditions.”
70. Chapter 12 of the NPPF seeks to achieve well designed places. Paragraph 126
advises that The creation of high quality, beautiful and sustainable buildings
and places is fundamental to what the planning and development process
should achieve. Good design is a key aspect of sustainable development,
creates better places in which to live and work and helps make development
acceptable to communities.”
71. Paragraph 135 sets out how good design should be achieved including
ensuring developments function well and add to the overall quality of the area,
not just for the short term but over the lifetime of the development, are visually
attractive as a result of good architecture, layout and appropriate and effective
landscaping, are sympathetic to local character and history, including the
surrounding built environment and landscape setting, while not preventing or
discouraging appropriate innovation or change (such as increased densities),
establish or maintain a strong sense of place, using the arrangement of streets,
spaces, building types and materials to create attractive, welcoming and
distinctive places to live, work and visit; optimise the potential of the site to
accommodate and sustain an appropriate amount and mix of development
(including green and other public space) and create places that are safe,
inclusive and accessible and which promote health and wellbeing.
51
72. Paragraph 139 sets out that significant weight should be given to outstanding
or innovative designs which promote high levels of sustainability or help raise
the standard of design more generally in an area, so long as they fit in with the
overall form and layout of their surroundings.
73. Chapter 14 of the NPPF relates to meeting the challenge of climate change.
Paragraph 157 states that the planning system should support the transition to
a low carbon future in a changing climate. It should help to; shape places in
ways that contribute to radical reductions in greenhouse gas emissions,
minimise vulnerability and improve resilience; encourage the reuse of existing
resources, including conversion of existing buildings.
74. Paragraph 159 states that new developments should avoid increased
vulnerability to the range of impacts arising from climate change. When new
development is brought forward in areas which are vulnerable, care should be
taken to ensure that risks can be managed through suitable adaptation
measures.
75. Chapter 16 of the NPPF relates to conserving and enhancing the historic
environment. Paragraph 201 of the NPPF advises that Local Planning
Authorities should identify and assess the particular significance of any heritage
asset that may be affected by a proposal (including by development affecting
the setting of a heritage asset) taking account of the available evidence and
any necessary expertise. They should take this into account when considering
the impact of a proposal on a heritage asset, to avoid or minimise any conflict
between the heritage asset’s conservation and any aspect of the proposal.
76. Paragraph 203 of the NPPF advises, “In determining applications, local
planning authorities should take account of:
a) the desirability of sustaining and enhancing the significance of heritage
assets and putting them to viable uses consistent with their conservation;
b) the positive contribution that conservation of heritage assets can make to
sustainable communities including their economic vitality; and c) the
desirability of new development making a positive contribution to local
character and distinctiveness.”
77. Paragraph 205 of the NPPF advises “When considering the impact of a
proposed development on the significance of a designated heritage asset, great
weight should be given to the asset’s conservation (and the more important the
asset, the greater the weight should be). This is irrespective of whether any
potential harm amounts to substantial harm, total loss or less than substantial
harm to its significance.
52
78. Paragraph 208 of the NPPF states Where a development proposal will lead to
less than substantial harm to the significance of a designated heritage asset,
this harm should be weighed against the public benefits of the proposal
including, where appropriate, securing its optimum viable use”.
79. Paragraph 209 of the NPPF states The effect of an application on the
significance of a non-designated heritage asset should be taken into account in
determining the application. In weighing applications that directly or indirectly
affect non-designated heritage assets, a balanced judgement will be required
having regard to the scale of any harm or loss and the significance of the
heritage asset”.
80. Paragraph 212 of the NPPF states Local planning authorities should look for
opportunities for new development within Conservation Areas and World
Heritage Sites, and within the setting of heritage assets, to enhance or better
reveal their significance. Proposals that preserve those elements of the setting
that make a positive contribution to the asset (or which better reveal its
significance) should be treated favourably.”
Statutory Duties
81. The Corporation, in determining the planning application has the following main
statutory duties to perform:
To have regard to the provisions of the development plan, so far as material
to the application, to local finance considerations, and to any other material
considerations. (Section 70 Town & Country Planning Act 1990);
To determine the application in accordance with the development plan
unless other material considerations indicate otherwise. (Section 38(6) of
the Planning and Compulsory Purchase Act 2004).
Main Considerations
82. In considering whether to grant planning permission for development which
affects a listed building or its setting, to have special regard to the desirability
of preserving the building or its setting or any features of special architectural
or historic interest which it possesses. (S66 (1) Planning (Listed Buildings and
Conservation Areas) Act 1990).
83. Account has to be taken of the documents accompanying the application, the
further information, any other information and consultation responses, the
development plan, and other material considerations including SPGs, SPDs
and emerging policy.
84. The principal issues in considering this application are:
a) The extent to which the proposals comply with Government policy advice
(NPPF) and with the relevant policies of the Development Plan.
53
b) The principle of development and proposed uses.
c) The loss of office floorspace.
d) The impact of the proposed development on the amenity of nearby
residential and other occupiers.
e) The impact of the proposal on public safety and security in the City.
f) The economic impact of the proposal.
g) The impact of the development on the character and appearance of the
conservation area and the design of the building itself.
h) The impact of the development on designated and non-designated heritage
assets.
i) The impact of the development on public realm.
j) The impact of the development on ecology.
k) The accessibility and inclusivity of the development.
l) The impact of the development on any potential archaeological assets
beneath the site.
m) The impact of the development on highway and transportation terms.
n) The impact of the development in terms of energy, sustainability and climate
change.
o) The impact of the development on air quality.
p) The impact of the development on health and wellbeing.
q) The impact of the development on fire safety.
r) The impact of the development on flood risk.
s) Duties under the Public Sector Equality Duty (section 149 of the Equality
Act 2010).
t) The Human Rights Act 1998.
u) The requirement of financial contributions and other planning obligations.
Principle of Development
85. The NPPF places significant weight on ensuring that the planning system
supports sustainable economic growth, creating jobs and prosperity.
86. Paragraph 96 of the NPPF states that planning decisions should aim to achieve
healthy, inclusive and safe places and provide social, recreational and cultural
facilities and services the community needs.
87. The Local Plan Core Strategic Policy states that when considering development
proposals, the City Corporation will take a positive approach that reflects the
presumption in favour of sustainable development contained in the NPPF. It will
always work proactively with applicants jointly to find solutions which mean that
proposals can be approved wherever possible, and to secure development that
improves the economic, social and environmental conditions in the area.
88. London Plan Policy GG2 sets out the Mayor’s good growth policy with regard
to making the best use of land. These include prioritising sites which are well-
54
connected by existing or planned public transport; proactively explore the
potential to intensify the use of land to support additional homes and
workspaces, promoting higher density development, particularly in locations
that are well-connected to jobs, services, infrastructure and amenities by public
transport, walking and cycling; applying a designled approach to determine
the optimum development capacity of sites; and understanding what is valued
about existing places and use this as a catalyst for growth, renewal, and place-
making, strengthening London’s distinct and varied character.
89. London Plan Policy GG5 sets out the Mayor’s good growth policy with regard
to growing London’s economy, To conserve and enhance London’s global
economic competitiveness and ensure that economic success is shared
amongst all Londoners, it is important that development, amongst others,
promotes the strength and potential of the wider city region; plans for sufficient
employment and industrial space in the right locations to support economic
development and regeneration; promote and support London’s rich heritage
and cultural assets, and its role as a 24-hour city; and makes the fullest use of
London’s existing and future public transport, walking and cycling network, as
well as its network of town centres, to support agglomeration and economic
activity.
90. London Plan Policy SD4 outlines that within the Central Activity Zones (CAZ) a
mix of strategic functions and local uses should be promoted and enhanced.
Cultural, arts, entertainment, night-time economy and tourism functions are
some of these functions.
91. London Plan Policy D3 states that a site’s capacity is optimised by a design-led
approach that requires going through an optioneering process of the most
appropriate form of development for the site considering its context and
capacity for growth including its infrastructure capacity form and layout,
experience and quality and character. Higher-density developments should be
located in areas with well-connected jobs, services, infrastructure and
public/sustainable transport.
92. Strategic Objective 1 in the City of London Local Plan 2015 is to maintain the
City’s position as the world’s leading international financial and business centre.
Policy CS1 aims to increase the City’s office floorspace by 1,150,000sq.m gross
during the period 2011-2026, to provide for an expected growth in workforce of
55,000. The Local Plan, policy DM1.2 further encourages the provision of large
office schemes, while DM1.3 encourages the provision of space suitable for
SMEs.
93. Strategic Objective 3 in the City of London Local Plan 2015 is to promote a
high-quality heritage environment with supporting and continued development
of the City as a cultural destination. The Local Plan envisions the continuity of
55
cultural and leisure destinations in the City for workers, residents and visitors
with equal opportunities, accessibility and involvement for everyone.
94. Strategic Objective 5 in the City of London Local Plan 2015 is to ensure the
provision of inclusive facilities and services that meet the high expectations of
the City’s business, resident, student and visitor communities, aiming for
continuous improvement in the City’s rating in satisfaction and quality of life
surveys. The Local Plan seeks to ensure high quality training and learning
opportunities are accessible to all. City and City fringe residents will develop
the skills needed to enter careers in the City and benefit from the City’s
prosperity.
95. The Strategic Priorities of the emerging City Plan 2040 sets out that the City
Corporation will facilitate significant growth in office development of the highest
quality to meet project economic and employment growth and protecting
existing office floorspace to maintain the City’s role as a world leading financial
and professional services centre and to sustain the City’s strategically important
cluster of commercial activities within the Central Activities Zone; broadening
the City’s appeal by ensuring new office developments deliver flexible, healthy
working environments and meet the needs of different types of businesses
including Small and Medium Enterprises, supporting specialist clusters such as
legal and creative industries and promoting a range of complementary uses;
creating a more vibrant and diverse retail economy; balancing growth with the
protection and enhancement of the City’s unique heritage assets and open
spaces and creating an inclusive, healthier and safer City for everyone.
96. The Strategic priorities of the emerging City Plan 2040 also focus on
maintaining and enhancing the City’s cultural, leisure and recreational offer,
visitor experiences and infrastructure and the City’s evening and weekend
economies to position the Square Mile as a key cultural and leisure destination.
To do so the emerging policies seek to encourage cultural placemaking and
creation of inclusive places contributing to residents, workers and visitors'
experiences; develop cultural, leisure and recreation facilities that offer unique
experiences across the City and during the whole day and week; protect and
enhance existing areas of cultural significance; provide accessible and
inclusive infrastructure and facilities that complement the cultural uses; place
heritage ay the heart of cultural placemaking and create cultural offer that
celebrates the City’s rich history; and encourage public realm improvements to
accommodate cultural events.
97. The above aims are reflected in the ‘Destination City’ vision for the future of the
Square Mile as a world-leading destination for workers, visitors and residents.
This initiative aims to create fun, inclusive and innovative spaces and places
that attract people and investment to the City.
56
Loss of Office Floor Space
98. The proposed development seeks to repurpose the existing historic tunnels
(formerly known as the Kingsway Tunnels) with the main focus being the
provision of a large subterranean heritage exhibition space that would curate
the history of the tunnels. The re-use of the tunnels coupled with high-end
technology is proposed to provide a unique learning experience for the visitors
along with the display of historic findings in a highly interactive environment.
99. A flexible exhibition space would also be provided in the tunnels with a
temporary nature for various exhibitions to take place independently of the
historic exhibition area, as well as the proposed repurposing of the historic bar.
100. As the main cultural spaces would be situated below ground. The development
requires the formation of a ground level entrance that would be appropriate for
this unique cultural use. There are currently two existing entry points to the
tunnels. On Furnival Street (located within the City of London) the building at
number 38-39 forms part of the historic tunnels, it offers 194sqm floorspace and
currently houses a goods shaft that leads to the eastern part of the tunnels,
forming one of the existing access points. A secondary existing access shaft to
the tunnels is situated at 31-33 High Holborn (London Borough of Camden).
This is located beneath residential and commercial accommodation and is
accessed via a narrow alley. The latter access point has very limited flexibility
given the constrained nature of the building/access and is therefore proposed
to work as the secondary entrance to the tunnels development. Therefore, the
principal visitor entrance is proposed to be located on Furnival Street.
101. The tunnels complex that runs along the City and Camden boundaries
measures approximately 7,829 sqm in floorspace which would be restored and
preserved. The proposed submission estimates that the cultural use would
attract approximately two million visitors annually, with a maximum capacity of
750 people being in the tunnels at any hour of a peak day. Because of the
capacity of visitors, the tunnels could accommodate, the building at 38-39
Furnival Street would not currently be able to provide a sufficient floor area for
the required ground floor facilities (reception, lobby, toilets, etc) and for the
provision of a highly accessible ground floor entrance on its own due to the
constricted space. The proposal therefore includes the adjacent building, 40-41
Furnival Street, into the development in order to create larger floorplates and
create the required primary access to the tunnels.
102. The following figure shows the existing ground floor layout of the two buildings
to demonstrate the limitation in floor space at 38-39 Furnival Street and the
additional floor area to be embedded from the inclusion of the adjacent building
into the proposal.
57
Figure 3. Existing Ground Floor Layout Plans
(40-41 Furnival Street left, 38-39 Furnival Street right)
103. No.40-41 Furnival Street forms a late 90s office building of higher scale than
the other buildings on the street and is currently occupied. It offers 1,229 sqm
(GIA) of office space and ancillary floorspace arranged over the basement,
ground and 6 upper floors.
104. The proposed development seeks to demolish the buildings at both 38-39 and
40-41 Furnival Street and redevelop a building with a combined layout. The
new conjoined building would provide ancillary uses (such as staff
accommodation and gift shop) and form the principal entrance to the proposed
cultural attraction to take place in the existing tunnels. This application would
therefore result in the loss of 1,229sqm (GIA) of existing Class E(c) office
floorspace.
105. London Plan Policy E1 supports the increase in current office stocks especially
within the central London office market. The City of London Local Plan 2015
and the Emerging City Plan 2040 promote the delivery of a world class business
city and the protection and provision of office floorspace. Local Plan policies
CS1 and DM1.1 and Emerging City Plan 2040 policies S4 and OF2 seek to
protect existing office accommodation.
106. Local Plan Strategic Policy CS1 and Policy DM 1.1, require applications for loss
of office accommodation to other uses be refused where the site is suitable for
58
long-term viable office use and there are strong economic reasons why the loss
would be inappropriate. Inappropriate losses are measured by any the following
reasons:
prejudicing the primary business function of the City;
jeopardising the future assembly and delivery of large office development
sites;
removing existing stock for which there is demand in the office market or
long
term viable need;
introducing uses that adversely affect the existing beneficial mix of
commercial uses.
107. The supporting text (paragraph 3.1.8) to Local Plan Policy DM1.1 and the Office
Use SPD indicates that proposals for the change from offices will normally be
refused if the building or site is considered suitable for long-term viable office
use. Paragraph 3.1.8 of Policy DM 1.1 however goes on to state that
Exceptionally, the loss of individual office developments to other commercial
or infrastructure uses may be acceptable, where the proposed alternative use
meets the wider objectives of the Local Plan.
108. Local Plan Policy DM1.3 promotes small to medium enterprises in the City and
encourages the continued use of existing small and medium sized units which
meet occupier needs.
109. Local Plan Policy DM1.5 promotes a mix of commercial uses in office
developments that support the city's workers, residents, and enterprises while
also adding to its economy and identity. Supporting text (paragraph 3.1.20) of
the same policy defines complementary uses as retailing, leisure, education
and health facilities and states these should support the prominent office
environment of the City by providing supporting activities and services.
110. Emerging Policies S4 and OF2 of the draft City Plan require the protection of
existing office stock from being lost to other uses where the existing floor space
would be viable in the longer term or where the loss would cause harm to the
primary business function of the City. Paragraph 6.3.9 of the emerging Policy
OF2 states that when a change of use from offices to other complementary
uses which meet the policy priorities of the City Plan is proposed, then a viability
assessment may not be required. The paragraph continues to define
complementary uses as those that meet the needs of City workers, residents
and visitors and help make City buildings much more open and welcoming to
all. The change of use of offices at ground and lower ground levels would also
include the provision of improved vibrancy including active frontages and
permeability. Sustainable development is also a priority to reduce carbon
emissions and retain embodied carbon.
59
111. The Office Use Supplementary Planning Document (SPD) sets out the
evidence required to support the loss of office floorspace. Paragraph 20 of the
SPD states that when a change of use application provides complementary
uses to the City’s business function, the LPA may accept the development
without the need to demonstrate the viability of the office site.
112. Emerging Policies S6 and CV2 promote opportunities for new cultural and
leisure facilities offering unique experiences in the City’s evening and weekend
economies that support the City’s role as a visitor destination. Policy CV2 also
encourages the use of historic buildings for the provision of such uses that
would contribute to the enjoyment, appreciation and understanding of the City’s
heritage in an inclusive, accessible and welcoming for all way.
113. The submitted evidence report for the proposed loss of office considers that the
commercial building at 40-41 Furnival Street, due to its modest scale and
location, makes very limited contribution towards the City's office stock and the
primary business function of the City and would not have the potential for large
office development in the future. However, officers acknowledge that the
building is considered a viable office as it is currently occupied. Policy DM 1.3
(Small and medium sized business units) in particular encourages the
continued use of existing small and medium size units that meet occupier
needs. Despite the strong policy focus on larger office developments in
strategic locations, having a variety of sizes and scales of offices within the City
and in different areas is important for the business function of the City and its
reputation as a global business centre as well as for attracting a diverse
workforce.
114. The existing office, while occupied, is generally not of high quality or located
within a building of particular architectural or historical merit. Given the dated
and somewhat constricted layout of the existing building officers consider that
there is likely a restriction on useability, limited sustainability measures and
inadequate cycle storage or shower facilities. Following the global pandemic
there is greater demand for cycling facilities and buildings with good air
circulation which would therefore likely decrease the desirability of the building.
It is therefore considered that the office would be a poor competitor to other
buildings in better locations.
115. The proposed cultural and visitor use is considered to fall within the definition
of a complementary use to the City’s business function and proposes to offer a
unique cultural experience in accordance with the Emerging Policies S6 and
CV2. While limited Viability Assessment documentation has been submitted as
part of the proposal, the loss of the modest office is to be weighed against the
exceptional re-use of the adjoining heritage asset, the inherent requirement of
60
40-41 Furnival Street for access/ancillary space and the wider economic
benefits the cultural use would bring to the City as a whole.
116. The tunnels have been identified as a non-designated heritage asset due to
their historic value. Their retention and repurpose to provide a cultural exhibition
space, that would be dedicated to being appreciated by visitors through a
playful and joyful interactive learning experience, would be in line with Emerging
Policy CV2. It is noted that the heritage benefits and repurposing of existing
infrastructure have been identified in comments received from members of the
public as a significant and unique benefit of the development.
117. The additional proposed floorspace by utilising 40-41 Furnival Street would
achieve accessibility and fire safety standards by providing the necessary
facilities at ground level such as better circulation space, an increased number
of lift shafts, emergency exits and cycle storage as shown in the figure below,
as well as creating ancillary areas at upper levels such as gift shop, staff
accommodation and MEP storage.
Figure 4. Proposed Ground Floor Plan 38-41 Furnival Street combined
floorspace
118. It is considered that the scheme would help create new jobs and significantly
revitalise the local economy by attracting visitors every year outside working
61
hours, during evenings and weekends, meeting the strategic objectives of the
City in order to sustain and complement its business function. Approximately
85 new full-time jobs are anticipated to be required to function the permanent
exhibition space in addition to extra staff that would be needed for the special
events space focusing on local recruitments. The proposed bar would operate
separately and would therefore employ its own staff. The application has
received 57 letters of support from the public the majority of which point out the
benefits the development would bring to the local economy in an area that has
suffered deprivation and fights to recover from the pandemic. Among them,
Fleet Street Quarter strongly supports the introduction of a much needed visitor
destination to this area. This would provide a transformative revitalisation of the
High Holborn area and as such has also been supported by the Central District
Alliance. Increased footfall by the development has been heavily supported on
that basis.
119. The supporting text in Local Plan Policy DM1.1 (Protection of office
accommodation) confirms that exceptional losses of individual office
developments to other commercial or infrastructure uses may be acceptable,
where the proposed alternative use meets the wider objectives of the Local
Plan. The high-quality, unique cultural use will contribute towards diversifying
the City’s visitor infrastructure, adding vibrancy and activity for seven days per
week and contribute significantly to the achievement of the City Corporation’s
Destination City ambitions and align with the City Corporation’s wider ambitions
for a post-Covid City. Furthermore, as highlighted above, the proposed use
would bring about a wider economic benefit to the City, providing 85 (FTE) local
jobs, up to 2 million visitors to the City per annum and the restoration of a
heritage asset. In this case therefore, while the proposal would reduce the
amount of potentially viable office space, the proposal is considered to fall
within the exceptional category of complimentary uses and as such acceptable
in principle.
120. Whilst the Local Plan 2015 resists the loss of office floorspace, it is considered
the scale of the loss on this site (1,229sqm) would not prejudice the overall
supply of office space in the City, nor prejudice the potential for future site
amalgamation or result in the loss of existing stock for which there is demand
or longer-term viable need.
121. Overall, whilst there would be a loss of existing office floorspace, this would not
have an adverse impact on the overall stock of floorspace in the City or
prejudice the City’s role as an international business and professional centre.
The proposed development would contribute to the support of the City’s
business function offering a unique experience for its workers, residents and
visitors, and add a significant cultural supply to the City’s stock meeting
Destination City’s aspirations. It is therefore identified as complementary use
62
that meets the wider objectives of the Local Plan in accordance with adopted
Policies DM 1.1, DM 1.3, DM1.5 and emerging Policies OF2 and CV2. The loss
of office floorspace at 40-41 Furnival Street is considered acceptable on that
basis.
Cultural Use (Use Class F1 (b) (c))
122. The proposed development seeks to change the use of the existing Kingsway
Tunnels to a cultural and visitor attraction (exhibition space), including a bar.
The tunnels are not currently publicly accessible and are not in use.
123. The site falls within the CAZ and London Plan Policy SD4 outlines that within
this area the unique concentration and diversity of cultural, arts and tourism
functions should be promoted and enhanced.
124. The London Plan Good Growth objectives GG1 and GG5 are considered
applicable to the provision of community and cultural use (Heritage and Cultural
Exhibition) within development proposals.
125. London Plan Policy E10 states that London’s visitor economy and associated
employment should be strengthened by enhancing and extending its
attractions, inclusive access, legibility, visitor experience and management and
supporting infrastructure, particularly to parts of outer London well-connected
by public transport, taking into account the needs of business as well as leisure
visitors.
126. Policy S1 of the London Plan seeks to ensure that the social infrastructure
needs of London’s diverse communities are met.
127. Policy HC5 of the London Plan recognises that the continued growth and
evolution of London’s diverse cultural facilities and creative industries should
be supported.
128. Local Plan Policy CS11 seeks to maintain and enhance the City’s contribution
to London’s world-class cultural status and to enable the City’s communities to
access a range of arts, heritage and cultural experiences, in accordance with
the City Corporation’s Visitor Strategy, by providing, supporting and further
developing a wide range of cultural facilities. The supporting text for Policy
DM11.1 goes on to state that the international reputation and high quality of this
cultural activity are acknowledged as having a critical part to play in the vibrancy
of the working environment of the City.
63
129. Emerging Strategic Policy S6 of the draft City Plan 2040 outlines that the City
of London will support and encourage access to and development of a wide
range of creative and cultural spaces and facilities across the City. Destination
City, the City Corporation’s flagship strategy, seeks to ensure that the City is a
global destination for workers, visitors and residents. It seeks to enhance the
Square Mile’s leisure and cultural offer by creating a sustainable, innovative
and inclusive ecosystem of culture that celebrates its rich history and heritage
and makes it more appealing to visitors as well as the City’s working and
resident communities.
130. Emerging Policy CV2 (Provision of Arts Culture and Visitor Facilities) of the
Draft City Plan 2040 encourages the provision of facilities that meet the needs
of visitors in new cultural developments. In particular by encouraging the
provision of arts, culture and leisure facilities in historic buildings and spaces
where this would contribute to the enjoyment, appreciation and understanding
of the City’s heritage in a way that is inclusive, welcoming and accessible for
all.
131. A Cultural Plan has been prepared by Future City and submitted as part of the
application which sets out the cultural vision, the development’s offer, the
delivery strategy and the future steps. The Plan envisages the activation of the
existing tunnels infrastructure to provide cultural exhibition spaces and
opportunities for programming and partnerships.
132. The proposals do not involve construction in the tunnels. The cultural mapping
has been made following the tunnels layouts and based on the historical
significance of each area. As mentioned earlier in the report, the tunnels were
built in phases and were used for different purposes during historic times. The
first phase (1942-1945) includes the construction of the ‘Streets’ that run
parallel to each other accessed by the former Chancery Lane tube station at
31-33 High Holborn. No.38-39 Furnival Street was built to make way for a goods
lift shaft. Originally built to serve as deep-level shelters but actually used for
‘Citadel’ accommodation housing telecommunications rooms where one of the
first Trans-Atlantic calls were made. A plan of ‘Chancery Lane Deep Tunnels’
is shown below demonstrating the various government departments in 1944.
This area is considered to hold the most important historic interest linked to
World War II period.
64
Figure 5. ‘Chancery Lane Deep Tunnels’ demonstrating the various
government departments in 1944
133. The tunnels were converted in the early 1950s after the Post Office and British
Telecom took their possession, which included the construction of four more
tunnels, known as the ‘Avenues’, on a north-south axis, formed part of the wider
expansion of Britain’s domestic telecommunications network. This area is
considered to be of secondary historic interest.
134. In some parts there are post-war plant and machinery remains associated with
the function and running of the Kingsway Exchange tunnels.
135. The figure below is an extract of the Cultural Plan and shows the defined areas
of the proposed cultural use within the tunnels.
Figure 6. Cultural Plan key showing areas in the tunnels
65
136. A History & Heritage experience would reside in the ‘Streets’ marked as the
permanent exhibition space. The site has a historical significance dated to
WWII and subsequent historic times which the proposed scheme seeks to
embrace by repurposing the existing infrastructure and remains. This space
would curate the history of the site through a historic timeline by displaying the
retained and restored telecommunications equipment alongside other findings
and historical assets, engaging visitors in their exploration. The narratives take
place at the construction of the tunnels, in the 1940s, and go on to their
influence on wider historical events in London including WWII and the Cold War
in connection with the role of the tunnels during that timeline and their use as a
telecommunications centre for British Telecom in the 1980s. Part of the Streets
may be used for medium term exhibitions on associated themes such as James
Bond, a theme deriving from Ian Fleming’s reference to the tunnels in his first
book of the infamous UK secret agent.
137. The temporary/flexible Cultural Exhibition space would take place in the
‘Avenues’ and provide a ‘black box’ space, as mentioned in the Cultural Plan,
which would offer an adaptable space for various cultural programmes.
Technological support equipment, such as curved digital screens and
interactive systems, could be installed to support future potential programmes.
138. The floorspace allocated for cultural uses is a total 3,713 sqm. The permanent
Heritage Exhibition would reside 53% of that area leaving 47% to be covered
by the flexible Cultural Exhibition.
139. The main entrance to both exhibition spaces would be at ground level through
a new building at 38-41 Furnival Street. The ground floor serves as a check-in
point and waiting area until the visitors are taken to the tunnels through a round
lift shaft.
140. The following diagram shows the proposed indicative visitor route in the
tunnels, starting from the lift shaft access point and following the heritage trail
towards the ‘South’ and the ‘North’ ‘Streets’ and back to the access point.
Similarly, a shorter indicative trail is marked for the temporary exhibition area in
the three ‘Avenues’.
66
Figure 7. Diagram showing Visitor Heritage Trail & Exhibitions
circulation routes
141. Almost the entirety of the development serves the cultural uses, including the
upper floors of Furnival Street buildings which provide ancillary space for the
cultural use. The first and second floors would be used for ancillary retail to
house a gift shop. Level three would house MEP equipment serving the tunnels
and level four would be used for staff accommodation offering ancillary office
space, toilet facilities, lockers and outdoor amenity space.
142. A licensed bar would repurpose the original bar built by British Telecom in the
1980s retaining its historic elements. It is suggested to form part of the cultural
experience within the tunnels, however, it would function independently from
the permanent and temporary exhibition spaces and would be accessed via
Fulwood Place, the secondary entrance located in the London Borough of
Camden.
143. The proposed development seeks to provide a visitor and cultural attraction
(Use Class F1(b)(c)) and bar (Sui Generis) within the existing vacant
subterranean Kingsway Tunnels. The level of historical significance the tunnels
hold is so unique that is considered unlikely to find another site of this nature
that would have the potential to make a cultural offer equal to the one of the
proposed development. The proposed provision of a culture and leisure facility
within the various historic buildings and spaces would contribute to the
enjoyment, appreciation and understanding of the City’s heritage. It would
maintain and enhance the City’s contribution to London’s world-class cultural
status and would contribute significantly to the City’s ambitions for Destination
City and post-Covid recovery. The proposed facilities would not only contribute
to ensuring the City becomes a key leisure destination for visitors but would
67
also maintain and enhance its position as a global business centre, by providing
cultural/leisure experiences for people living and working in and around the
Square Mile. The proposed permanent Heritage Experience would directly
reference the historic tapestry of the City and the flexible exhibition spaces
would provide a unique and distinctive space for cultural events within the
Square Mile. Finally, the proposed uses would contribute to the balance and
mix of uses in the immediate locality, which is comprised of commercial,
educational, residential and office uses.
144. The Cultural Plan and Socio-Economic Assessment suggest that the proposed
development aims to attract up to two million visitors annually, boosting national
and international tourism, with an expectation to generate over 100 jobs and
increase local expenditure. There is a series of benefits brought forward
through the scheme that focus on inclusion and equal opportunities. These
include free school visits, opportunities for local jobs and apprentices, training
opportunities, providing spaces designed for a greater group of people, and co-
curation / co-creation programmes to engage the local community in shaping
the exhibition areas. The development scheme makes use of an existing
infrastructure that would otherwise stay untapped. It does that by creating a
space that focuses on their legacy and embraces their history in a unique way
with a commitment to invest millions of pounds to deliver that vision.
145. It should be noted that during the application’s public consultation, 57 letters of
support have been received, strongly supporting the provision of a touristic
attraction with the characteristics of the proposed scheme in an area that has
been battling to recover from the pandemic. Notwithstanding that, none of the
overall 24 letters of objection raised an objection to the retention and restoration
of the existing historic tunnels.
146. A Section 106 obligation would be required to secure the provision of the
proposed cultural spaces and public benefits brought forward, including a
Cultural Implementation Strategy and Operational Management Plan, and
securing a Cultural Operator or future Partners focusing on inclusive
procurement programmes. Officers consider these obligations to be necessary
for the delivery of the proposed cultural use.
147. The proposed cultural spaces would contribute to the cultural and community
offer in this part of the City. The scheme would align with the City’s ambitions
and direction of travel set out in the recent Destination City which seeks to
ensure that the City is a compelling, seven day a week destination. The
proposed development is therefore considered to be compliant with London
Plan Policies SD4, GG1, GG5, E10, HC5, Local Plan 2015 policies CS11,
DM11.1 and Emerging City Plan 2040 policies S6 and CV2.
68
Conclusion of proposed uses
148. For the reason stated above, it is considered that the proposed development
would contribute to the support of the City’s business function offering a unique
experience for its workers, residents and visitors, and add a significant cultural
supply to the City’s stock meeting Destination City’s aspirations. There are key
heritage and social benefits brought forward in the scheme and is considered
to constitute a positive development that meets the aims of policies in the Local
Plan and London Plan and meets key strategic objectives and emerging
policies of the Draft City Plan 2040. The proposed development is therefore
considered to be compliant with London Plan Policies SD4, GG1, GG5, E10,
HC5, Local Plan 2015 policies CS11, DM11.1 and Emerging City Plan 2040
policies S6 and CV2.
Design and Heritage
Policy Context
149. The relevant local policies for consideration are DM3.2, CS10, DM10.1,
DM10.3, DM10.4, DM10.8, CS11, CS12, DM12.1 and DM12.2 of the Local Plan
policies and S8, DE2 of S11 of the emerging City Plan, and London Plan
policies D3, D5, D8, HC1. HC5, HC6, GG2 and GG5.
Existing Site and Context
150. No.38-41 Furnival Street is located at the northern end of Furnival Street and
within the Chancery Lane Conservation Area. The existing site is composed of
two distinct buildings, No.40-41 is a modern office building and No.38-39 is an
existing entrance to the Kingsway Tunnels and has been identified as a non-
designated heritage asset due to its historic and rarity value.
151. Furnival Street is a narrow street which runs north-south connecting Cursitor
Street and Holborn. The townscape of the locality is of a modest scale, Furnival
Street is generally constructed of four and five-storey buildings with varied
roofscapes. The scale and massing of 39-41 Furnival Street sit comfortably into
the existing streetscape however although 38-39 Furnival Street is slightly
smaller in scale than the surrounding buildings. The architecture and
appearance of Furnival Street is a narrow enclosed street and dominated by
the use of brick and uniform gridded façades and a fine urban grain. No.38-39
is a positive and unusual contrast to the surrounding buildings, its simple
industrial brick façade hinting to the wider tunnel network below ground. The
architecture of No.40-41 dating from the 1990s is less successful due to the
dominating glazed bow frontage which breaks the uniformity of the streetscape.
69
152. The existing ground floor frontages have little street presence. At No.40-41 the
frontage is formed by an office lobby which has a lack of façade articulation and
limited street activation. No.38-39 is dominated by black-painted solid doors.
Overall, the buildings underperform for a streetscape which is characterised by
numerous openings and high levels of articulation.
Height/Bulk and Massing of No.38-41 Furnival Street
153. The disposition of the finial massing and bulk has followed a design-led
approach considering local townscape views, daylight assessment and
relationship with neighbouring buildings and access requirements to the
underground network. The massing and façade design has also been designed
around the delivery of optimal microclimatic conditions, including daylight,
sunlight and overshadowing to the building and its neighbours. With respect to
massing, height and façade treatment, the development would demolish the
entirety of No.38-39 and No.40-41 Furnival Street, and the proposed massing
and height of the new structures would largely recreate the existing building
proportions. The proposal would retain the appearance of two buildings,
maintaining the urban grain of the East side of Furnival Street. The changes in
height would be imperceptible and only experienced in oblique views.
154. The proposal would be formed of three levels of basement covering the extent
of the site. The proposed massing of No.38-39 would use the full extent of the
site and would slightly increase in height to accommodate ground plus three
storeys with a rooftop amenity, increasing the overall height by 3.4m. The
balustrading for the rooftop amenity would be set in from the main building
façade reducing its visual impact in the oblique views along Furnival Street, the
top height of the balustrading would be +36.10m AOD. The proposed massing
of No.40-41 would be formed of four storeys above ground plus a setback plant
enclosure at roof level, reaching +41.75m AOD. The massing would use the full
extent of the site footprint however it would be set back at the ground floor to
allow for a covered canopy over the entrance. Widening the public realm around
the entrance would reduce the impact of the increased footfall associated with
the new visitor attraction. The massing at the rear of No.38-41 has been
designed to ensure its visual impact on the neighbouring building has been
minimised by sloping the massing in the middle of the proposal from level 03
and above.
155. The proposal would positively address the street by introducing curved corners
to the body of the building reducing the visual appearance of the currently
unsuccessful blank flank wall which is visible in local townscape views looking
north and south down Furnival Street. The proposed massing would improve
70
these townscape views by reducing the furthest extent of the massing into the
street by 300mm and pulling the building line back at the ground floor to align
with No.14-18 Holborn.
Architecture and Materiality of No.38-41 Furnival Street
156. The primary frontage of No.40-41 would be a bold addition to the townscape.
The architectural treatment would express the new function of the building while
maintaining the traditional proportions of the street through its expression of
base, middle and top. While the façade of No.38-39 would reimagine the
existing brick façade celebrating the unique history of the site.
157. The proposal allows for a connected single internal floorplate to be achieved
without the disconnected inflexibility of joining the existing buildings. The two
blocks would read as distinct but connected buildings, tied together by a
consistent ground floor frontage and industrial architectural language and
materiality.
158. The development would transform the existing ground floor experience to
Furnival Street introducing a defined, active base of a human scale expressed
as a single height with a recessed covered entrance associated with the main
entrance. The site is constrained with limited frontage and through a design-led
approach the proposal has provided a high level of activation alongside
providing the required servicing entrance and fire escapes. The activation is
created through increased levels of glazing and the primary use of the ground
floor as the entrance to the tunnels. The servicing doors would be integrated
into the façade minimising their impact on the appearance of the building in line
with Local Plan policy DM10.1 and emerging City Plan 2040 policy DE2.
159. The primary entrance would be distinctive, and publicly located parallel to the
street within the 1500mm setback. The soffit treatment, of textured reflective
stainless steel would run from outside into the internal reception creating a
welcoming and visually interesting primary entrance. The entrance including
the soffit treatment would be designed to ensure that the highest standards of
accessibility and inclusivity are achieved in line with Local Plan policy DM10.8
and emerging City Plan 2040 policy DE2. The detailed design would be secured
via condition.
160. Materiality has been a central consideration. The building would have a high-
quality industrial appearance, with the rebuilding of the brick façade at No.38-
39 and the use of glass blocks at No.40-41. The materiality has been developed
to celebrate the history of the site while also providing a high level of natural
light into the building, creating a transition point for visitors between the
subterranean tunnels and the outside. The proposed materiality including
71
colour, design details and intricacies would be secured through conditions
including samples and bays studies.
161. The use of basalt cladding across the base of No.38-41 would provide a
consistent language across the two buildings and ensure that a high-quality
finish is achieved while ensuring that there is sufficient robustness for a primary
entrance with sufficient footfall.
162. The upper storeys of No.38-39 Furnival Street would celebrate the existing
building located on the site maintaining the unique industrial language by
reinstating the existing brick façade and incorporating the existing concrete
ventilation panel. The brick façade would be framed with black louvred panels
which would be setback from the brick elevation by 400mm creating a clear
hierarchy to the façade. No.38-39 originally had a metal crane, which has been
lost a would be replicated and reinstated.
163. The upper floors of No.40-41 would be characterised by the bold, simple and
elegant glass block four-storey façade, a modern interpretation of the industrial
language found at the existing No.38-39 Furnival Street. The glass block façade
was developed following an extensive pre-application process which looked to
balance the need to provide a high level of ventilation to the third-floor plant
space alongside providing adequate light levels to the ancillary office floor on
level 04. The bold façade would provide visual interest and express the public
uses without being overwhelming. The surrounding townscape is of a varied
character and the independence of the architectural approach and materiality
would add to the surrounding character.
164. The top floor of the No.38-39 would be the rooftop amenity for the tunnel’s
supporting workforce. The balustrading would be set back from the façade line
reducing the visual impact on local townscape views. The terrace has been
designed in line with the City of London Corporation Preventing Suicides in High
Rise Buildings and Structures planning advice note. The balustrading of the
terraces would be a minimum of 1.4m high and have a planted buffer zone
located in front of the balustrading line, creating a natural deterrent. Further
detail regarding suicide prevention would be secured via condition.
165. The outdoor amenity and urban greening of the terrace would provide visual
and physical amenity for the tunnel workforce supporting their mental health
and wellbeing in line with Local Plan policy DM10.3 and emerging City Plan
2040 policy DE2.
166. The glass block façade of No.40-41 Furnival would accommodate integrated
removable façade panels to allow for plant replacement in line with Local Plan
72
policy DM10.1 and emerging City Plan 2040 policy DE2. The junction detailing
and materiality would be secured by condition.
167. The roof top plant equipment and lift overruns would be screened by the plant
screen which is set back from the façade line reducing its visual impact on local
townscape views. The proposed plant and building services equipment would
be fully screened from view and integrated into the design of the building in line
with Local Plan policy DM 10.1, greening would be optimised where possible in
line with Local Plan Policy DM10.2 and emerging City Plan 2040 policy DE2.
Further details are required and would be secured via condition including the
5th elevation.
168. Appropriate lighting, in accordance with Local Plan Policy DM 10.1, would
deliver a sensitive and co-ordinated lighting strategy integrated into the overall
design, minimising light pollution, respecting the historic context, responding to
public safety and enhancing the unique character of the City by night.
Irrespective of the approved drawings, a detailed Lighting Strategy would be
subject to conditions to ensure final detail, including form, quantum, scale,
uniformity, colour temperature and intensity are delivered in a sensitive manner
in accordance with guidance in the City Lighting Strategy. The proposed public
realm lighting strategy would provide low-level illumination to architectural
features, to enhance the pedestrian experience, improve safety and protect the
existing surrounding residential amenity.
169. Cycle parking facilities for the Tunnel workforce would be accessed via an
entrance on Furnival Street. The short-stay cycle parking would be provided in
public realm. The active edges would improve the pedestrian experience and
cycle facilities would encourage active travel walking and cycling. The
proposals are acceptable and allow for active travel and comply with Local Plan
policy DM10.1 and emerging City Plan 2040 DE2.
170. Irrespective of the approved drawings, full details of the ground floor frontages,
design and materiality of the public realm improvements, and wayfinding
strategy are reserved for condition to ensure these are well-detailed and are
useable. The development has had regard for Local Plan Policy DM 3.2 and
the Mayors Public London Charter promoting a safe, inclusive and welcoming
environment.
171. A high-quality signage strategy and way finding for the proposal would be
required and would be secured via condition.
Conclusion of Architecture and Massing of No.38-41 Furnival Street
73
172. The proposals would successfully integrate into the modest scale of Furnival
Street and would significantly enhance the streetscape by providing increased
active frontage. The distinctive sense of separate buildings, materials, the
celebration of industrial heritage and intended quality would introduce a well-
considered, refined, neighbourly architectural set piece. The bold architectural
expression would reflect the unique cultural use of the buildings and the
subterrane tunnel network. The development is sensitive to townscape contexts
at macro and local scales. The proposal would optimise the use of land, whilst
significantly improving the buildings’ interface with their surroundings.
173. The development would create a high-quality culture-led commercial
development utilising the existing heritage of the site. The proposals align with
Local Plan Policies CS10, CS11 and CS12, Emerging City Plan 2040 Policy
DE2 and London Plan Polices D3, D5, HC5 and HC6. It is considered that the
scheme would represent ‘Good Growth’ by design, in accordance with the
London Plan Good Growth objectives GG2 specifically GG2E: understand what
is valued about existing places and use this as a catalyst for growth, renewal,
and place-making, strengthening London’s distinct and varied character and
GG5 specifically GG5F: promote and support London’s rich heritage and
cultural assets, and its role as a 24-hour city. The proposals would also align
with the mandate of Destination City by supporting London as a 24-hour city
and creating a new cultural offering in this corner of the City of London
174. An informative for architect retention is proposed.
175. Overall, the proposals accord with the City’s broader visions to deliver
outstanding places, as part of ‘Destination City’, ‘City Recharged’ (2020),
‘Future City’ (2021) and ‘Culture and Commerce’ (2021).
176. The proposals are in overall general conformity with Local Plan Strategic
Policies CS10 (Design), London Plan Policies D3/D8 and emerging City Plan
2040 Strategic Policy S8 (Design).
Heritage Impacts
Direct Impacts Chancery Lane Conservation Area
Significance:
177. The Chancery Lane Conservation Area and its buildings contain considerable
historic character and appearance to convey the area’s historical ethos through
their variety and quality.
74
178. The characteristics which contribute to the special interest of the Chancery
Lane Conservation Area can be summarised as follows:
An exceptional span of building ages and styles, resulting in a townscape of
arresting contrasts;
Significant historic associations with the legal profession, with origins as a
centre for medieval legal administration;
The collegiate surroundings of Staple Inn and Barnard’s Inn, which
incorporate rare secular medieval survivals;
A historic association with educational establishments that has persisted to
the present time (e.g. the Inns of Court, Birkbeck College, King’s College
London);
The site of the Knights Templars’ first precinct and church in London (at
Southampton Buildings);
A well-preserved and easily legible historic street network;
Monumental 19th century Victorian public buildings in a range of styles;
One important early act of conservation (Staple Inn north range) and several
buildings of varying periods associated with a single company’s patronage
(Prudential Assurance Co.);
Well-considered 21st century insertions into a historic context.
179. No.38-39 is located adjacent to No.35 and No.36-37 which both offer examples
of 20
th
century executions of traditional forms. It is seen to have a positive
contribution to the conservation area and is noted within the CA Character
Summary and Management Strategy SPD as offering a strikingly industrial
aesthetic to the street, contrasting with the refined architecture of No.10
opposite. The key features which contribute to the industrial aesthetic as the
plain brick elevation, iron crane and large ventilation grille.
180. The character of No.40-41 is out of keeping with the prevailing architectural
aesthetic of Furnival Street due to its large bow front and is not deemed to be
a positive contributor to the conservation area.
Direct Impact:
181. It is noted that a number of objections have been raised regarding the impacted
of the proposal on the character of the Chancery Lane Conservation Area
however this is in contradiction with officers Appraisal and further discussion
regarding the impact of the proposals is set out below.
182. No objection from Historic England or Conservation Area Advisory Committee
(CAAC) have been raised regarding the impact on the Conservation Area.
75
183. No.38-39 has been identified as having a positive contribution to the
conservation area due to its industrial past and appearance and historic
associations as citadel accommodation. Due to the narrow grain of the street,
it is acknowledged that it is primarily the front façade of No.38-39 which
provides the positive contribution to the conservation area. The proposed works
at No.38-39 would comply with Local Plan policy DM12.2 and emerging City
Plan 2040 policy HE1 as the positive contributors of the existing building would
be reinstated within the proposed works, specifically the brick façade, concrete
grille and reconstruction of the metal crane.
184. No.40-41 Furnival Street would be replaced by a high-quality glass block façade
which would follow the existing datums set by No.14-18 Holborn. The
architectural language would create a modern industrial aesthetic at No.40-41,
emphasising the unknown heritage asset at No.38-39 and would create a
positive addition to the streetscape. Adding to the existing key characteristic of
the conservation through further addition of contrast and well-considered 21st
century insertions in line with Local Plan Policy DM12.2.
185. The view down Furnival Street from Holborn is currently framed by the high-
quality façade of No.10 Furnival Street and the blank red brick flank wall of
No.40 Furnival Street. The proposed works would make a positive contribution
to this view due to the activation of the flank elevation which would be achieved
through the introduction of curved corners and the continuity of the materiality
around corners.
186. The site appears in one local townscape view which has been highlighted in the
Chancery Lane CA Character Summary & Management Strategy SPD as
having a strong contribution to the character of the conservation area, the view
is taken from the junction of Cursitor Street looking north along Furnival Street.
The existing view is characterised by buff brick buildings to the west and a
mixture of red brick and stone to the east, terminating the street is the Grade II*
Prudential Assurance Building. The view would remain largely unchanged due
to the site being located at a significant distance, however, due to the change
in the façade line at No.40-41 Furnival Street the view would be opened up to
allow further appreciation of Prudential Assurance Building.
187. Where the proposal would be visible from higher level windows, officers are
satisfied that the designs would be of high quality, due to its materiality and
greening, providing a high level of architectural and visual interest.
188. On balance, there is sufficient quality within the architecture of the proposal, to
consider the impact on local townscape is acceptable, given that proposals are
of high quality and suitable massing which would be well articulated, and would
respond to its local context forming part of an interesting, varied, streetscape
76
along Furnival Street. The proposal would result in total demolition of No.38-41
Furnival Street however this would be mitigated by the reinstatement of the
brick façade, concrete grill and metal crane at No.38-39, which would
successfully promote the industrial heritage of the site.
Direct Impacts - Non-Designated Heritage Asset
189. Non-designated heritage assets are buildings, monuments, sites, places,
areas, or landscapes identified by plan-making bodies as having a degree of
heritage significance meriting consideration in planning decisions, but which do
not meet the criteria for designated heritage assets. The guidance in Historic
England’s Advice Note 7: Local Heritage Listing has been used to assess
whether the buildings on the site have the potential for non-designated heritage
asset status. The Kingsway Exchange Tunnels were identified to have such
status as a result of that scoping exercise.
Kingsway Exchange Tunnels
Significance:
190. Asset Type and Rarity: Only eight deep-level tunnels were built as part of the
air shelter programme and the majority of these are located in predominantly
residential areas, except for Chancery Lane and Goodge Street which are
located in predominantly commercial and institutional areas of central London.
The entrance located at No.38-39 Furnival Street is a rare example of industrial
architecture in the City of London, this is represented in the simple brick façade
with concrete ventilation panels and the metal crane which has been lost.
191. Age: The Kingsway Exchange Tunnels were completed in 1942 alongside the
entrance at Fulwood Place and the entrance at No.38-39 Furnival Street was
completed later in 1952. The age of the building does not relate to established
local characteristics or building traditions and does not contribute to the interest
of the Kingsway Tunnels.
192. Architectural and Artistic Interest: The tunnels network was constructed in a
similar way to the underground train network and is of a standard construction
methods. The purpose-built entrance at No.38-39 Furnival Street has a
utilitarian façade which is indicative of its function while its materiality helps
contextualise it into the surrounding streetscape. The intrinsic design and
aesthetic value of the heritage asset do not relate to the local vernacular and
the materials and construction where standard for the time period. The
Kingsway Tunnels do not have any intrinsic architectural or artistic interest.
77
193. Group Value: The Kingsway Tunnels does not have any clear design
relationship with the surrounding development, with the majority of the asset
hidden underground. The above ground structure at No.38-39 Furnival Street
is part of the 20
th
century piecemeal contemporary transformation of Holborn
Kingsway Tunnels does not have any group value with the surrounding
development.
194. Archaeological Interest: The building does not provide evidence of past human
activity in the locality and below ground archaeology is considered in detail in
the next section of the report.
195. Historic Interest: The Kingsway Exchange Tunnels were completed in 1942 and
originated as the Chancery Lane deep-level shelter one of eight deep-level air
raid shelters constructed during the Second World War to provide shelter to
Londoners during aerial bombing attacks. The structure and arrangement of the
Chancery Lane deep-level shelter was standard compared to the other seven
constructed. It comprises two principal tunnels, which run in parallel and are
connected by cross passages. The Chancery Lane deep-level shelter was
never used for civilian shelter and was instead converted to ‘Citadel’
accommodation in 1944. At this time the tunnels were adapted to accommodate
a reserve government headquarters in case of invasion or equivalent
emergency. In 1949 the General Post Office took over the tunnels for use as a
telephone exchange and works began at the beginning of the 1950s, in
complete secrecy under emergency powers, to extend the tunnels through the
construction of four large-diameter north-south tunnels, known as the avenues,
these were built to house the automatic switching equipment. It was at this time
that the building and goods lift at 38-39 Furnival Street was constructed. Its
historical uses, although no longer the building’s current use, adds to the
historic significance of the tunnels. The subterranean network of tunnels still
retains many features associated with their use as a citadel accommodation
and subsequent telephone exchange including a canteen, bar, sleeping
chambers and mechanical equipment. The site was also the location of the
UK’s termination point for TAT-1, the first transatlantic telephone cable in 1956.
Which acted as the ‘hotline’ between Washington and Moscow during the
Cuban Missile Crisis. The country's first radio paging terminal was also installed
on this site in the 1970s. The Kingsway Tunnels have significant historic value.
196. Landmark Status: There are no identifiable communal or especially striking
aesthetic values which make the Kingsway Tunnels stand out in the local scene
as much of the asset is formed of subterrane tunnels with limited above ground
presence. The architecture of No.38-39 Furnival was purposely designed to be
unobtrusive and recessive, so it is not considered to possess landmark status.
78
197. The Kingsway Exchange Tunnels have been identified as a non-designated
heritage asset, and the significance of the Kingsway Exchange Tunnels
primarily arises from its rarity and historic interest as a deep-level air raid
shelter, citadel accommodation and telephone exchange. The above-ground
entrance elements are minimal parts of this much larger complex and are not
representative of the extensive subterranean space and are of limited interest.
The rarity and historic interest are primarily associated with the subterranean
tunnel network.
Impact:
198. The proposal, as described previously, would result in the loss of some historic
fabric, and changes to the above-ground structures at 30-33 High Holborn and
total demolition of No.38-39 Furnival Street to be replaced by a reconstructed
brick façade with additional massing and an increase in overall height.
199. The proposals would result in a demolition of historic fabric to No.38-39 Furnival
Street, with the complete demolition of the above-ground structure and the
widening of the goods lift. The new proposal would dismantle the existing brick
façade and concrete vent and reintegrate them into the new façade. The
original crane which has been lost would be reinstated. The proposal would
create a modern reinterpretation of the existing building and the industrial
identity of the building would be maintained and emphasised by the new
building at No.40-41 Furnival Street. The works would comply with best practice
guidelines regarding cleaning and deconstruction and a complete methodology
would be secured via condition.
200. The works to the subterranean tunnel network would result in a minor loss and
alteration to the historic fabric associated with the refurbishment works. The
works associated with tunnels structures would be minimal and primarily
associated with the remove of the asbestos and works to the access shafts
which is required to ensure safe and inclusive access down into the tunnels.
The form and structure of the tunnels would be maintained, and key features of
the tunnels would be retained including the reinstatement of the deepest bar in
UK and creating a permanent exhibition with the surviving telecom’s equipment,
including the trunk exchange, generators and main distribution frame. The
proposed works would allow for the tunnel network to be opened up to the public
and allow for this currently unknown heritage asset to be enjoyed by a wide
public audience.
201. The proposed works to the Kingsway tunnels have been considered in line with
paragraph 209 of the NPPF regarding the harm or loss of a non-designated
heritage asset. The demolition of No.38-39 Furnival Street and reconstruction
of the brick façade would result in loss of part of the non-designated heritage
79
asset but on balance this would not diminish the overall significance of the
heritage asset due to limited level of demolition in regard to the entire network
of tunnels, and the continued expression of the tunnels above ground through
the use of simple industrial architecture. Overall, officers consider that the
proposed designs for the Kingsway Tunnels would improve the accessibility
and visibility of this currently unknown heritage asset to a wide public audience
without distracting from its historical and rarity value in line with London Plan
Policy HC1, Local Plan Policy CS12 and Emerging City Plan 2040 Policy S11.
202. In line with paragraph 210 of the NPPF, a condition is recommended to be
secured via Section 106, requiring a Cultural Operator to be secured prior to
any demolition works. Officers consider this as a necessary condition to ensure
the partial loss of the non-designated heritage asset would occur only when the
operation of the proposed cultural development would be secured.
Indirect Impacts:
No.25 Southampton Buildings - Grade II*
Significance:
203. Library and Offices of 1890-1912 by the Office of Works’ principal architect, Sir
John Taylor. The present complex also incorporates three bays of the elevation
of an earlier structure, Staple Inn Chambers, which was designed and built in
1842-43 for the Taxing Masters in Chancery by the London-based architects
Wigg and Pownall. Architecturally the buildings are of considerable interest: the
complex is formed of six distinct blocks with different architectural treatments.
The principal architectural interest of the building lies in the surviving interior
spaces, such as the atrium Reading Room with two gallery floors with
decorative ironwork and Corinthian columns. Further interest is derived from
the building facades which display handsome Victorian and Edwardian
architectural detailing. The Furnival Street and Southampton Buildings façades
are particularly elaborate in their architectural detailing and make a positive
contribution to the historic commercial character of Holborn. Significant historic
interest is also derived from its function as the reading room and offices for the
Patent Office, a government body established in 1852 to grant patents,
trademarks and design rights.
Contribution of Setting:
204. The buildings are located within a dense network of narrow streets and squares
with frontages to Furnival Street, Took’s Court, Southampton Buildings and the
gardens associated with the listed Staple Inn Building. The surrounding area is
80
characterised by large institutional and commercial premises, such as the Inn
of Court and the setting contributes to the understanding of its historical interest
as a Patent Office and Library. In the 19th century the commercial character of
the area developed with the construction of large-scale office buildings with
impressive street frontages. This is illustrated by the former Patent Office, the
Public Record Office to the south on Chancery Lane (also by Sir Henry Tanner)
and the Prudential Assurance offices to the north on High Holborn. There has
been piecemeal redevelopment throughout Furnival Street and the surrounding
area that has eroded the historic character of the area; however, these are
generally respectful in scale and function.
Impact:
205. No.38-41 Furnival Street is located to the west of the former Patent Office on
the opposing side of Furnival Street, the proposals would amount to change in
a neutral element of its setting. The proposals would be seen together in the
kinetic experience of Furnival Street however both would only be glimpsed in
oblique views. The changes to the façade line of No 40-41 would pull the
massing away from the listed building. Coupled with the setting back of the
upper level of No.40-41, the overall effect would be a distinctive and deferential
new volume that would not appear to dominate the listed building or challenge
it in these views. Accordingly, the proposals would preserve the setting and
significance of the listed building and the ability to appreciate it.
Prudential Assurance Building- Grade II*
Significance:
206. The office building was constructed between 1885 and 1901 to designs by
Alfred Waterhouse. In 1930-32, the building was altered and extended by EM
Joseph. The building is Gothic Revival in style and constructed in a distinct
combination of granite, red brick and red terracotta. The building occupies an
entire urban block within Waterhouse Square, with its principal façade to High
Holborn. The building has a complex floor plan with an interconnected series of
courtyards within the block. The Prudential offices occupy the former site of
Furnival’s Inn, one of Holborn’s Inns of Court, demolished in 1897.
207. The office building has a historical interest as the headquarters of the Prudential
Assurance, Investment and Loan Association, founded in 1848. The building
was extended over several years and designed to reflect the prestige of the
company. The building has further associations with architect Alfred
Waterhouse, who was responsible for well-known works such as the Natural
History Museum and Eaton Hall. The architectural interest of the building
derives from its imposing street presence on High Holborn and its high level of
81
Gothic detailing. The building is a fine example of purpose-built commercial
office architecture, designed to reflect the values of the company it housed. The
building has strong national associations with other Prudential Assurance
offices, demonstrating a national company identity.
Contribution of setting:
208. The setting of the Prudential Office building contributes positively to its
significance in its visual and spatial relationship with other large commercial
and institutional sites on and around High Holborn. The Prudential Office
building holds a prominent position on Holborn and the primary façade can be
appreciated in its entirety. There are fragments of the historic streetscape that
once characterised this commercial centre on the south side of High Holborn,
which contribute to an understanding of the development of Holborn in the late
19th century. To the east and west of the listed building, there is modern
commercial development of a contrasting style and materiality, which detract
from the architectural and historic interest of the building.
Impact:
209. There is minimal intervisibility between the listed building and No.38-41 Furnival
Street. The proposals would be seen in views of the listed building looking north
along Furnival Street, this would be a kinetic experience and the proposal would
only be glimpsed in oblique views. The changes to the façade line of No.40-41
would pull the massing back and open up the view towards the listed building.
Coupled with the setting back of the upper level of No.40-41 would be a
distinctive and deferential new volume that would not appear to dominate the
listed building or challenge it in these views. The site is a peripheral element in
the wider setting of the building and the proposals would preserve the setting
and significance of the listed building and the ability to appreciate it.
No.32 & 33 Furnival Street Grade II
Significance:
210. A pair of early 18
th
century townhouses of three to four storeys over basement.
The buildings are typically Georgian in style and proportion, with architrave
windows, string courses, parapet roofline and door-hoods. The buildings have
architectural interest as a rare example of 18th century domestic development
in central London. The buildings have historic interest as an illustration of the
history of Holborn which developed as a residential suburb to the city before it
declined in popularity in the 19th century and became predominantly
institutional and commercial in character. The townhouses derive group value
from one another through their historic and visual association.
82
Contribution of setting:
211. The setting of the townhouses contributes positively to their interest, located in
the identifiable historic street pattern of Furnival Street and the surrounding
area, and the visual relationship with No. 10 on the opposite side of Furnival
Street. Furnival Street has undergone piecemeal redevelopment, meaning that
the neighbouring buildings to the listed townhouses are modern constructions.
These vary in architectural quality but overall respect the narrow plot size of the
historic development.
Impact:
212. No.38-41 Furnival Street is separated from the listed buildings by intervening
development. They share a wider visual relationship in the kinetic experience
of views looking north or south along Furnival Street however both would only
be glimpsed in oblique views. Accordingly, the proposals would preserve the
setting and significance of the listed building and the ability to appreciate it.
Indirect Impacts Chancery Lane Conservation Area
Significance:
213. The significance of the Conservation Area lies in its historic association with the
legal profession and educational establishments that have persisted to the
present time, Inns of Court, Birkbeck College, King’s College London. The
architectural character of the conservation area covers an exceptional span of
ages and styles resulting in a townscape of arresting contrast. The
Conservation Area is bound by busy arterial roads, Holborn and Chancery Lane
but vastly made up of well-preserved narrow network historic streets.
Setting:
214. The conservation area is surrounded by a varied and diverse character: to the
East, large scale modern commercial buildings, to the South the diverse
character of commercial buildings associated with the Fleet Street
Conservation; to the West is the Bloomsburg Conservation Area characterised
by low rise buildings around formal landscape squares; to the North is the
Prudential Assurance Building located in the Hatton Garden Conservation
Area.
Impact:
83
215. The indirect impacts on the Chancery Lane Conservation Area derive from the
above ground works associated at Fulwood Place within the London Borough
of Camden. There would be limited intervisibility with the Chancery Lane
Conservation Area and the works are deemed to have no impact on the
Conservation Area.
Wider Heritage Impacts
216. The definition of setting is the extent to which an asset is ‘experienced,’ which
is not geographically set and can change over time, relating to more than just
a direct visual influence. Given the dense central London location, the site is
potentially within the setting of an enormous amount of heritage assets, and it
would be disproportionate to assess them all. As part of a scoping exercise, this
assessment is in accordance with paragraph 200 of the NPPF and is deemed
proportionate and no more than is sufficient to understand the potential impact
of the proposal on its significance. In accordance with paragraph 201 a number
of potentially affected assets were scoped, accounting for their significance and
contribution of setting to that significance. Additional assets assessed include:
No.4, 5 and 6 Staple Inn (Grade I)
337 and 338, High Holborn (Grade II*)
No. 9 and 10 Staple Inn (Grade II)
Staple Inn Hall (Grade II)
No. 7 and 8 Staple Inn (Grade II)
The Institute of Actuaries (Grade II)
Staple Inn North and South Buildings (Grade II)
Mercer’s School Hall and Building Adjoining (Grade II*)
Barnard’s Inn Hall (Schedule Monument)
Hatton Garden Conservation Area (Camden)
Bloomsbury Conservation Area (Camden)
Conclusion of Heritage Impacts
217. The proposals, by way of impact on setting and character, would preserve the
heritage significance and setting of all aforementioned heritage assets. The
proposals comply with policies CS12 and DM12.2 of the Local Plan 2015 and
S11 and HE1 of the emerging City Plan 2040.
218. The loss of historic fabric associated with the Kingsway Tunnels as a non-
designated heritage would be mitigated through the improvement to the
accessibility and visibility of this currently unknown heritage asset to a wide
public audience. The industrial language of No.38-39 Furnival Street would be
maintained through the reconstruction of the brick façade and the reinstatement
84
of the metal crane. As such, the proposals are considered to accord with Local
Plan Policies CS12, DM12.1 and DM12.2, emerging City Plan Policies S11 and
HE1, London Plan Policy HC1, having accounted for and paying special regard
to section 72 of the Town and Country Planning (Listed Buildings and
Conservation Areas) Act 1990 (as amended) and the relevant NPPF policies.
Archaeology
219. Policy DM12.4 of the Local Plan 2015 and policy HE2 of the draft City Plan
2036 outline the requirements with regards archaeology, that the City will
preserve, protect, safeguard and enhance archaeological monuments, remains
and their settings, seeking inclusive access to, public display and interpretation
where appropriate.
220. An Archaeological Desk-Based Assessment has been submitted with the
application.
221. The development site lies in an area of archaeological interest (Archaeological
Priority Area) identified in the City Local Plan. The City of London is considered
an archaeologically sensitive area in its entirety. In accordance with the City of
London Local Plan 2015, all of the City is considered to have archaeological
potential, except where there is evidence that archaeological remains have
been lost due to deep basement construction or other groundworks.
222. The desk-based assessment highlights that there was an archaeological
excavation by the Museum of London’s Department of Urban Archaeology in
1988 prior to the erection of the existing building at 40-41 Furnival Street. This
revealed medieval gravel quarries backfilled with brickearth, a series of 13th-
15th Century rubbish pits and a chalk-lined cesspit. The remains of the 17th
Century L-shaped building were excavated on the southern half of the site
which might have removed any evidence of the earlier inn. It is therefore likely
that archaeological remains have been removed from 40-41 Furnival Street.
The current building has a basement level with a floor slab at approximately
3.70m deep and it is considered that any archaeological survival would be very
low.
223. At 38-39 Furnival Street, bombing damages occurred during WWII and the
previous building was demolished. The current building hosts a vent shaft and
a lift in its basement that provides access to the tunnels. Given the old
basement housing the Kingsway Tunnels’ vent shaft and access shaft lay on
the site, archaeological survival is likely to be very low. The Kingsway Tunnels
have survived almost intact.
224. The scheme proposal includes the demolition of 38-39 and 40-41 Furnival
Street and their redevelopment, including the construction of a new four-level
85
basement across the footprint of the new buildings. The existing round shaft at
38-39 Furnival Street would be retained within the new basement and
excavation works would aim to enlarge the areas around it to provide space for
evacuation stairs.
225. There would be no construction works for the tunnels themselves, however
refurbishment works would be necessary to bring the tunnels into use. It is
acknowledged that these works could affect some of the earlier historic features
of the tunnels dating in the 1940s such as the air-raid shelter and later bunker
and computer centre.
226. The Greater London Archaeological Advisory Service (GLAAS) advised that
further archaeological work should be undertaken for 38-39 Furnival Street
before any excavation takes place as some archaeological potential remains.
In relation to the tunnels, GLAAS identifies the high heritage interest they hold
and recommends that historic building recording is carried out for them prior to
the redevelopment works. The historic building recording should utilise the
digital scans that have already been carried out for the site. The proposed
development works are identified as possible to cause harm to archaeological
remains and field evaluations should be carried out to determine the
appropriate mitigation measures. GLAAS, therefore, recommends two-stage
pre-commencement archaeological conditions requiring a Written Scheme of
Investigation (WSI) and a Historic Building Recording to be carried out prior to
any demolition works. This would comprise firstly, evaluation to clarify the
nature and extent of surviving remains, followed, if necessary, by a full
investigation.
227. The proposals are acceptable in archaeological terms subject to conditions to
cover a WSI and historic building recording. The application therefore complies
with Local Plan Policy DM12.4 and draft City Plan Policy HE2.
Public Access and Inclusivity
228. Developments should be designed and managed to provide for the access
needs of all communities, including the particular needs of disabled people as
required by policies CS10, DM10.1, DM10.5 and DM10.8 of the Local Plan,
policies S1 and S8 of the emerging City Plan 2040 and policy D5 of the London
Plan. Plan 2040 and policy D5 of the London Plan. In particular, policy DM10.8
requires to achieve an environment that meets the highest standards of
accessibility and inclusive design in all development (both new and
refurbished), open spaces and streets.
229. Local Plan policy DM 10.8 requires “to achieve an environment that meets the
highest standards of accessibility and inclusive design in all developments (both
86
new and refurbished)”. A service provider also has an anticipatory duty under
the Act.
230. A Design and Access Statement has been submitted in conjunction with
supplementary letter of clarification prepared by David Bonnett Associates
(DBA) in response to officers requests.
231. It is also noted that the proposed development has been reviewed by City of
London Access Group (CoLAG) during pre-application stage.
232. The proposed development has been carefully designed within the constraints
of the existing buildings to ensure that the access needs of all users have been
considered.
233. The provision of places to store a mobility scooter is welcome in principle and
should include fire prevention measures and accessible charging points.
Further details of this would be included within an Access Management Plan.
Arrival at the Site
234. Consideration has been given to the points of arrival at the site and the main
entrance to the cultural use amended following officers comments. Details of
the points of arrival and entrances to the site would be secured by an Access
Management Plan.
235. Arrival at the site has been considered for a number of travel options. The
walking distances from key public transport nodes exceed the recommended
50m without a rest. It is therefore welcome that resting points with accessible
seating are proposed wherever possible at maximum intervals of 50m along the
approaches to the buildings from key points of arrivals, to be secured under a
Section 278 Agreement. It is also welcome that an additional blue badge space
is proposed on Furnival Street near the site’s entrance. The exact location and
timed restrictions would be subject to further consultation carried out under a
Traffic Regulation Order. It is noted that Blue Badge holders are limited to 4
hours parking in City of London accessible parking bays.
236. The applicant has provided a framework to provide new high quality public
realm which would significantly improve the pedestrian environment and
capacity, the details of which would be guaranteed within a S278 Agreement.
The highways authority is exploring the further works under a healthy streets
scheme in conjunction with the above on Furnival Street and connecting roads,
that will look to provide the required accessible parking space, provide suitable
pavement to provide access to all, offer suitable resting areas where possible.
87
237. Continuing provision of the existing Blue Badge space in the area during
construction is important provided it is safe for use and it is recommended that
details are reserved of how this continuous provision will be secured through
the Deconstruction and Construction Logistic Plan.
238. Staff arriving on large outdoor mobility scooters would have one dedicated
parking space in the ground floor cycle store. An independent and dignified
inclusive transfer strategy to access level four office accommodation would be
required to be agreed under the Access Management Plan.
Cycle Provision
239. The long stay cycle entrance for the staff of the tunnels would be provided onto
Furnival Street and would be automated. The Access Advisor has advised that
controls should meet best practice guidance as set out in BS 8300 (2) 8.2.3 to
be accessible to a range of users. The submitted plans show that a space for a
larger cycle would be provided.
240. It is noted that 5% of cycle spaces should be suitable for larger cycles in order
to meet London Plan 2021 Policy T5B and London Cycling Design Standards
8.2.1 guidance. Wheelchair-accessible sanitary and changing facilities are also
necessary. On the submitted plans these appear to be provided within the
Furnival Street building in close proximity to the office accommodation.
However, access to associated staff changing facilities would be limited during
hours of operation. Further detail of operational management is recommended
to be reserved by condition to ensure that associated impacts are limited.
Entrance
241. The Access Statement details the entrances to 38-41 Furnival Street and 31-
33 High Holborn and confirms that they will all be step free with a clear opening
width of at least 1000mm. The primary visitor entrances at both Furnival Street
and Fulwood Place have been confirmed to be an automated swing doors.
Further detail is proposed to be secured via condition to ensure the design of
the manifestation, thresholds, mat wells and floor finishes designed to inclusive
design best practice guidance.
242. Reception facilities should be consistent with AD M(2): 3.6 and BS 8300 8.6.2
Routes from the entrance/lobbies and should be logical, clearly defined and
unobstructed, with adequate and sufficient circulation space. Reception area
desks should be positioned away from the entrance to minimise noise, with
lowered counter sections, appropriate hearing enhancement systems and the
surface of the reception area should be slip resistant. Circulation space around
the front entrance desk should ensure clear movement for wheelchair users,
88
people with buggies and mobility scooter users. Details are proposed to be
provided through condition.
Vertical Movement
243. London Plan D5, (B)5 states ‘in all developments where lifts are installed, as a
minimum, at least one lift per core (or more subject to capacity assessments)
should be a suitably sized fire evacuation lift suitable to be used to evacuate
people who require level access from the building’. Supporting text (paragraph
6.2.1) further states that there should be an evacuation lift in addition to fire-
fighting lifts. Proposals and the access statement confirm that all lifts will be
more than 1100x1400mm with appropriately sized landings and back-up lifts
are identified across the site in case of failure.
244. The lifts which provide access to the office accommodation from Furnival Street
are not sufficient for users of larger mobility vehicles and alternative provision
should be identified through the Access Management Plan. It is recommended
that details of lifts are reserved by condition.
245. The lifts at Fulwood Place which provide access to the tunnels and are integral
to the escape strategy from the tunnels do not meet the recommended size set
out by BS 8300-2:2018 (Table 4) for users of larger mobility vehicles and
alternative provision should be identified through the Access Management
Plan. It is recommended that details of lifts are reserved by condition.
Horizontal Movement
246. Corridor widths and door openings are confirmed as consistent with AD M(2),
including sufficient door widths and passing places for wheelchairs and will be
subject to detailed design development.
Terraces and Garden Space
247. The areas of landscape have the potential to offer places for rest and recovery,
consistent with guidance in PAS 6463: Design for the Mind. The detailed design
for the amenity terrace should meet best practice guidance as set out in BS
8300-1:2018 to be accessible to a range of users. It is noted that the details of
hard and soft landscaping will be secured by condition.
Sanitary Facilities
248. It is confirmed that unisex accessible toilets will be provided on all floors, with
a range of handed units across the development. Separate male and female,
as well as gender neutral cubicles, ambulant disabled cubicles, baby changing
89
facilities, and a Changing Places facility are provided across the development.
Further details of the toilet facilities layouts would be required by condition and
their access arrangement through S106 obligation under the AMP.
249. A Changing Places toilet was agreed during development of the proposals, and
which will support the public functions of the tunnels and help make it more
accessible to more people. There are few Changing Places facilities within the
City at present and, although not available on a 24 hour basis, this is a key
element of making the scheme more inclusive. Management and operation
should be covered in the AMP and would be secured via Section 106 obligation.
Internal recovery and restoration areas
250. Recovery and restoration areas have been deemed important for the proposed
development given the long distances to cover in a subterranean environment
and potential for high sensory stimulation, including from exhibitions. The
exhibition space targets to attract a broader audience including children,
elderly, families, people with restricted mobility, a place that would be
accessible to everyone. It is therefore critical to ensure that areas of rest and
isolation are provided in strategic locations within the tunnels for restoration and
recovery.
251. The letter of clarification by DBA proposes accessible seating to be provided at
50m maximum intervals within the exhibition spaces and a quiet room to be
placed in the Avenues, where the temporary exhibition space would be
provided. Recovery areas are proposed at approximately 60m intervals with
exact locations and design to be reserved by condition. Recovery areas would
feature accessible seating and tables, drinking points, visually and acoustically
calming spaces. Further details could be reserved in the Access Management
Plan as an obligation.
Signage and Wayfinding
252. Signage and wayfinding will be important for navigating the site and should be
designed with reference to guidance in PAS 6463: Design for the Mind and
following the principle of ‘two senses’. Details of a Wayfinding Strategy will be
secured by a condition.
Inclusive Procurement and Co-curation
253. An obligation for Inclusive Procurement has been made under the Section 106
including but not limited to opportunities of co-creation / co-curation,
partnerships with artists from underrepresented groups, as well as
opportunities for volunteering, training and mentoring for underrepresented
groups of people.
Public Access and Inclusivity Conclusion
254. The proposal has been designed to ensure that the site is accessible for the
greatest range of people. In order for the proposed cultural use to fulfil its goal
90
of being a top-tier tourist destination, high accessibility standards and inclusive
environments and practices are essential. Great consideration has been given
as to how to get beyond the limitations posed by the existing building and
tunnels infrastructure in order to secure the optimal solution for everyone.
Subject to further design details and an Access Management Plan, it is
considered that the proposal accords with the access related policies outlined
above.
255. Overall, and subject to the imposition of conditions, the proposal would accord
with the access policies outlined above.
Culture and Education Strategy
256. Policy S1 in the London Plan states that development proposals that provide
high quality, inclusive social infrastructure that addresses a local or strategic
need and supports service delivery strategies should be supported.
257. Local Plan policies CS11 and DM11.2 and draft City Plan 2040 Strategic Policy
S6 encourage new cultural experiences and art works. A Cultural Plan has been
submitted in accordance with emerging Policy CV2 of draft City Plan 2040.
258. A Cultural Plan has been prepared by Future City which sets out the vision and
strategy for the use of the existing tunnels as cultural and visitor attraction. The
proposed cultural destination has been characterised as the ‘London’s
Underground Connector’ in the Cultural Plan, as it strategically sits between the
London Borough of Camden and City of London, two local authorities offering
prominent cultural landmarks and central attractions linked to London’s rich
history from the Roman period, to the presence of St Paul’s and Tower Bridge,
and various livery halls and historic walks. The site would be an opportunity to
add a layer of the 20
th
century history to London's legacy.
259. The culture and education strategy has been developed around four key
principles: Cultural Intelligence; History and Heritage; Active Participation; and
Sustainable Futures. It is envisaged to use high-end technologies with
programming partners to create transformative experiences in the tunnels
providing a unique opportunity for visitors to interact with a range of media
through a digital stimulus. The history of the site plays a key role in creating a
context of physical heritage assets and programming along the cultural
exhibition areas. In line with the Destination City vision and the consultation
feedback through engagement with stakeholders inclusive and accessible
spaces would be introduced in the tunnels for everyone to enjoy, with part of
the cultural programming focusing on raising awareness about environmental
issues.
91
260. As mentioned previously, the tunnels would comprise three spaces: The
temporary Cultural Exhibition Space (in the ‘Avenues’); the permanent Heritage
Exhibition Space (in the ‘Streets’); and the Bar. The latter falls outside the
Corporation’s boundary.
261. The applicant's plan is to assemble a dedicated Cultural Delivery Team, for the
delivery of the exhibition programmes outlined in the submitted Cultural Plan,
in relation to the temporary exhibition space. A bespoke team would be
responsible for the operation of the venue. It is envisaged to partner with
London Festivals and Cultural Institutions to enable a variety of cultural
exhibitions and events. It is estimated to secure up to 12 events per year. The
access, operation and coordination of these events would be secured by an
obligation for a Public Access and Events Management Plan in the Section 106.
262. The Cultural Plan identifies the ‘History & Heritage Space’ (permanent
exhibition space) as a ‘continuous excitement’ with recurring programming
responding to the historic significance of the tunnels. It envisions partnerships
with historical and heritage institutions within London and the UK. The Imperial
War Museum, the British Museum and the Museum of London are mentioned
as potential large-scale programming partners, but it is also envisioned to
partner with smaller-scale organisations.
263. A final Cultural Operator is not secured at this stage, however the applicant has
been in meaningful long discussions with providers who have expressed
interest. Suggestions have been made to house the Military Intelligence
Museum in the tunnels. A Cultural Implementation Strategy as a Section 106
obligation would be secured restricting demolition works until an Operator is
secured.
264. The Cultural Plan refers to an initiative of creating a figurative Lab, referred as
the T-Lab, a partnership project that would bring together university, tech-
institutions, creative communities as key partners with further collaborations
with local and London-wide communities, to support generating and providing
content in both exhibition spaces. Opportunities for co-curation and co-creation
of cultural spaces with the help of local communities are considered key factor
to achieve inclusive developments. An Inclusive Procurement and Cultural
Implementation Strategy would be secured by an obligation in the Section 106
agreement which would require further details on inclusive partnerships
including the involvement of underrepresented artists and groups in the
formation of special exhibitions.
265. The proposed exhibition space is anticipated to attract up to two million visitors
per year which would boost national and international tourism. The submitted
Socio-Economic assessment suggests that these visitors could spend between
£60m - £85m in the local area each year. It is estimated that the development
92
would generate over 100 jobs through direct employment within the cultural use
and an addition of 50 jobs that would arise through the supply chain and worker
expenditure at the London level. The proposed development would generate
approximately £6.1 million of additional Gross Value Added (defined as “the
measure of the value of goods and services produced in an area, industry or
sector of an economy”).
266. The applicant has made a commitment to offer free school visits to the cultural
use. A minimum of two school-trips every week has been found logistically
achievable. Free entry is also considered for up to 20 members of the military
per weekday while discounts would be available for universal and pension
credit holders, emergency workers and carers, teachers, students, young
people and local residents.
267. It is targeted to attract audiences which can differ between the different cultural
offers within the tunnels. Indications of the audience segments include cultural
tourists, incidental tourists, young creatives, families, older learners, education
groups (including schools, colleges, universities, further education, etc), special
interest groups (clubs, societies, etc), local residents and workers.
268. The social benefits of the proposed cultural use include the following features
and commitments made by the applicant as stated in the Socio-Economic
Assessment:
Offer entry discounts for universal and pension credit holders, emergency
workers and carers, teachers, students, young people and local residents
and free school trips and members of the military to the proposed cultural
exhibition space;
Maximising opportunities for local jobs and apprentices in collaboration with
London Borough of Camden and City of London, including placements for
local school age children and/or local adults residents;
Work with local community centres to keep local residents informed on the
development progress and job and training opportunities;
Accessibility and Inclusivity the cultural spaces would feature enhanced
access for people with disabilities (both visitors and employees) and ensure
spaces would be designed to be enjoyable and safe for everyone;
Inclusive procurement and partnerships with inclusive cultural providers;
opportunities for co-created/co-curated exhibitions (community participation
is shaping the design of new cultural events/spaces/galleries); partnerships
with artists of underrepresented groups; volunteering and training
programmes for vulnerable groups of people and for schools;
Repurposing existing historic tunnels the proposed development aims to
provide access to the existing infrastructure that has been non-operational
since the 1980s by investing £140m in restoration and preservation. The
applicant commits to an £80m investment for installing the immersive
technology that will help bring the story of the tunnels to life.
93
269. The provision of the proposed cultural spaces and the benefits that are brought
forward would be captured and secured under a Section 106 agreement for a
Cultural Implementation Strategy and Operational Management Plan.
270. The proposed cultural spaces would provide a destination cultural and
community space which would contribute towards the Corporations Destination
City initiative of creating fun, inclusive and innovative spaces and places that
attract people to the City.
271. The proposed cultural spaces are considered to be an enhancement to the
City’s cultural provision and provide public benefits such as free school-trips at
least twice a week and delivering a highly accessible and inclusive venue.
272. As such, officers consider that the proposal would be in accordance with Policy
CS11 to maintain and enhance the City’s contribution to London’s world-class
cultural status and to enable the City’s communities to access a range of arts,
heritage and cultural experiences, in accordance with the City Corporation’s
Visitor Strategy, Policy DM 11.2 Public Art To enhance the City’s public realm
and distinctive identity.
Transport and Highways
273. The site has the highest level of public transport provision with a public transport
accessibility level (PTAL) of 6B. The application site is also in close walking
distance of London Underground (LU) stations, namely Chancery Lane Station
(c.130 metres), Farringdon (c.650 metres) and Holborn (c.700 metres).
Chancery Lane provides a direct connection to the Central Line and is
reachable within 2 minutes on foot. Farringdon provides access to the Circle
Line, Hammersmith and City Line, Metropolitan Line and the Elizabeth Line.
Holborn (one stop from Chancery Lane) provides onward connection to the
Piccadilly Line and Central line.
274. Farringdon Station is an 8-minute walk away (approximately 650m to the
northeast of the Site). In addition to providing access to the Circle,
Hammersmith & City, Metropolitan, and Elizabeth Line, Farringdon Station also
has access to National Rail services, via Thameslink. The station is served by
regular trains to St Albans, Cambridge, Brighton, Horsham, and Bedford,
amongst others.
275. City Thameslink is a 10-minute walk away approximately (800m south of the
Site). It is served by trains operated by Thameslink on the Thameslink Route
which is a 24-hour main-line route, running from Bedford, Luton, St Albans City,
94
Peterborough and Cambridge via Central London to Sutton, Orpington,
Sevenoaks, Rainham, Horsham, Brighton and East Grinstead.
276. The closest bus stop to the Fulwood Place Site access is the Chancery Lane
Station bus stop, 125m to the east. The access at 38-41 Furnival Street is
closest to the bus stop at Holborn Circus, 120m to the north-east of the access
point. Chancery Lane Station bus stops are located between the two access
points in Fulwood Place and 38-41 Furnival Street. The stops are served by 5
services, the number 8, 59, 133, N8, N25, and N242.
Trip Generation
277. The applicant has submitted a Transport Assessment (TA) to support the
application, which includes details on trip generation and modal splits. The trip
generation has been calculated by reviewing the theoretical capacity of a busy
design day for visitors coming to The London Tunnels. The design day has
been designed to accommodate the predicted trip generation for the 20 busiest
days of the years (bank holidays etc) based on a density of 6.53sqm per person
in the tunnels, equating to a maximum of 1,020 visitors on site with 750pp/hr in
the tunnels. A normal day (weekday) has been calculated at 10sqm per person
which equates to 490pp/hr in the tunnels and 760pp/hr across the Site as a
whole.
278. Based on the maximum capacity of 1,020 visitor capacity, extrapolating this
over to a maximum daily, weekly, monthly and annual capacity is shown below
in Figure 8.
Figure 8. Maximum visitor capacity assessment
279. Within the initial submission of the Transport Assessment the applicant
compared the likely modal split of the site to the Postal Museum in Islington.
Amended documents have since been submitted with the more likely
compatible site of the Museum of London as a comparison which is considered
to be more similar in nature and likely to generate a similar modal split for the
proposed development.
95
280. Officers are satisfied that based on this latest submission the outlined impact
of the development can be assessed based on the current assumptions
included within the Transport Assessment Addendum.
Figure 9. The modal split for the proposal
281. The overall numbers travelling to and from the site each day are likely to be
significant and therefore require mitigation. While there is also a potential
additional impact from the staff trip generation, with only 85 staff based at this
site at any one-time, officers have focused the impact of the assessment on the
public highway on the number of visitors.
282. In addition to this the additional visitors attending the special events proposed
for a typical operational purposes are required to be taken into account within
the assessment.
283. Focusing on the main visitor trips, based on the above modal split, there are
four key areas of consideration:
The pedestrian impact in the area. With a predicted 2025 additional
pedestrians travelling to/from the area, additional visitors coming via
public transport and coach would need to be assessed as they would
also likely all need to utilise pedestrian links to and from the site. This
would inevitably have an impact on pedestrian comfort levels in the area.
Public transport capacity. With the significant number predicted to use
the train and underground travelling to and from the site, initial impact
analysis assessments have been provided to demonstrate that local
public transport infrastructure can cope with the additional uplift in trips.
Taxi mitigation. With a predicted 135 people likely to use taxis to travel
to and from the site, on an assumption of two to three capacity per taxi,
96
this would generate an additional 45-68 taxis per day travelling to and
from Furnival St.
Coach mitigation. Coach trips to and from the site would be discouraged.
284. In summary, this application would produce a significant impact on the public
highway. That being said, officers are confident that through the below outline
mitigation measures, conditions and obligations the application is considered
acceptable in transport terms.
Events Management
285. In additional to the outlined 'day to day’ trip generation the application seeks to
use the venue for other out-of-hours uses as a potential events venue. This
impact would need to be carefully managed with consideration being given
specifically to any impact on local residents from noise or vehicle movements.
286. Any events would likely need to be considered on a case-by-case basis,
particularly if these events would require special deliveries, any special
allowance of vehicles to and from the site, possible queuing or dwelling outside
the site. Operation and opening times would also be required to be managed
to minimise the impact of these events and ensure that any impact on the public
highway can be mitigated.
287. Therefore, in order to manage these events appropriately, an Event
Management Plan is proposed to be secured via the attached Section 106 legal
agreement which would include the requirement of event management plans to
be submitted to the highway authority prior to each event. It is noted however
that should the Highway Authority feel that the impact on the public highway is
unacceptable then the Authority reserve the right to refuse permission for the
event proceed.
Pedestrian Impact and Public Realm
288. Upon review the submitted proposals would likely generate a high number of
visitors traveling to or from the site each day, with an expected 2,025 pedestrian
trips per day. The overall impact on the public highway and specifically on the
pedestrian comfort levels has been a significant focus in assessing this
application.
289. A site visit was conducted by the applicant to measure the footway widths within
an agreed study area to measure the critical paths. Critical Paths are defined
as the effective width of the footway where pedestrians can walk. The critical
paths additionally took into account street furniture and any frequent pedestrian
queues at bus stops or other areas.
97
290. This corresponded with a pedestrian count for the area (June 2023), with which
the pedestrian comfort levels can be assessed with. The applicant has applied
the expected uplift in pedestrian numbers should planning permission be
granted to this assessment along with predicted uplift in footfall by 2041 to
predict any potential alterations to the pedestrian comfort levels.
291. Pedestrian Comfort Levels range from A-E, with A being the most comfortable
for free-flowing pedestrian movement. The City of London is committed to
providing no lower than B+ standard of all public spaces both of private public
realm and on public highway.
292. In general, the impact of comfort levels is acceptable, as this is mainly helped
by the many options for pedestrian routes and public transport access across
the area. However, given the constraints of the site there is likely to be an
impact on Furnival Street for which the main entrance to the site is proposed.
293. Furnival Street is a narrow street that is north bound for general traffic only with
a contra flow cycle lane. It currently suffers from very narrow footways which
would need amendments should planning permission be granted. Initial
concerns from officers about queuing from the main entrance of the site onto
Furnival Street have been satisfied with the submission of a supporting
assessment, showing the permeation of pedestrians into the building. The
submitted document is considered to be sufficient to meet the above needs and
would ensure no external queuing on the surrounding public highway.
294. In order to address the pedestrian comfort levels of Furnival Street it is likely
that mitigation would be required to allow the street to cope with the increased
demand. These measures could take the form a raised table along the whole
of Furnival Street from the northern point of the site.
295. However, Furnival street will still need to be left open to vehicles, including
emergency vehicles, for required access to the site, along with maintaining two-
way access for cyclists.
296. The proposal aims to mitigate its impacts by including various public realm
improvement works along the Furnival Street, in conjunction with the City of
London’s Healthy Street aspirations for the area. The general aim of the Healthy
Street plan for Furnival Street is to redesign the street and manage access to
make streets more accessible, engaging and providing safe places for people
to walk, cycle and spend time. The proposal has considered how the application
would intertwine with the City’s scheme and the measures proposed above are
considered to be compliant with the CoL’s Healthy Street aspirations. The
extent of the works to be secured under a Section 278 agreement.
98
297. In conclusion the proposals impact on the local and wider streets is acceptable,
subject to the outlined changes which will require the applicant to enter into a
Section 278 agreement.
Building Line
Figure 10. Change in Building Line
298. The applicant has proposed to bring the building line on the north side of the
site on Furnival Street back to accommodate the visitors, as outlined from the
red delineation line on Fig 3. This will enable the permeation of visitors into the
site. The section would remain as private given the location underneath and the
protruding first floor.
Taxi movements and drop off
299. The development is expected to generate 15 taxi trips per hour, which would
equate to approximately 8 vehicle movements (based on 2 people per taxi). It
is proposed that all taxi’s would drop off and collect from Holborn, as per
existing highway arrangement.
300. Furnival street is currently used as a cut through for taxis and therefore,
realistically, is likely to be the key area for loading. While the Travel Plan
proposes to minimise vehicle trips on Furnival Street during the development
opening hours this will also need to be backed up by alterations to transport
infrastructure.
301. In order to mitigate the impact from taxis and to prevent vehicles from picking
up and dropping off directly outside of the site, the City’s Healthy Street Scheme
will consider restricting vehicle movements. The scheme could potentially
introduce timed closures or traffic mitigation measures however this is subject
to consultations with the neighbouring properties. The Section 278 therefore,
agrees a scope of work which would include immediate measures, such as
pavement widening, and future collaborative mitigation.
99
Coaches loading and dwell time
302. The development is expected to generate up to 135 people travelling to and
from the site by coach. With coach capacities varying between 40 to 60
passengers, this would generate between 3-4 coaches arriving to the site each
day.
303. Officers have worked with the applicant who is in agreement that coaches
should be discouraged from traveling to the site and at the point of initial
booking would be advised to seek alternative modes of travel to the site and to
utilise schemes such as the School Party Travel run by Transport for London.
304. A number of locations have been proposed to date for possible loading and
dwelling area for coaches away from the application site. Coaches that must
travel to the site will therefore be advised they are not to dwell or wait for
passengers in the local vicinity of the site.
Servicing
305. The proposed development would be car free, which is considered acceptable.
All vehicle trips generated by the development would likely be associated with
taxis and delivery & servicing. It is estimated that around eight deliveries are
expected to be generated per day.
306. Due to the narrowness and the restricted access of the site on Furnivall Street,
the main delivery point would be from Holborn, specifically outside 8-9 Holborn,
which is set away from residential properties. Access from that section of
highway is currently restricted by a mandatory cycle lane which is in operation
between the times of 7:00 AM and 7:00 PM Monday to Friday. The proposed
solution has been considered by CoL Environmental Health officers who did not
raise any objection, but seek to ensure best practice and ways of minimising
noise to the local residents through the management plans to be secured for
the site in the legal agreement.
307. The applicant therefore has agreed to all deliveries taking place out of hours,
with the main delivery point on Holborn, between the hours of 7:00 PM and
10:00 PM Monday to Friday. In order to secure this agreement, the Service
Management Plan would be secured as an obligation.
308. It is noted that the above arrangements would serve the main cultural use of
the site. Any servicing and deliveries in relation to the proposed bar would be
agreed with Camden officers and would not occur within the City.
100
309. Some limited deliveries, such as refuse collection could be allowed to take
place on Furnival Street for health and safety reasons. The full details of the
scheme are subject to further design work and consultation.
Disabled Motor Vehicle Parking
310. Policy T6.5 of the London Plan and Policy 16.5 of the Local Plan requires
proposals to provide disabled parking for users of the site. However, due to the
constrictive size of the site at surface level, combined with the structurally
restrictive existing supports that link in with access of the lower tunnels,
provision of the disabled parking on site cannot be achieved.
311. In order to provide parking for disabled users, the scheme under the Section
278 agreement on Furnival street, will seek to provide disabled parking in or
close by, in conjunction with the Healthy Streets scheme. As part of this
agreement it shall be outlined that one of the key considerations for the
proposed Highways scheme is to provide disabled car parking near the site.
Travel Plan
312. In order to mitigate the impact on this development a Full Travel Plan is required
to be put in place, which is required to cover the active travel promotions as
well as monitoring for staff and visitors. Travel Plans are an effective tool for
managing visitors, volunteers and employees at a site by helping to promote
sustainable transport and raising awareness of their benefits. It is particularly
important to note that actions discouraging coach use to and from the site
should be integral to targets and actions within this Travel Plan. The
discouragement of coaches has been outlined in the Transport Assessment
Addendum and this states that coach trips would be discouraged wherever
possible.
313. A Travel Plan (TP) is proposed to be secured as a Section 106 planning
obligation in order to meet London Plan policy T4 and Local Plan Policy 16.1.
The travel plan would need to be approved by the CoL prior to occupation and
this would include a requirement for a Travel Plan Co-ordinator to be appointed
no less than 3 months before occupation. The TP should include the action plan
with smart objectives, aiming to encourage the use of the sustainable modes of
transport.
314. Transport for London encourages developers to use the TRICS database for
trip generation predictions. Under the proposed legal agreement the applicant
will also be required to undertake a TRICS after study and provide TfL and the
City of London with the results on completion of the development. TfL would
then be able to update the TRICS database with the trip generation results for
101
the various use categories associated with this development. The necessary
after surveys and results are proposed to be secured by Section 106 agreement
as part of the Travel Plan review and monitoring process.
Cycle Parking
315. London Plan Policy T5 (Cycling) requires cycle parking be provided at least in
accordance with the minimum requirements set out within the London Plan.
Policy T5 (Cycling) requires cycle parking to be designed and laid out in
accordance with the guidance contained in the London Cycling Design
Standards and that developments should cater for larger cycles, including
adapted cycles for disabled people.
316. The level of cycle parking proposed as part of the development for long stay
parking meets minimum London Plan requirement for the cultural use with 12
long stay cycle parking spaces are proposed as being provided. At ground level
is proposed 3 Sheffield stand providing 3 general spaces and 1 fully accessible
space. At basement level which is accessible via a large lift at the secondary
entrance is proposed the remaining 8 spaces with the provision of two-tier
Joster Stand. Provision of additional 2 spaces is also required to cover for the
requirements of the bar at the same basement location. Details of the cycle
stores have been secured by condition.
317. The accessible Sheffield stand is welcomed and meets the London Plan
requirement for 5% of long stay parking to be accessible to disabled bicycle
users. It is also considered that the other long stay cycle parking meets cycle
design guidance standards and is acceptable. Officers encourage the provision
of an accessible cycle bay at the basement storage and require the inclusion of
a range of cycle space types split across the two bike stores by way of condition.
Furthermore, the proposed application also seeks to provide one accessible
shower at the staff accommodation at fourth level and another one at basement
level where the rest of the bikes are to be stored. In addition, provision of lockers
for staff is made in the office area and the basement cycle store. The supporting
facilities are considered acceptable for the 14 long stay cycle spaces.
318. Short stay cycle parking requirements for similar uses as outlined in the London
Plan is 1 space per 100sqm. If this requirement is applied to the total size of the
development, there would be a requirement to provide 125 short stay cycle
parking spaces.
319. Due to the constraints of the development site, the constricted floor layout
required for queueing and access to the tunnels and the large number of cycle
spaces required it is not possible to provide spaces within the development
itself. Nevertheless, it is proposed that the Section 106 legal agreement would
102
secure the provision of cycle parking spaces on the public highway, including
improvements to the cycle infrastructure in the vicinity of this development.
Camden Officers have agreed to provide 20% of the total requirement on their
public highway. Therefore, subject to this provision the application is considered
acceptable on this basis.
Management and Construction Impacts on the Public Highway in the local area
320. The proposal would involve a significant amount of demolition and construction
works. This would generate a large number of construction vehicle movements
during the overall construction period. Demolition and construction at ground
level as well as access to works below the surface would require cross
boundary access between two authorities, the London borough of Camden and
the City of London corporation. It is also important to note that works would be
conducted under Transport for London's strategic road network on high
Holborn, as well as close to London Underground assets. All of the above
mentioned stakeholders would be required to agree construction logistic plans
prior to the commencement of works.
321. The proposed works would likely have a significant impact on the operation of
the public highway if not managed effectively. Officers primary concern is public
safety but would also need to ensure that construction traffic does not create
(or add to existing) traffic congestion or impact on the road safety or amenity of
other highway users. The proposal is also likely to lead to a variety of amenity
issues for local people (e.g. noise, vibration, air quality) during the construction
stage.
322. London Underground while not objecting has asked to impose a condition for
approval to safeguard their assets from ground movement impacts during
demolition and construction works.
323. A preliminary Construction Logistic Plan (CLP) has been submitted in support
of the planning application and this provides useful information to outline the
proposed works and methodology.
324. It has been proposed that the majority of the demolition and construction works
would be carried out from Furnival Street within the CoL boundary, with an
additional secondary access from Fulwood place in the London borough of
Camden. Furnival street is located within a gyratory network, that contains
narrow roads with tight corners and will have limitations on vehicle access
through the area. It should be noted that the final admission of the construction
logistic plans would need to provide details and significant consideration on how
access would be managed.
103
325. A more detailed CLP and DLP would be secured by via condition with a
requirement to be prepared once a Principal Contractor has been appointed,
which would need to be in line with TfLs Construction Logistics Plan Guidance.
326. The City of London needs to ensure that the development can be implemented
without being significantly detrimental to the amenity or the safe and efficient
operation of the highway network in the local area. Therefore, a CLP and a DLP
is proposed to be secured as via condition to ensure the construction and
demolition of the site is in accordance with The London Plan Policy T7 and
DM16.1 of the CoL Local Plan. This would provide a mechanism to
manage/mitigate the impacts which the proposed development would have on
the local area. The CLP would need to be approved by the CoL prior to works
commencing on site.
Waste Management
327. Local Plan policies CS17 and DM17.1 require sustainable choices for waste
and for waste facilities to be integrated into building design. Draft City Plan
Policies S16 and CE1 require developments to consider circular economy
principles.
328. A Waste Management Plan has been submitted as part of this application which
sets out the servicing and waste collection strategy. The proposed development
would be serviced on site with all deliveries and refuse collection activities being
carried out at ground floor level, accessible via Furnival Street. These
arrangements serve all activities taking place within the building at Furnival
Street and underground. The bar would be served via Fulwood Place, in LB of
Camden.
329. The City’s Cleansing team were consulted and raised some initial concerns of
health and safety regarding the internal transfer of bins form the basement level
1 to the ground level. An updated Waste Management Plan has since been
prepared to address these concerns and was submitted to CoL for review. The
Cleansing team has reviewed the responses and confirmed that the proposed
waste storage and collections facilities comply with CoL’s requirements and no
objections were raised.
330. The waste storage is considered to comply with Local Plan policies CS17 and
DM17.1 and draft City Plan policies S16 and CE1. An obligation for the
Servicing and Delivery arrangements of this development would be secured in
the Section 106.
104
Transport Conclusion
331. The proposals are acceptable in transport terms, subject to the necessary
conditions and obligations as discussed above.
332. Nos. 38-39 and 40-41 Furnival Street represent a constrained site within a
tightly knitted, urban section of the City of London. Furnival Street itself is also
restricted in terms of its size, design and current vehicular and pedestrian
usage. The proposed development would significantly increase the use of both
the public realm and the highway that is located immediately adjacent to the
site. However, the submitted documentation details appropriate mitigation and
measures that would reduce the impact on the surrounding highway network
while also promoting active and sustainable transport.
333. The following S106 planning obligations and conditions would therefore need
to be secured:
The applicant has agreed to enter into a S278 agreement, which would
intertwine with the City of London’s Healthy Street plan for the area.
These plans would be delivered in conjunction with the City’s aspiration
for the area and mitigate the impact of the proposed development by
delivering a substantial uplift in the quality of the surrounding highway
network. The submitted drawing, titled Vision zero/Healthy Streets Plan
ref: 70106185-TP-SK-18 rev: P02, includes a shaded area in green,
showing the extent of S278 works, and agreed with the applicant. The
works are subject to further design and consultation.
Any design would also need to address the City of London's key
transport objectives for the area, which is to:
i. provide a healthy streets scheme with consideration to providing
a shared surface, increased footpath, additional street furniture,
additional blue badge parking and further public realm
improvements
ii. improve sustainable transport to and across the area
iii. provide additional greening
iv. maintain the contra flow cycle lane
v. maintaining access for emergency vehicles
Contributions towards cycle infrastructure.
Travel Plan (TP) s106 agreement shall state that the TP for all users of
the development shall be approved prior to occupation of the site.
Delivery and Servicing Management Plan (DSMP). The Section 106
agreement shall state that the DSMP shall be approved prior to the first
occupation of the site and the approved plan shall be followed.
A condition to secure a Construction Logistic Plan (CLP). The condition
shall state that the CLP shall be approved prior to any works starting on
site and the approved plan shall be followed thereafter. It should also
105
restrict HGV movement to and from the site to with in the hours of 9:30
to 16:30 Monday to Friday, 8 till 13:00 Saturdays and fully restrict
movement on Sundays and Bank Holidays unless agreed with the CoL
in advance.
S106 obligation - requiring the submission of an Event Management
Plan (EMP) to no less than 12 weeks prior to each event commencing.
The Highway Authority (HA) will then have at least 21 days to request
alterations or object to any event.
A condition requiring the details of the long stay cycle parking spaces
for the development. The spaces to be designed to London Cycle Design
Standards, implemented prior to occupation, maintained and retained as
part of this development thereafter.
Daylight, Sunlight and Overshadowing
334. Policy D6(d) of the London Plan states that the design of development should
provide sufficient daylight and sunlight to surrounding housing that is
appropriate for its context, whilst avoiding overheating, minimising
overshadowing, and maximising the usability of amenity space.
335. Local Plan Policy DM10.7 ‘Daylight and Sunlight’ seeks to resist development
which would reduce noticeably the daylight and sunlight available to nearby
dwellings and open spaces to unacceptable levels, taking account of the
Building Research Establishment (BRE) guidelines.
336. Draft City Plan 2040 Policy DE7 states that development proposals will be
required to demonstrate that the daylight and sunlight available to nearby
dwellings and open spaces is appropriate for its context and provides
acceptable living standards taking account of the Building Research
Establishment’s guidelines.
337. Paragraph 3.10.41 of the Local Plan indicates that BRE methods will be applied
consistent with BRE advice that ideal daylight and sunlight conditions may not
be practicable in densely developed city centre locations. Paragraph 3.10.41 of
the Local Plan and Policy HS3 of the Draft City Plan states when considering
on the amenity of existing residents, the Corporation will take into account the
cumulative effect of development proposals.
338. The BRE guidelines “Site layout planning for daylight and sunlight - A guide to
good practice” (2022) present the following methodologies for measuring the
impact of development on the daylight and sunlight received by nearby existing
dwellings and any existing non-domestic buildings where the occupants have
a reasonable expectation of natural light:
106
Daylight: Impacts to daylight are measured using the Vertical Sky
Component (VSC) method: a measure of the amount of sky visible from
a centre point of a window; and the No Sky Line (NSL) method, which
measures the distribution of daylight within a room. The BRE advises
that this measurement should be used to assess daylight within living
rooms, dining rooms and kitchens; bedrooms should also be analysed
although they are considered less important. The BRE Guide states that
diffuse daylighting of an existing building may be adversely affected if
either the VSC measure or the daylight distribution (NSL) measure is not
satisfied.
Sunlight: Impacts to sunlight are measured using Annual Probable
Sunlight Hours (APSH) for all main living rooms in dwellings if they have
a window facing within 90 degrees of due south. The guidelines consider
kitchens and bedrooms to be less important, but that care should be
taken to not block too much sun from these rooms.
Interpreting results
339. In undertaking assessments, a judgement can be made as to the level of impact
on affected windows and rooms. Where there is proportionately a less than 20%
change (in VSC, NSL or APSH) the effect is judged as to not be noticeable.
Between 20-30% it is judged to be minor adverse, 30-40% moderate adverse
and over 40% major adverse. All these figures will be impacted by factors such
as existing levels of daylight and sunlight and on-site conditions. It is for the
Local Planning Authority to decide whether any losses result in a reduction in
amenity which would or would not be acceptable.
Overshadowing
340. Overshadowing of amenity spaces is measured using sunlight hours on the
ground (SHOG). The BRE guidelines recommends that the availability of
sunlight should be checked for open spaces including residential gardens and
public amenity spaces.
Assessment
341. An assessment of the impact of the development on daylight and sunlight to
surrounding residential buildings and public amenity spaces has been
undertaken in accordance with the Building Research Establishment (BRE)
Guidelines using daylight (VSC, NSL) and sunlight (APSH) assessment
methodologies and considered having regard to policy D6 of the London Plan,
policy DM 10.7 of the Local Plan and policy DE7 of the draft City Plan 2040.
Policy D6D of the London Plan 2021 states that the design of development
107
should provide sufficient daylight and sunlight to new and surrounding housing
that is appropriate for its context whilst avoiding overheating, minimising
overshadowing and maximising the usability of outdoor amenity space. The
BRE guidelines can be used to assess whether daylight or sunlight levels may
be adversely affected. Local Plan policy DM10.7 states that development which
would reduce noticeably the daylight and sunlight to nearby dwellings and open
spaces to unacceptable levels taking account of BRE guidelines, should be
resisted. The draft City Plan 2040 requires development proposals to
demonstrate that daylight and sunlight available to nearby dwellings and open
spaces is appropriate for its context and provides acceptable living standards
taking account of its context.
342. The report has identified the following sensitive receptors:
1 to 6 Dyers Buildings (residential);
34-37 Furnival Street (residential);
10 Furnival Street (office/commercial); and
10-12 and 14-18 Holborn (office/commercial).
343. The report states that due to window locations and views across the Site, only
1 to 3 Dyers Building have been considered relevant for assessment for daylight
and sunlight. However, several of the properties within 4 to 6 Dyers Buildings
have windows facing directly towards the development site, which have not
been included for assessment. Officers requested to undertake assessment of
these properties. In response, a VSC assessment was undertaken by GIA on
the windows of 4-6 Dyers Buildings facing the site.
344. The assessment also excludes the residential premises within Sterling House,
12 Dyers Buildings which have windows facing the site, which have not been
identified as sensitive receptors. However, given the height and scale of the
proposal and the separation distance of this property from the site these
windows are not considered relevant for assessment.
345. The residential premises immediately to the south of the proposed development
site, at 34-35 and 36-37 Furnival Street, have not been assessed because their
windows are not orientated within 45 degrees of the uplift of the proposed
development in line with the advice set out within the BRE (2022) Guidelines.
346. The criteria set out in Building Research Establishment (BRE) Guidelines: Site
Layout Planning for Daylight and Sunlight (2022) are used as guidance in
forming a judgement on whether the design of the proposed development
provides for sufficient daylight and sunlight to surrounding housing and is
appropriate for its context (London Plan policy D6D), and when considering
whether the daylight and sunlight available to nearby dwellings is reduced
noticeably to unacceptable levels (Local Plan policy DM 10.7) and in
considering whether daylight and sunlight is appropriate for its context and
108
provides acceptable living standards (draft City Plan policy DE7) it is
appropriate to have regard to the assessment carried out in accordance with
the BRE guidelines.
347. Two commercial receptors have been identified as listed above. However, the
impact on their daylight and sunlight has not been assessed. Local Plan
Strategic Policy CS10 seeks to ensure that buildings are appropriate to the
character of the City and the setting and amenities of surrounding buildings and
spaces. The BRE daylight guidelines are intended for use for rooms adjoining
dwellings where daylight is required and may also be applied to non-domestic
buildings where the occupants have a reasonable expectation of daylight; this
would normally include schools, hospitals, hotels and hostels, small workshops
and some offices. The BRE sunlight guidelines are intended for dwellings and
for non-domestic buildings where there is a particular requirement for sunlight.
The proposed increase in height to 38-39 Furnival Street would be likely to have
a minor impact on daylight to Chancery Exchange, 10 Furnival St. (opposite), it
is however worth noting that the proposed development would still be lower in
height (by over 3 metres) (than the building opposite at 10 Furnival St.). In this
case officers do not consider that the offices surrounding the application site
fall into the category contemplated by the BRE where occupiers have a
reasonable expectation of daylight, and officers do not consider that the
surrounding offices have a particular requirement for sunlight. The dense urban
environment of the City, is such that the juxtaposition of commercial buildings
is a characteristic that often results in limited daylight and sunlight levels to
those premises. Commercial buildings in such locations require artificial lighting
and are not reliant on natural daylight and sunlight to allow them to function as
intended, indeed many buildings incorporate basement level floorspace or
internal layouts at ground floor and above without the benefit of direct daylight
and sunlight. As such the daylight and sunlight impact is not subject to the same
policy test requirements as residential premises.
348. There are no nearby gardens or amenity areas directly to the north of the
development that would require a sunlight / overshadowing assessment.
Daylight and Sunlight
349. Daylight has been assessed for both Vertical Sky Component (VSC) and No
Sky Line (NSL), these are complementary assessments for daylight: VSC is the
measure of daylight hitting a window, NSL assesses the proportion of a room
in which the sky can be seen from the working plane. Daylighting will be
adversely affected if either the VSC of the NSL guidelines are not met.
350. The BRE criteria state that a window may be adversely affected if the VSC
measured at the centre of a window is less than 27% and less than 0.8 times
its former value (i.e. experiences a 20% or more reduction.) In terms of NSL, a
109
room may be adversely affected if the daylight distribution (NSL) is reduced
beyond 0.8 times its existing area (20% or more reduction).
351. Both the London Plan 2021 and the draft City Plan 2040 require daylight and
sunlight to residential buildings to be appropriate to their context, and this will
need to be considered alongside reductions in daylight and sunlight assessed
under the BRE methodology.
352. The applicant has submitted a Sunlight and Daylight Assessment and a
Daylight and Sunlight Addendum letter.
1 to 3 Dyers Buildings
Daylight
353. 1 to 3 Dyers Buildings is a five-storey residential development located
immediately to the east of the application site. Given the close proximity of this
development to the application site, which are effectively separated by a light
well, the existing daylight levels are low, particularly at basement, ground, first
and second floor levels. The daylight and sunlight report has assessed 59
windows serving 18 rooms within this development for daylight.
Windows: Vertical Sky Component
354. Of the 59 windows assessed, 35 would meet the BRE guidelines for skylight
visibility (VSC). Of the 24 windows which fall below the guidance for VSC, eight
experience proportional VSC reductions between 20% to 30% (minor adverse
impact), nine between 30%-40% (moderate) and seven in excess of 40%
(major).
355. Of the 24 windows that fall below the BRE recommendations, 18 serve known
living rooms. Four remaining windows serve rooms for which the use is
unknown but are assumed to be habitable. A further two rooms serve bedrooms
which are considered to have a lower requirement for natural light.
356. It is noted that the VSC levels to the windows on the basement, ground, first
and second floors are exceptionally low in the existing scenario (the majority of
windows experience a VSC of below 10% with some as low as 0-0.3%). These
windows are therefore more susceptible to greater proportionate reductions in
skylight visibility. So, whilst these windows see reductions in VSC over that
which is recommend by the BRE guidelines, the absolute reductions in VSC
are generally quite small (i.e. between 0-4.3%). Of the 24 windows that fall
below guidance, nine see an absolute VSC reduction of less than 1%. A further
eight windows see no more than a 3% absolute change for VSC, and the
remaining eight windows see no greater than a 5% absolute change in VSC.
The report points out that absolute reductions of 3% have been referenced in
past appeals as “virtually imperceptible”, and absolute reductions of 5% have
110
been described as “barely noticeable”. As such, while there is identified
breaches of the BRE Guidance, the existing level of VSC is exceptionally low
that any minimal change would result in the windows falling below the guidance.
The reductions proposed however are modest in reduction, would fall under the
imperceptible category and as such are assessed as acceptable.
Rooms: Daylight Distribution
357. Of the 18 rooms assessed, 13 would meet the BRE guidelines for daylight
distribution (NSL). Of the five rooms that fall below the guidelines, two would
experience a percentage alteration of between 30%-40% (moderate adverse
impact), and three would experience a percentage alteration in excess of 40%
(major adverse impact).
358. Two of the five rooms (F00, R2 and R3) assessed for daylight distribution (NSL)
that fall below the guidelines serve bedrooms, which have a lower requirement
for daylight. These rooms would experience proportionate reductions in daylight
distribution of 32.1% and 67.7%.
359. The remaining three rooms are a ground floor living room (F00, R4), and LKDs
on the first and second floors (F01/R2 and F02/R2). The living room on the
ground floor would experience a reduction in daylight distribution from 15.4%
to 8.5% of the room having a view of the sky. The LKD on the first floor sees a
reduction in daylight distribution/sky visibility (NSL) from 30.6% to 13.5% and
the LKD on the second floor sees a reduction in sky visibility from 51.1% to
35.3%. Although the daylight distribution analysis is based on assumed layouts
and the results carry uncertainty and the actual impacts may be different in the
existing rooms, it is considered that the impact would be acceptable given that
the impact in minor adverse to a limited number of rooms.
Sunlight
360. 35 windows have been identified as eligible for assessment for sunlight. The
report demonstrates that all the windows assessed would meet the BRE
Guidelines for sunlight (APSH) with the proposed development in place.
4-6 Dyers Buildings
361. A VSC assessment was undertaken in GIA’s Phoenix application on the
windows of 4-6 Dyers Buildings facing the Site. This showed no alterations
beyond 20%, therefore all windows would be BRE compliant and no further
technical assessments were deemed necessary. Furthermore, given the
proposed massing of the building and separation distances to the residential
property the impact in terms of daylight and sunlight is considered to be
acceptable in this instance.
111
10 Furnival Street (Chancery Exchange) and 10-12 &14-18 Holborn
362. It is not considered that the commercial buildings at 10 Furnival Street, 10-12
and 14-18 Holborn are of a nature that requires exceptional daylight and
sunlight levels mainly due to its location in a dense urban environment and the
type of accommodation which is expected to be largely used during office hours
and being relied upon artificial lighting throughout the day. As such the daylight
and sunlight impact is not subject to the same policy test requirements as
residential premises. The dense urban environment of the City, is such that the
juxtaposition of commercial buildings is a characteristic that often results in
limited daylight and sunlight levels to those premises. On that basis, the
assessment has not considered the surrounding commercial buildings, which
officers found an acceptable approach.
Conclusion
363. The assessment results included in the daylight and sunlight assessment report
submitted with the application demonstrate a moderate to hight level of BRE
compliance. Where there are technical breaches of the BRE guidelines, they
can be partly attributed to the low existing levels of daylight received by the
neighbouring residential properties assessed, which would be sensitive to
proportionately higher percentage reductions as a result of the low existing
levels of daylight.
364. Overall the daylight and sunlight available will be sufficient and appropriate to
the context, and acceptable living standards would be maintained. As such, the
overall impact (including the degree and extent of harm) is not considered to be
such that it would conflict with, London Plan policy D6, Local Plan Policy
DM10.7 and Policy DE7 of the draft City Plan 2040.
Light Pollution
365. Local Plan Policy DM15.7 and draft City Plan 2040 Policy DE8 require that
development should incorporate measures to reduce light spillage particularly
where it would impact adversely on neighbouring occupiers, the wider public
realm and biodiversity.
366. It is considered that only the front (west) facade of previous 40-41 Furnival
Street building would be designed with glass bricks creating a level of
translucency which would create light spill from internal lighting towards the
occupiers facing the west side of the building which is relevant to the
commercial building at 10 Furnival Street. There would be no translucent
elevations opposite the residential buildings and therefore light pollution has not
been considered a material factor in the submitted Daylight and Sunlight
Assessment.
112
367. To ensure that appropriate lighting levels are achieved externally and internally
including at roof terrace level, and to mitigate impacts of public realm and
nearby residential properties, a condition for the submission of relevant details
of a Lighting Strategy and Technical Lighting Design would be required to be
submitted for approval. This will have to be submitted prior to the occupation of
the building and the details shall accord with the requirements as set out in the
Lighting SPD, including but not limiting to details of all external, semi-external
and public-facing parts of the building and of internal lighting levels and how
this has been designed to reduce glare and light trespass.
Air Quality
368. Local Plan 2015 policy CS15 seeks to ensure that developments positively
address air quality. Policy DE1 of the draft City Plan 2040 states that London
Plan carbon emissions and air quality requirements should be met on sites and
policy HL2 requires all development to be at least Air Quality Neutral,
developers will be expected to install non-combustion energy technology where
available, construction and deconstruction must minimise air quality impacts
and all combustion flues should terminate above the roof height of the tallest
part of the development. The requirements to positively address air quality and
be air quality neutral are supported by policy SI1 of the London Plan.
369. The application includes an Air Quality Assessment which addresses the likely
impact of the proposed development on air quality as a result of the construction
and the operational phases of the development.
370. The proposed development will be car free and heating will be through air
source heat pumps which is welcomed. The development meets both the
transport and building emissions benchmarks for the Air Quality Neutral
Assessment. The proposal includes a visitor attraction in underground tunnels
where levels of indoor air pollution should be minimised.
371. The City’s Air Quality Officer has reviewed the proposal and has raised no
objections subject to conditions and informatives in respect of generators
combustion flues, Non-Road Mobile Machinery Register, and the Indoor Air
Quality.
372. In light of the above and subject to conditions, the proposed development would
accord with Local plan policy CS15, policies HL2 and DE1 of the draft City Plan
2040 and SI1 of the London Plan which all seek to improve air quality.
113
Impact on amenity (Noise, Disturbance and Overlooking)
373. London Plan Policy D13 requires the proposed development to mitigate noise-
generating uses and Policy D14 aims to avoid significant adverse noise impacts
on health and quality of life. Local Plan Policies DM3.5 and DM15.7, seek to
ensure that operational noise does not adversely affect neighbours and that
any noise from plant should be at least 10dBa below background noise levels.
Policies S1 and HL3 of the Draft City Plan 2040 requires that noise does not
adversely affect nearby land uses, supporting a healthy and inclusive City.
374. Local Plan Policy DM21.3 and Emerging Policies HS3 and DE4 seek to protect
the amenity of residential properties from uses which would cause undue noise,
disturbance and requires new development near existing dwellings to
demonstrate adequate mitigation measures to address the impact.
Development proposals are expected to be designed to avoid overlooking to
adjacent residential accommodation in line with Policies DM10.3 and DM21.3
of the Local Plan and Policies HS3 and DE4 of the Draft City Plan 2040.
375. An Acoustic Assessment has been submitted which provides an outline
assessment of the impact of noise and vibration from the mechanical plant on
the surrounding area. In addition, operational use noise and construction
impacts have been considered.
376. The nearest noise sensitive receptors that have been identified in the
assessment are the residential properties to the south and east of the site, 36-
37 Furnival Street and 1-6 Dyer’s Buildings, and the commercial occupiers to
the west, 10 Furnival Street and 9 Holborn and to the north at 14-18 Holborn.
Noise surveys have been conducted to obtain the background noise levels of
these properties from two measurement positions. Tabulated results are
provided within the submitted Acoustic report.
377. Plant equipment serving the building and the tunnels would be housed within
38-41 Furnival Street building. The new building would house the primary
entrance to the cultural exhibition space, ancillary office accommodation and
retail spaces at upper levels, basement plant rooms, an air handling unit (AHU)
plant room and a roof plant room situated at the northern roof level which forms
the highest part of the proposed building. The proposed plant would be subject
to a condition that require noise levels to be compliant with the City’s standard
of at least 10 dBa below background noise level as well as a condition to
minimise transmission of structure borne sound or vibration to any other part of
the building.
378. The impacts of the demolition and construction work on the surrounding area
would be controlled by conditions requiring the submission of schemes of works
to protect neighbouring occupiers. Noise and vibration mitigation, including
114
control over working hours and types of equipment to be used would be
included in a construction management plan to be secured by condition, and
freight movements would be controlled through the Construction Logistics Plan,
secured by condition. These would need to demonstrate compliance with the
City’s Code of Practice for Deconstruction and Construction Sites and the
Mayor of London’s Construction Logistics Plan Guidance.
379. The impact of the proposed development in terms of noise associated with the
operational stage of the cultural use (i.e. the actual underground use) has been
considered to be negligible based on the fact that the main visitor space is
provided underground and therefore away from nearby noise receptors. Since
the earth has enough bulk to keep noise from escaping, noise breakout from
the cultural exhibition spaces through the ground is therefore not regarded as
a problem. It is however acknowledged that the proposed development has the
potential to increase activity at street level with visitors arriving to the venue and
exiting through from the upper levels of the gift shop back to the street level.
Officers acknowledge that increased footfall in the area would likely increase
the noise generated and disturbing to nearby properties. For that reason, the
submitted Transport Assessment has produced a robust worst-case scenario
based on predictions for the busiest day on site. It is estimated that a standard
visitor will spend a total of 1 hour and 20 minutes on the site. Model outputs
have tested the operation of the ground floor site entrance on Furnival Street to
understand if there will be any external queueing that would have adverse
impacts to the amenity of neighbouring occupiers. The dynamic model takes
into consideration different parameters proposed to mitigate impact on the
highway such as the proposed footway widening in front of the principal
entrance that has been designed to maximise any pedestrian queues within the
curtilage of the site and the proposed operational and management plan of the
venue (including the capacity of the visitor lifts, security check points and
processing time for ticketing). The results demonstrate that queuing would not
be expected into Furnival Street at the tested scenario. Notwithstanding that, a
worse-case scenario of 20% uplift in visitor numbers has been tested with all
other parameters taken into account and results still showed no external
queuing on the street.
380. In addition, it has been logically assumed that visitors arriving and leaving the
site would most like be coming from Holborn where public means of transport
and cycle/motorbike parking facilities are available alongside other commercial
uses such as F&Bs which people can visit before or after their booked visit to
the site. It is therefore considered that visitors arriving and leaving the cultural
exhibition space would not create significant queues at street level or use the
part of Furnival Street that extends southern to the site which would have likely
cause some disturbance to nearby occupants.
115
381. The existing buildings on Furnival Street are either vacant or serve a modest
scale office. The proposed change of use to a cultural facility, by its very nature,
would likely increase the pedestrian and vehicular movement within the
immediate vicinity. This would be particularly pertinent for the residents of 36-
37 Furnival Street and 1-6 Dyer’s Buildings. While the highway modelling
described above confirms limited use of the street for significant queues,
officers are cognisant there would likely be an increase in general noise and
disturbance to the surrounding properties from increased activity. This is
however the case with all similar cultural use applications that are intending to
draw visitors to the site and officers consider that the noise increase would not
vastly differ from that already found within the immediate locality (for example
on Holborn or other surrounding uses). Care has been taken to prevent
significantly detrimental impacts occurring to neighbours, through constrained
servicing times and event management conditions, however the potential
increase in general human activity is considered to be acceptable and
proportional to this highly urbanised, constrained setting.
382. The application also includes a Security Strategy that outlines the security
measures to be implemented on site that would support the smooth operation
of the development. The site would benefit from a comprehensive management
team, including on-site staff such as receptionist and security staff who would
be present throughout the site’s operational hours. The building would benefit
from Video Surveillance Systems (VSS) monitored by on-site staff at a Security
Control Room (SCR) to aid in the management of the building and surrounding
spaces. As such, officers consider that adequate management of the
development would likely ensure no adverse impacts are cause due to
increased pedestrian movements around the site or increased number of users
of the building. Details of an Operational Management Plan would be secured
in the Section 106.
383. The proposal involves the operation of two separate cultural exhibition spaces
within the tunnels. The Heritage Exhibition space forming the permanent visitor
attraction would operate on a daily basis, and the Cultural Exhibition space
which would be available for temporary exhibitions along the year and would
operate with programmed events. The Cultural Plan estimates approximately
12 events taking place intermittently over a year. Further details on event
programming and minimising the impact of events on amenity in terms of
dispersal of visitors at night time and noise and disturbance would be required
as part of the Public Access and Event Management Strategy that would be
secured in the Section 106.
384. The proposed roof terrace at level four, would be used by the working staff and
no members of the public would be allowed to access it. The terrace would
measure 40sqm area with a 1.4m high boundary and embedded plant floor
along its perimeter to provide privacy. The residential properties to the east and
116
south side of the terrace would be further protected from overlooking by the
proposed frosted glass screen of 1.4m height and excessive greening against
the eastern boundary of the terrace. Notwithstanding that, it is noted that the
terrace is set back from the eastern side as the east elevation has been
designed with an inclination to this portion of the building. This design provides
greater distance from the adjacent residential properties and reduces the level
of potential overlooking drastically. An external staircase is proposed to the
southeast corner of the terrace to be used only as a fire escape. An alarmed
gate would be in position to ensure that these stairs are only used in an
emergency. The Environmental Health team has recommended a condition to
restrict the use of the proposed roof terrace between the hours of 20:00 on one
day and 08:00 on the following day and not at any time on Sundays or Bank
Holidays, other than in the case of emergency in order to safeguard the amenity
of the nearby occupants. Officers consider the proposed privacy measures
sufficient to safeguard the privacy of the surrounding dwellings and recommend
a condition for the approval of details in relation to the proposed screening and
planting of the roof terrace.
385. It should be noted that the proposed bar and the programmed school trips to
the Heritage Exhibition space would access the site solely through the
secondary entrance at High Holborn only, which is located within London
Borough of Camden. Therefore, the relevant Local Planning Authority would be
responsible to control noise and disturbance to safeguard the amenity of
neighbouring properties around the secondary entrance.
386. Due to there being nearby sensitive receptors it is also considered necessary
to restrict overnight servicing, therefore a condition will be included to ensure
no servicing of the development shall take place between 23:00 and 07:00
Monday to Saturday and between 23:00 on Saturday and 07:00 on the following
Monday and on Bank Holidays.
387. Subject to the imposition of conditions, in particular those relating to noise from
plant and schemes of works to protect against the impacts of demolition and
construction and event management, it is considered that the application is in
accordance with London Plan Policies D13 and D14, Local Plan Policies
DM3.5, DM10.3 DM15.7 and DM21.3, and Emerging Policies S1, HL3, HS3
and DE4 of the draft City Plan 2040.
Health Impact Assessment
388. Policy HL9 of the draft City Plan 2040 requires major developments to submit
a Healthy City Plan Checklist to assess potential health impacts resulting from
proposed developments.
117
389. The applicants have submitted a Rapid Health Impact Assessment (HIA) using
evidence and assessments of impact within documents submitted with the
planning application. The London HUDU Planning for Health Rapid HIA Tool
Fourth Edition (October 2019) recommends the assessment of potential health
impacts under 11 different broad health determinants. The HUDU checklist has
been satisfactorily completed and there are not expected to be any adverse
health impacts resulting from the proposed development.
390. The Assessment concludes that the development would have an overall
positive impact on health. Positive impacts include:
Improvements to the public realm along Furnival Street to be secured under
Section 278;
A Heathy Street approach would be adopted;
Reuse an existing infrastructure and create accessible arrangements for
everyone to have the opportunity to enjoy;
Provision of a cultural space including heritage exhibition space;
A car-free development with cycle parking proposed on and off site;
Inclusivity and Accessibility at the heart of the Cultural Plan;
Design out crime practices;
Access to local employment and training opportunities as well as inclusive
local procurement to be secured under Section 106;
An outdoor amenity space is provided for the staff, greenery is incorporated
wherever possible and active travel is promoted.
391. The HIA does not identify any negative impacts. However, officers considered
that some impacts would arise during the construction and operational phases
such as dust, noise, vibration and odours, and air pollution caused by traffic.
These impacts would be mitigated by the requirements of relevant conditions
and Section 106 obligations. For example, by implementing a Delivery and
Servicing Plan that ensures sustainable modes and operation of freight; a
Construction Environmental Management Plan and Construction Logistics
Plan; securing local employment and training opportunities; and other air quality
and environmental health mitigations addressed elsewhere in the report.
392. The HIA assessment adequately addresses potential health impacts and
therefore the development complies with draft City Plan HL9.
Sustainability
Circular Economy
393. London Plan Policy SI7 (‘Reducing waste and supporting the circular economy’)
sets out a series of circular economy principles that major development
proposals are expected to follow. The Local Plan Policies CS15 and DM 17.2
118
and the emerging City Plan 2040 Policy S16 set out the City’s support for
circular economy principles.
394. The London Plan Policy GG5 states that “Creating a low carbon circular
economy, in which the greatest possible value is extracted from resources
before they become waste, is not only socially and environmentally responsible,
but will save money and limit the likelihood of environmental threats affecting
London’s future”
395. ‘Circular economy’ is defined within the London Plan’s glossary as, “An
economic model in which resources are kept in use at the highest level possible
for as long as possible in order to maximise value and reduce waste, moving
away from the traditional linear economic model of ‘make, use, dispose’”.
Development Proposal
396. The full extent of the tunnel network is proposed to be retained and refurbished
(>90% of material retained). No.s 38-39 and 40-41 Furnival Street are proposed
for demolition due to the practicalities of construction and challenges of plant
arrangement. Further details are included under Carbon Options Appraisal
below.
397. Fulwood Place (31-33 High Holborn, Camden) would require limited structural
works at basement and ground level only to facilitate visitor access and the
MEP strategy. The building will also be refurbished likely including minor
upgrades to the façade (e.g. glazing replacement and draughtproofing).
Carbon Options Appraisal
398. In line with the CoL Carbon Options Guidance, the application includes a study
of opportunities to retain and refurbish the buildings at no. 38-39 and 40-41
Furnival Street including a carbon assessment. The Carbon Option appraisal
was subject to review by a third-party expert. The reviewer has confirmed that
the optioneering has been carried out in compliance with the Carbon Options
Guidance.
399. The demolition of No. 38-39 (ventilation building) is consistent across all three
options. Due to access requirements (escape stairs, elevator upgrade,
installing plant equipment) and the practicality of construction any retention was
deemed unfeasible. Redevelopment of No. 38-39 would include: new three-
level basement constructed, shaft enlarged down to tunnel entrance and
superstructure rebuilt with one additional floor. Dependent on their condition,
existing bricks and concrete louvres from 38-39 will be reused to rebuild the
replacement.
400. No. 40-41 with its 7-storey concrete frame offers some retrofit potential. Three
options were explored for 40-41 Furnival Street only:
119
Option 1: Major refurbishment
401. All substructure and majority of superstructure retained. Openings created in
level 5 slab to accommodate MEP. One additional floor added. Retained slabs,
columns and possibly foundations strengthened to accommodate openings and
increased loading.
Full Replacement and upgrade of existing façade system.
Option 2: Major refurbishment with vertical extension
402. Substructure and ground to 3rd floors retained. Retained slabs, columns and
possibly foundations strengthened to accommodate increased loading.
Demolition of top 3 levels of superstructure. Replacement structure has no
additional floors but greater height and more efficient space for MEP plant.
Full Replacement and upgrade of existing façade system.
403. Option 3: Full demolition and redevelopment (Development proposal)
Demolition and rebuild, including new three-storey basement. One-storey
increase in height to no. 40-41.
Figure 11. Optioneering
404. The subterranean nature of the tunnels and proposed cultural use with significant
visitor numbers requires a significant size and quantity of plant equipment for
ventilation and cooling. The existing floor to floor heights of no. 40-41 causes
challenges with accommodating the plant. Some of the plant also requires access
to fresh air and cannot be placed underground. Options 1 and 2 work within these
constraints to propose feasible options which retain existing structure. As the
120
extent of demolition increases, improvements to system efficiencies are expected
due to larger, more flexible plant area at street level.
405. The appraisal of the three scenarios is underpinned by a quantitative assessment
of whole life-cycle carbon emissions of each option. Quantitative results from the
options appraisal for 40-41 Furnival Street only are set out in the table below.
406. The operational energy figure accounts for the Tunnels and Furnival Street
energy use and is based on Category A fit-out which includes regulated
emissions (heating, cooling, lighting) and fixed services (e.g. lifts) but does not
include any tenant equipment such as audio-visual equipment.
407. The majority of energy consumption takes place in the tunnels; however the
plant is predominantly located above ground in the Furnival Street buildings
(with minor variation between options). The operational energy rate per m2 is
divided by the area (GIA, m
2
) of Furnival Street only in order to align with the
embodied carbon figures which also apply to Furnival Street only.
Table 7. Quantitative results from the options appraisal for 40-41 Furnival Street
Furnival Street Options
Option 1
Major
refurbishment
Option 2
Major refurb
with extension
Option 3
Redevelopment
(Optioneering stage)
1. Gross Internal area (GIA) m²
1979
2125
2589
2. Increase in GIA (over
existing)
10%
35%
60%
3. Substructure % retained by
mass
100%
100%
0%
4. Superstructure % retained by
area
(frame, upper floors, roof,
stairs, ramps)
55%
35%
0
5. Upfront Embodied Carbon
(A1-A5) (kgCOe/m² GIA)
exc. sequestration
666
616
818
6. In-use & End of Life
Embodied Carbon (B-C)
(kgCOe/m² GIA) excl. B6 &
B7
464
461
453
7. Life-cycle Embodied Carbon
(A1-A5, B1-B5, C1-C4)
(kgCOe/m² GIA)
1,130
1,077
1,271
8. Fuel source
Electricity
Electricity
Electricity
9. Operational Energy Use (B6)
of the Tunnels + Furnival St.
(divided by GIAm
2
of Furnival
St. only) (kWh/m²/yr GIA)
424
395
324
10. Estimated Whole Building
Operational Carbon for
883
822
675
121
building lifetime (B6)
(kgCOe/m² GIA)
11. Total WLC Intensity (incl.
B6 & pre-demolition)
(kgCOe/m² GIA) Module B7
is not considered
2,026
1,918
1,977
12. Upfront embodied carbon
(A1-A5) (tCOe)
1,318
1,309
2,118
13. In-use embodied carbon (B-
C, excl. B6 & B7) (tCOe)
918
980
1,173
14. Operational carbon for
building lifetime (B6) Tunnels
+ Furnival St. (tCOe)
1,747
1,748
1,746
15. Total WLC (incl. B6 and pre-
demolition) (tCOe) Module
B7 is not considered
4,009
4,077
5,117
Figure 12. Estimated Cumulative Carbon Emissions Intensity
0
500
1,000
1,500
2,000
2,500
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60
Years (2024-2084)
Estimated Cumulative Carbon Emissions Intensity (kgCO₂e/m² GIA/year)
Major refurbishment Major refurbishment with extension New build
Upfront Embodied
Carbon (PC)
incl.A1-A5 &
demolition
122
Figure 13. Estimated Total WLC
408. The study found marginal differences between the two refurbishment options.
Option 2 is able to achieve better operational performance and reduced upfront
emissions compared to Option 1 due to a more efficient spatial arrangement
and structural grid and the significant strengthening work Option 1 would
require to accommodate the MEP equipment.
409. Total upfront emissions increase by ~1,000,000 kgCO2e from Option 2 to
Option 3. For Option 3, 8% of the total WLC emissions (393,528 kgCO2e )are
attributed to the new substructure works (inc. 3 basement levels).
410. Option 2 and 3 include capacity for additional sustainability benefits such as a
blue roof which allows water retention and an amenity terrace with greening for
the staff.
411. The new build option was chosen as the preferred option based on overall
benefits including “constructability, maintenance and space utilisation.” Fitting
the required plant within the existing structure of 40-41 Furnival St. is
complicated, in part due to restricted floor heights, and would require
strengthening works which have an associated carbon impact. As new build
area increases operational performance is also predicted to improve as plant
specification/layout can be optimised. The new build option offers the greatest
increase in floor area which allows the most flexibility in spatial design terms
and improved facilities including:
a) Improved accessibility and public realm
0
1,000
2,000
3,000
4,000
5,000
6,000
Major refurbishment Major refurbishment with extension New build
tCO₂e
Estimated Total WLC (tCO₂e)
Estimated existing building demolition A1 - A5 B - C (excl. B6 & B7) B6
123
b) Larger area of amenity terrace for staff and additional greening
c) Increased plant space which;
simplifies provision of future heat network connection
improves smoke management and stair pressurisation increasing
potential visitor capacity.
Development Proposal
412. The Circular Economy Statement (CES) submitted describes the strategic
approach to the incorporation of circularity principles and actions according to
the GLA Circular Economy Guidance.
413. Approximately 90% of the existing site (by area), including the entire tunnel
network will be retained. 31-33 High Holborn (Camden) will be largely retained.
The Tunnels are being refurbished and adapted to offer an adaptable and
flexible space for future occupants.
414. Outline proposals for incorporating circular economy principles:
All internal partitions (other than fire lobbies) can be dismounted and
altered for future adaptation
Materials used will be high quality and high durability to ensure long
service life and minimise the impact of replacement with new Tunnels /
shaft linings designed for a 120-year design life.
Various building elements, including lifts, glass balustrades, façades, and
steel frames, have been designed for disassembly and recycling
Services are designed for ease of maintenance and replacement.
Demountable sections have been incorporated into the glass block
façade for plant replacement.
Generally, all MEP items can be de-commissioned and removed for re-
use or recycling. Ductwork will be installed with flanges and pipework
which will aid in the deconstruction
Steel frames supporting the first-floor gallery, spiral stair and façade at
Furnival Street can be adapted, strengthened, or finally deconstructed
and reused, if necessary in future.
Where possible, precast reinforced concrete elements (likely to include
walls, infill panels and Tunnels lining structure) will be discussed with the
contractor at the next stage. These can be prefabricated off site reducing
waste and emissions.
415. Figure 2 of the Circular Economy Statement summarises a list of circular
economy commitments/approaches as follows:
124
a) The development aspires to achieve the GLA recommended target of
minimum 20% of all new material being reused/recycled content by value.
b) Specific materials targets for investigation at developed design stage:
20% of new materials used should contain reused/recycled content
by value (as per GLA recommended target)
25% GGBS in concrete
20% recycled content in steel
60% recycled content in plasterboard
97% recycled content in rebar
35% recycled content in aluminium
Materials from suppliers who participate is responsible sourcing
c) schemes such as the BRE BES 6001:2008 Responsible Sourcing
Standard will be prioritised.
d) Exploring prefabricated and modular design options throughout the
detailed design phase to minimise construction waste; specifically, precast
reinforced concrete (RC) elements, including walls, infill panels, and the
Tunnels lining structure.
416. A pre-demolition and retrofit audit was undertaken to assess which materials
can be re-used or recycled in order to retain maximum value and advise on
material recovery strategies.
417. Total demolition waste forecast is 36,257 Tonnes of with an estimated
recovery rate (reuse/recycling) of circa 95%. Concrete that will be crushed
accounts for 90% of total waste by weight. Plant equipment, furniture and
Bakelite have been designated for possible reuse with all other items
proposed for recycling at a raw material level. Further details will be provided
at detailed design stage.
418. The ‘material recovery options’ table indicates how materials will be
segregated and which will be sent to specialist recyclers for further
processing. The development will submit a Waste Management Plan and
advise the contractor of the targets to be achieved.
419. A number of specific elements have been earmarked for reuse, depending on
their condition:
cast iron shaft rings repurposed as lift shaft cladding
shaft linings will be reused as architectural elements lining the new stair
and lift shaft.
Brickwork and concrete louvres to rebuild 39 Furnival St.
125
420. Updates to the detailed Circular Economy Statement are required by condition,
prior to commencement (excluding demolition), and post completion, in line with
the Mayor’s guidance on Circular Economy Assessments. The statement is to
include details of elements recovered for reuse on/off site and the demountable
internal partitions.
BREEAM
421. Emerging City Plan 2040 Policy DE1: Sustainability Standards requires
proposals for major development to achieve a minimum BREEAM rating of
“Excellent” (70% of credits) and aim for “Outstanding” (80% of credits) against
the current, relevant BREEAM criteria at the time of application, obtaining
maximum credits for the City’s priorities (energy, water, pollution, and materials)
as well as the climate resilience credit in the Waste category.
422. Given the specific nature of the development and following discussion with CoL
officers and BREEAM the assessment type selected is: BREEAM Non-
Domestic Refurbishment and Fit Out 2014 Bespoke.
423. The development is targeting a high-scoring ‘Very Good’ rating, which does not
meet City Plan policy of minimum ‘Excellent’. The pre-assessment results show
a target score of 67% and a potential score of 81% (Outstanding) if all the
additional credits identified were achieved. This demonstrates good scope to
achieve an ‘Excellent’ rating as a minimum. Options for additional credits are to
be incorporated into the project cost plan to assess the costs required to
achieve an ‘Excellent’ rating.
424. Pre-assessment results show the development to be on track to achieve high
credits in the Water category and moderate credits in the Energy, Materials and
Pollution categories.
425. A post construction BREEAM assessment is required by condition.
Whole Life-Cycle carbon emissions
Policy and guidance
426. London Plan Policy SI 2 (Minimising greenhouse gas emissions) requires
applicants for development proposals referable to the Mayor (and encourages
the same for all major development proposals) to submit a Whole Life-Cycle
Carbon assessment (WLCA). The assessment captures a building’s
operational carbon emissions (from regulated and unregulated energy use), as
well as embodied carbon emissions, (i.e. those associated with raw material
extraction, manufacture and transport of building materials and construction)
and emissions associated with maintenance, repair, and replacement as well
as dismantling, demolition and eventual material disposal. The Circular
Economy strategy is therefore closely interlinked, addressing reuse and
126
recycling of existing buildings and materials, as well as the longevity, flexibility,
and adaptability of the design proposal.
427. Core Strategic Policy CS15 of the City’s Local Plan requires “all redevelopment
proposals to demonstrate the highest feasible and viable sustainability
standards in the design, construction, operation and “end of life” phases of
development.
The application proposal:
428. Approximately 75% of the proposed development by floor area (GIA) is made
up of retained existing entities (all tunnels, shafts and 31-33 Holborn buildings),
whilst the other 25% (Furnival St) is new build.
429. The proposed change of use would transform the Tunnels into a cultural venue
with the exhibition divided broadly into two key components a permanent
historical section occupying the Streets’ tunnels and a flexible digital
component located in the Avenues’. Within the flexible avenues spaces
innovative digital led experiences will be developed, sometimes combined with
physical installations. These experiences will be short to medium term
exhibitions and one-off events. Detailed exhibition content would be developed
during the refurbishment period. The DAS describes the proposal as follows:
The seamless integration of state-of-the-art audio-visual technology will form a
key element in the delivery of a successful immersive and interactive visitor
experience, with a combination of LED screens, projectors and advanced
sound system technology built to create best in class immersive experiences.
Figure 14. Indicative projectors in the tunnels
127
430. The WLCA lays out three potential fit-out scenarios based on differing extents
of audio-visual (AV) equipment (indicative final fit-out designs) which result in a
very wide range for both embodied and operational carbon emissions. The
extent of AV will depend on the museum operator and programme of temporary
(short or medium term) exhibitions and special events, changing throughout the
year. The WLCA and Energy Statement have been based on the medium use
scenario.
Table. 8. Implications of different Scenarios
Scenario
Summary
Implications
Low
Base building/CAT A design
(inc. heating, cooling,
ventilation, lighting and fixed
energy loads such as lifts)
operating with anticipated
occupancy and opening hours
but only limited audio-visual
(AV) equipment installed.
Includes audio-visual and other
equipment for the Heritage Museum
in the Streets, and the Bar, and
limited use of projectors in the
Avenues.
Many of the cultural use scenarios
fall in this category.
Medium
Base building plus a mix of low
energy AV systems including
some LED screens and high-
fidelity projectors.
Based on anticipated occupancy
and opening hours. Improved
HVAC efficiencies due to
equipment running at part load
and the use of cooling from
ambient air temperatures.
Balanced use of projector
technology and LED. Includes
higher LED loads including music
events or immersion visual
experience, set out in the Cultural
Plan, but does not include the full
extent of AV provision allowed for
the highest case.
This is a conservative position that
allows much cultural flexibility.
High
Based on anticipated occupancy
and opening hours. Base
building plus, a higher amount of
AV equipment with a high
proportion of LED screens.
The Highest case relates to the
possible installation of a fully
immersive LED solution installed in
up to 50% of the surface area of the
Avenues.
This level of energy use may
happen for some cultural
installations but is not expected to
be applied for long periods of time.
The table below provides a breakdown of screen area and number of projectors by
area for each scenario.
128
Low scenario
Medium scenario
High scenario
Screen
area
(m2)
No. of
projectors
Screen
area (m2)
No. of
projectors
Screen
area (m2)
No. of
projectors
Entrance Hall
0
1
102
12
204
23
Avenues
0
10
1104
63
2208
126
Streets
0
10
788
33
1575
33
Total
0
21
1994
108
3987
182
The table below shows a comparison of upfront and total WLC carbon figures by
scenario and with GLA Retail Benchmarks.
431. Total embodied WLC emissions per m2 for Medium and High scenarios are
substantially higher than the GLA Retail Benchmarks. It is noted that retail
benchmarks are not representative of this unique development but are
considered the most relevant by the applicant and agreed by the 3rd party
reviewer of the WLCA.
432. The detailed WLC and energy assessments are based on the medium scenario.
The final fit-out is currently uncertain but will be developed throughout the
detailed design stages and finalised once museum operators are on board. A
detailed whole life-cycle carbon assessment confirming the proposed fit-out
plan including quantities of audio-visual equipment and predicted frequency of
events or special exhibitions as well as the associated carbon impacts is
required by pre-commencement (exc. demolition) condition.
129
Table 9. Life-cycle carbon emissions by module based on the medium scenario.
Estimated
Whole Life
Carbon
Emissions (over
60-year
lifespan)
Upfront
Embodied
Carbon
(A1-A5 excl.
sequestered
carbon)
Total embodied
Carbon
(A-C excl. B6-
B7; incl.
sequestered
carbon)
Module
B1-B5
Whole
Building
Operational
carbon
(B6-B7)
Total Whole
Life Carbon
(inc. B6)
Development
Total (kg CO2e)
7,911,775
17,554,764
9,087,567
11,582,588
29,137,352
Total per m2
(kg CO2e/m2
GIA)
745
1,652
855
1,090
2,742
433. Total WLC emissions (embodied and operational) are estimated at 29,137,352
kgCO2e.
434. Embodied carbon emissions total 17,554,764 kgCO2e with MEP equipment
accounting for approximately 70% (~15% is typical for an office scheme
according to research by LETI). Two-thirds of those embodied emissions from
MEP are attributed to maintenance and replacement.
435. The sustainability consultants included an estimated embodied carbon
comparison with the Museum of London and Liverpool Everyman Theatre to
provide context with buildings of a more similar programme to the proposed
development. A comparison of operational emissions was not provided.
Table 10. Estimated embodied carbon comparisons
London Tunnels
Medium
Scenario
Museum of
London
Liverpool
Everyman
Theatre
Year
2029
2026
2013
Size (m2 GIA)
10,625
49,996
4,690
Visitors/year
2,000,000
(target)
2,000,000
(target)
120,000 (actual)
Embodied carbon
(A-C) total (kgCO2e)
17,555,000
29,997,000
4,845,000
Embodied carbon per
m2 over 60-year period
(kgCO2e)
1,652
600
1,033
Embodied carbon
per visitor over 60-year
period (kgCO2e)
146
250
670
436. The Tunnels has the highest embodied carbon ‘intensity’ (rate per m2) of the
venues assessed. The underground nature and elongated form of the tunnel
130
network naturally requires extensive ventilation/cooling and long servicing runs
in order to be made into a viable tourist attraction. The comparison table shows
that if these venues attract (close to) their target (or actual) visitor numbers then
over a 60-year period the Tunnels attraction would have a lower embodied
carbon cost per capita than these other indicative cultural venues. The
embodied carbon cost (per capita) for the tunnels becomes less than the
Museum of London after around 35 years.
Furnival Street New structure
437. A variety of structural systems were considered during design phase table
and evaluated against project brief, architectural design intent, programme,
sustainability, and cost. Relative carbon intensity was assessed at high-level
based on previous experience. The primary system chosen is a concrete
frame with post-tensioned concrete slabs. Steel and CLT options were
discounted before carbon and detailed structural design was undertaken as
they cannot achieve the architectural intent for structural floor zone and
spans. The choice is justified by the intention to allow greatest flexibility in
floor space and plant equipment layout.
438. The strategy to minimise embodied carbon includes the following measures:
Hybrid elements of structure with a variety of structural framing and floor
plate types has been proposed to optimise efficiency based on
parameters such as loading requirements
Prioritisation of prefabricated elements, likely to include walls, infill panels
and tunnel lining structure, to minimise material use and thereby reduce
construction waste and carbon emissions
Floor load allowance to be refined following clarification of MEP plant in
next stage. To avoid overspecification of predicted loads;
Post-tensioned system reduces slab thickness and requirement for beams
Refrigerant specified for cooling system has very low global warming
potential of <1 a negligible effect on global warming
439. The design and specifications will ensure that environmentally sensitive (non-
toxic) building materials are used throughout. Specifically, the design and
specification of materials used internally will be based on the use of products
that contain low levels of or no Volatile Organic Compounds (VOCs). This is
important for health and wellbeing as well as carbon reduction.
440. Design optimisations will be explored at detailed design stage to reduce carbon
emissions including:
Further reduction of superstructure PT slab thickness
Non-metallic ductwork
Alternative chilled ceilings
131
Potential to source reused steel sections
Reclaimed raised access flooring.
Operational energy strategy and carbon emissions
Policy and Guidance
441. London Plan Policy SI 2 Minimising greenhouse gas emissions sets out how
major developments should be net-zero carbon by “reducing greenhouse gas
emissions in operation and minimising both annual and peak energy demand
in accordance with the following energy hierarchy:
be lean: use less energy and manage demand during operation
be clean: exploit local energy resources (such as secondary heat) and
supply energy efficiently and cleanly
be green: maximise opportunities for renewable energy by producing,
storing and using renewable energy on-site
be seen: monitor, verify and report on energy performance”
442. Policy SI2 also states that “Major development proposals should calculate
and minimise carbon emissions from any other part of the development,
including plant or equipment, that are not covered by Building
Regulations, i.e. unregulated emissions.” [emphasis added]
443. Development Clause 9.9.2 expands on the priority of the energy hierarchy
which is to minimise energy demand, and then address how energy will be
supplied and renewable technologies incorporated. An important aspect of
managing demand will be to reduce peak energy loadings.” [emphasis
added].
444. London Plan Policy SI4 Managing Heat Risk states that Development should
minimise adverse impacts on the urban heat island through design, layout,
orientation, materials, and the incorporation of green infrastructure. Through an
energy strategy, development should demonstrate how they will reduce internal
overheating and reliance on air conditioning systems in accordance with the
cooling hierarchy.
Application proposal:
445. For the medium scenario, total operational carbon emissions (B6 & B7) are
calculated at 11,582,588 kgCO2e or 1090kgCO2e/m
2
- about 40% of total WLC
emissions.
446. The proposed development employs a highly efficient and fully electric HVAC
system of air source heat pumps, cooling towers, and water-cooled chillers with
heat recovery, which help reduce carbon emissions.
132
447. Avenues and Streets supplied with minimum fresh air via combined general
ventilation and smoke control ductwork. Duct sizes are minimised to the smoke
requirement to save material and embodied carbon and CO2 control in air
handling units and Avenue zones help minimise energy consumption.
448. The operational energy of the proposed development is affected significantly
by the final fit-out and specific equipment associated with exhibitions/events as
demonstrated in the Low, Medium, and High scenarios set out above.
449. Audio-visual equipment has a very significant impact on energy consumption
for the building. Compared with the base building adding projectors across the
Avenues, Streets and Entrance Hall leads to an increase in annual energy
consumption of 188% from 67 kWh/m2 to 126 kWh/m2. This shift also
increases the cooling demand by over 700%.
450. The adopted GLA energy assessment guidance (2022) requires developments
to calculate Energy Use Intensity (EUI), a measure of total energy consumed
in a building annually including regulated and unregulated energy use, as well
as the space heating demand. For offices, the GLA sets a target EUI of 55
kWh/m2(GIA)/year, and a space heating demand of 15 kWh/m2(GIA)/year
whilst the UKGBC target is 90 kWh/m2/year. As there are no industry targets
for cultural buildings and given the unique nature of the Tunnels, these targets
is for guidance only.
Table comparing estimated annual energy use intensity for the proposal
scenarios with office targets.
Office Targets
Low
scenario
Medium
scenario
High
scenario
GLA
Target
UKGBC
target
2025-30
UKGBC
target
2030-35
Whole building
energy
intensity
kWh/m2GIA
67
126
191
55
115
90
451. The current anticipated competition date for the Tunnels is 2029. Against the
2025-30 target, the EUI for the medium and high scenarios is 10 and 66%
higher respectively. Against the 2030-35 target, the medium and high scenarios
are 40% and 112% higher respectively.
452. The Tunnels have low heating loads due to the insulation/thermal mass
provided by the surrounding soil. Cooling demand for the site is predicted to be
very high due to large visitor numbers and intensive AV equipment in a confined
environment. The maximum predicted cooling load is 1.8MW.
133
453. The following strategy has been designed to optimise cooling delivery and
minimise waste heat rejection (impact on the local heat island) but there is a
significant embodied carbon footprint associated with the extent of plant
required:
Heat recovery has been implemented wherever possible to minimise heat
rejected and improve system efficiencies.
Heat is rejected by highly efficient cooling towers and water source
chillers, circulating chilled water
Chilled water panels located throughout the ‘avenue’ and streets’ tunnels
absorb heat locally helping to capture heat from equipment such as
screens and projectors.
The inclusion of chilled panels enables cooling during unoccupied hours
using only the cooling towers, avoiding energy usage associated with
operating the chillers.
Rejected heat from the Tunnels will be able to pre-heat air in order to heat
above ground areas of the building and provide hot water.
454. The application proposal has been designed to achieve an overall 41.4%
reduction in regulated emissions compared to the notional existing building
based on GLA energy guidance, meeting the London Plan requirement of 35%
minimum on site.
455. The proposal does not meet the GLA requirement for net zero carbon, so a
carbon offset payment in required. This has been provisionally calculated based
on the medium scenario as £123,951. An updated energy assessment based
on fit-out with a high level of AV equipment should be undertaken prior to
occupation and the offset payment calculated accordingly. The energy
statement should be secured under condition. The payment should be secured
through S106 agreement.
456. A S106 clause will be included requiring reconfirmation of this energy strategy
approach at completion stage and carbon offsetting contribution to account for
any shortfall against London Plan targets, for the completed building. There will
also be a requirement to monitor and report the post construction energy
performance to ensure that actual operational performance is in line with GLA’s
zero carbon target in the London Plan.
Be Lean
457. The first step of the energy hierarchy is to reduce demand through energy
efficiency measures. The majority of the development utilises existing buildings.
Due to the existing heritage of the projects, has not been possible to update the
material in the actual Tunnels however these already benefit from the insulation
provided by the soil surrounding the structure.
134
458. At application stage, the proposed energy demand reduction strategy (‘be lean’)
only achieves an operational saving of 0.3%, well below the 15% GLA
requirement for commercial buildings.
459. This is due largely to the nature of the tunnels (subterranean, long, enclosed
spaces), combined with the operational requirements of the proposed change
of use to museum/event space high visitor numbers and AV equipment
requiring ventilation and cooling.
460. The energy efficiency measures proposed exceed minimum building regulation
requirements and include:
Highly efficient building fabric at Furnival Street
Centralised ventilation with heat recovery
All spaces will include 100% low energy lighting with lighting
controls/sensors
Smart control systems and building management system to ensure
efficient control and monitoring of MEP services to minimise energy
waste.
Be Clean
461. The applicant team has consulted with the local heat network operator (Citigen).
At present there is no heat network infrastructure planned for the area. In
accordance with GLA guidance a low temperature hot water system has been
specified and the plant room designed to facilitate heat network connection in
future. Evidence of provision for connection to a future heat network is required
by an obligation.
462. Utilising waste heat through connection to a heat network, direct transmission
to a nearby building or otherwise, is key to reducing the environmental impact
of the proposed development. An obligation is to be included which requires the
development to thoroughly explore possible options for beneficial rejection of
waste heat.
Be Green
463. The proposed development employs a fully electric HVAC strategy using highly
efficient air source heat pumps and water-cooled chillers which help reduce
carbon emissions.
464. Potential for roof mounted PV at Furnival Street was assessed but roof area is
limited. The largest area is occupied by plant which requires ventilation so
cannot accept PVs above. The other roof area has been prioritised as a staff
amenity terrace as the only outside space available on the site.
135
465. A detailed Whole Life-Cycle carbon assessment incorporating improvements
achieved through the detailed design stage, and a confirmation of the post-
construction results are required by conditions.
Urban Greening and Biodiversity
466. Local Plan Policy DM19.2 promotes Urban Greening and Biodiversity, DM 10.2
(Design of green roofs and walls) and 10.3 (Roof gardens and terraces)
encourages high quality roof gardens and terraces.
467. The existing site has negligible ecological value. The proposal provides
greening at roof level, on the staff terrace and plant room roofs, and a green
wall on the south façade of 40-41 Furnival Street. At level 4, a planting palette
of flower rich perennial planting, including small trees/shrubs and climbers, at
level 5, an intensive roof sown with a wildflower seed mix with plug planting.
These measures will improve public realm quality and achieving a UGF of
0.135.
468. Project constraints make it difficult to achieve the recommended UGF of 0.3;
Proposed development is predominantly underground
136
Constrained form, in part due to rights of light envelope, provides limited
area to provide more greenery without away from the only outdoor space
available for the staff.
Proposed Roofs
Extensive Green Roof Area
31.2 m²
Intensive Green Roof Area
24 m²
Green wall
13.5 m²
Blue Roof Available
Attenuation Volume
4.9 m³
Rainwater harvesting tank
8 m
3
Photovoltaic Panels
None
469. Details of the quality and maintenance of the proposed urban greening are
required by conditions (1. Rainwater attenuation and biodiversity, 2. Visual
amenity).
Climate Change Resilience
Water resources
470. The development incorporates best practice technologies to limit its water
consumption to a minimum. Including:
Water leak detection and automatic shut off valves
Water efficient / low flow sanitary fittings
Rainwater harvesting for irrigation/WC flushing
Flood Risk, Water Management and Drainage
471. The GLA’s London Plan 2021 Policy SI 12 gives specific guidance on the
provision of flood resilience which is relevant to this development with Policy SI
13 noting that developments should aim to achieve greenfield runoff rates and
ensure run-off is managed as close to the source as possible.
472. Local Plan 2015 policy CS18 seeks to “reduce the risk of flooding from surface
water throughout the City, by ensuring the development proposals minimise
water use, reduce demands on the combined surface water sewer and
sewerage network”. The use of Sustainable Drainage Systems (SuDS) is
supported by Local Plan policy CS18 and policy CR3 of the draft City Plan 2040.
473. The submitted Flood Risk Assessment identifies the site as lying in Flood Zone
1 (an area of very low flood risk). As such the application site is at low risk of
fluvial and tidal flooding. The risks of groundwater flooding are also considered
to be low, however, given the subterranean nature of the tunnels appropriate
137
waterproofing and underfloor drainage and pump systems are proposed to
collect any remaining seepage and redirect it to the public sewer system.
474. The proposed drainage strategy includes capturing rainwater landing on roof
levels and remaining impermeable areas and directing this to the blue roof
system or via downpipes/pipe network to storage systems (tanks) before being
discharged to the existing combined public sewer in Furnival Street. Systems
have been sized to accommodate the 1 in 100-year storm rainfall event with a
40% additional allowance for climate change.
475. The proposed maximum discharge rate from the Proposed Development is 1.5
l/s, which is as close as technically feasible to greenfield run-off rates given the
nature of the development and offers a significant betterment on existing pre-
development run-off rates.
476. The Lead Local Flood Authority and Thames Water have been consulted and
recommended conditions and informatives are to be attached.
477. The proposed Flood Risk and SUDS strategy would accord with policies CS18
of the Local Plan 2015, S15, CR2 and CR3 of the draft City Plan 2040 and
policies SI12 of the London Plan.
478. Although the likelihood of flooding is considered low for the development, the
consequences of flooding in the Tunnels is high so the following are considered:
Appropriate waterproofing measures should be deployed to manage risk
of groundwater seepage.
Any routes for surface water ingress to the Tunnels (i.e. via the shafts) are
protected by finished floor levels that rise to a minimum of 150mm above
adjacent street levels;
Where practicable, all electrical and life safety infrastructure is provided a
minimum of 300mm above finished floor levels, or where not practicable,
equipment is designed to be flood resilient;
479. A Flood Evacuation Plan was submitted over the course of the application
which has been reviewed by CoL Environmental Resilience Officer. The
proposed egress and access routes both internal and external, have been
identified go through unflooded areas in compliance with CoL Flood Emergency
Plans for New Developments Planning Advice Note (June 2020). The site is
low flood risk and the possible flooding mechanism of the tunnel (groundwater
and burst watermains) fall into residual risk (i.e. it is defended against and will
only result if those defences fail). The two routes with distinct exit points helps
to mitigate this risk yet further. Officers would therefore consider this
development to meet the policy in this area (flood egress and access). Further
138
details would be required to be provided in the AMP under Section 106, to
ensure safe egress of all groups of people is being considered.
Heat Stress
480. Policy SI 4 of The London Plan (2021) states that major development proposals
should reduce potential overheating, and reliance on air-conditioning systems,
and demonstrate this in accordance with its cooling hierarchy.
481. The most prescient risks to the building of these changes are overheating, and
increased cooling demands & costs. Thermal modelling has been carried out
as part of the design process to ensure the impacts of these heightened
temperatures can be managed and minimised.
482. 100% low energy LED lighting will reduce internal heat gains whilst an efficient
water-cooled system allows mitigation of overheating space. All electric cooling
plant minimises carbon impact of additional cooling requirement.
Urban Heat Island
483. All air handling systems will be equipped with heat recovery systems to reduce
the amount of heat expelled to the external environment.
484. Water Greening on the Furnival Street terrace will contribute to a reduction in
the heat island effect as plants mitigate retention of heat.
Natural Capital and Pest & Diseases
485. Overall, this development includes a range of measures which will improve its
resilience to climate change. Details of these measures will determine how
effectively the building performs in coming decades, with detailed modelling and
planting plans required by conditions including comparison against the UK
Climate Projections UKCP18 to 2080 (tools and data that show how the UK
climate may change in the future, based on potential emissions scenarios).
486. Prior to the commencement of the development (other than demolition) a
Climate Change Resilience Sustainability Statement (CCRSS) shall be
submitted to and approved in writing by the Local Planning Authority, that
demonstrates how the development will be resilient and adaptable to predicted
climate conditions during the lifetime of the development. This condition may
be fulfilled by a satisfactory assessment in support of the BREEAM Wst 05
credit.
Conclusion on Sustainability
487. The City of London Climate Action Strategy supports the delivery of a net zero,
climate resilient City. The agreed actions applicable to the planning process
139
relate to the development of a renewable energy strategy in the Square Mile,
to the embedding of carbon analysis, circular economy principles and climate
resilience measures into development proposals and to the promotion of green
spaces and urban greening as natural carbon sinks. The Local Plan policies
require developments to demonstrate highest feasible and viable sustainability
standards in the design, construction, operation, and end of life phases of
development as well as minimising waste, incorporating climate change
adaption measures and urban greening, and promoting biodiversity and overall
wellbeing.
488. Demolition of both buildings on Furnival Street is deemed acceptable, justified
by the practical constraints of the construction process, achieving greater
access to the Tunnel network (for visitors and equipment) and the greater
servicing efficiencies which can achieved through the size/layout of a new build.
489. The whole life-cycle carbon assessment sets out the large, embodied carbon
cost of the refurbishment and fit-out works as well as plant replacement over
life-cycle period of 60 years. High energy and cooling demand are driven by
high visitor numbers and extensive AV equipment proposals. However, a highly
efficient, water-based and localised cooling system with heat recovery has been
designed to manage overheating within the tunnel network and reduce
operational energy.
490. The London Tunnels proposal offers a unique visitors attraction in a strategic
location for a new cultural offering. The scheme would bring an underutilised
piece of historic infrastructure with a storied past into public use, bringing
economic benefits to the area. The change of use of deep level tunnels
designed for emergency shelter and secure telecommunication to a cultural
exhibition and event space offering an immersive audio-visual experience is
technically challenging and requires an extensive amount MEP equipment to
accommodate the high visitor numbers targeted/anticipated.
Security
491. London Plan Policy D11 requires consultation with the City of London Police to
identify the community safety needs and maintain safe and secure
environments. Local Plan Policy CS3 and Emerging Policy S2 highlight the
needs for the City to be secure from crime, disorder and terrorism thereby
increasing public and corporate confidence in the city's role as the world's
leading international financial and business centre.
492. Concerns have been raised by residents regarding the security and safety
impacts of the proposed development.
140
493. A Security report has been prepared and submitted as part of this application.
The Security Strategy focuses on internal attacks in the tunnels and proposes
mitigation measures such as the introduction of a bag scanning and searching
system at check-in of visitors. All visitors would be required to pre-book their
visit, with information provided at the booking regarding the security process
and a list of prohibited items. Locker rooms would be available at ground level,
before entering the exhibition space, where visitors would lock their personal
staff that cannot be carried inside the tunnels. A grouping system would be
adopted to control visitors journey and access to spaces. Video Surveillance
Systems (VSS) will monitor the site through Security Control Room (SCR). It is
not anticipated to have people queuing outside the building and therefore
Hostile Vehicle Mitigation (HVM) has not been proposed for implementation.
494. Visits to the bar would be also pre-booked. The bar is only accessible via
Fulwood Place, the secondary entrance in Camden, where security control
would be in place. Access from the bar to any other areas of the tunnels would
not be available outside of the exhibition spaces operational hours.
495. City Police and Counter-Terrorism Security Advisers have reviewed the
information provided and have made a number of recommendations to prevent
potential attacks on site with advice given for ongoing consultation with them
as the plans for the site develop. Officers consider that the application complies
with London Plan Policy D11, Local Plan Policy CS3 and Emerging Policy S2.
Recommendations for Operational and Events Management Plan have been
made, including crowd management, dispersal, levels and system of control on
site that would help prevent antisocial behaviour, to be secured via Section 106.
Informatives have been also recommended for the continuous involvement of
the City Police and CTSA at the detailed design stage of the scheme.
Suicide Prevention
496. Local Plan policy CS3 requires that security and safety measures are of an
appropriate high-quality design. The City Corporation has recently adopted the
Planning Advice Note “Preventing Suicide from High Rise Buildings and
Structures” (2022) which advises developments to ensure the risk of suicide is
minimized through appropriate design features. These features could include
planting near the edges of balconies and terraces, as well as erecting
balustrades.
497. Policy DE4 of the draft submission City Plan 2040 advises that appropriate
safety measures should be included in high-rise buildings, to prevent people
from jumping or falling.
498. The proposal includes a roof terrace at level four, which would only be
accessible to staff working on-site.
141
499. The Design and Access Statement confirms that the roof terrace has been
designed in line with the adopted Advice Note with the provision of a balustrade
of 1.4m in height to the perimeter of the terrace, exceeding the 1.1m required
by building regulations and in line with the 1.4m suggested by the Planning
Advice Note. Perimeter planters are also proposed to be embedded in the floor
to restrict and deter access to the boundary of the useable terrace.
500. The terrace would not be accessible to any member of the public which
provides a more controlled use of the outdoor space. However, a condition has
been recommended for details of suicide prevention measures to be submitted
and approved by the City prior to the first occupation of the building.
501. The proposal is considered to comply with Local Plan Policy CS3 and draft City
Plan Policy DE4 and the recommendations of the Planning Advice Note. A
condition has been imposed as mentioned above.
Fire Statement
502. Policy D12 of the London Plan seeks to ensure that proposals have been
designed to achieve the highest standards of fire safety, embedding these into
developments at the earliest possible stage. Policy D5 requires development to
incorporate safe and dignified emergency evacuation for all building users with
a minimum of one lift per core to be a suitably sized fire evacuation lift.
503. The application is accompanied by a Fire Statement in accordance with London
Plan Policy D12B for major developments and the fire safety regulations.
504. The application predicts an annual visitation of two million on site. The tunnel
exhibition visitors are estimated to reach maximum 750 people/hour and the
visitor of the underground bar is estimated to be 120 people/hour. The Fire
Statement clarifies that the conventional British Standards guidance would
potentially not be adequate for achieving optimal fire safety levels due to the
unique nature of the proposed development. Instead, an engineering and risk-
based design approach has been suggested, along with the implementation of
a Basis of Design (BoD) document to guarantee adherence to fire safety
regulations.
505. A water-based suppression system is proposed to be installed which would be
activated in the event of a fire to extinguish or control the fire. The presence of
fire/smoke shutters in the tunnels ensures that there are several layers of fire
separation between the occupants and the fire source. This compartmentation
allows the occupants to safely make their way towards the protected lobbies of
the evacuation shafts. The lobbies next to the lift shafts at the two entrance
points would be designated as safe areas equipped with fire-resistant materials
142
and would be pressurized to prevent smoke accumulation in case of sprinkler
system failure. These refuge areas can accommodate up to 50% of the tunnel's
occupants for evacuation through lifts or stairs.
506. In line with London Policy D5, evacuation lifts would be available at both
entrances. At Furnival Street the round lifts would serve the east side of the
tunnels and levels 1 and 2, and the lifts at the rear would serve the upper levels
of the Furnival buildings for evacuation to Furnival Street. Fulwood Place works
as an emergency exit to the west side of the tunnels. Vertical evacuation would
be available on this side as well that leading to Fulwood Place and then to High
Holborn.
507. Incorporating smart signage and wayfinding systems linked to the detection
system will help guide occupants to the protected lobbies based on the fire's
location.
508. The CoL District Surveyors have reviewed the application and the Fire
Statement and raised no objections.
509. Given the somewhat unique nature of the proposal and the proposed use,
officers have sought London Fire Brigade’s view of the submitted documents.
The London Fire Brigade (LFB) is not a statutory consultee under the Town and
Country Planning Act 1990, however due to the uniqueness of the site, the
subterranean layout and the long underground distances Offices consider it
pertinent to review measures in detail at an early stage. London Fire Brigade
have therefore indicated various measures that would need to be considered
post planning stage.
510. In general, LFB is content that the methodology outlined in BS 7974:2019 would
be applied and this has been supported. As part of this methodology a
Qualitative Design Review (QDR) process would be undertaken and LFB would
expect to be involved in this process as a key stakeholder. This QDR process
would take place post planning and would therefore fall under Building
Regulations, i.e. post planning. Notwithstanding this however, a number of
areas have been identified for review given concerns from LFB and the
applicant has confirmed that these would be reviewed under any subsequent
next step. These identified matters consist of the extended travel distances for
occupant means of escape and firefighter access/intervention, radio
communications coverage for firefighters and other emergency responders,
Electric Powered Personal Vehicles and the construction phase fire safety.
511. Again, while these issues would be included as part of any QDR process, which
takes place prior to a statutory Building Regulations consultation with LFB, they
are discussed below for completeness.
143
512. With regard to the extended travel distances for occupant means of escape and
firefighter access, given the nature of the existing tunnel infrastructure is such
that travel distances hose laying distances for firefighter access/intervention will
be extended beyond the distances recommended within guidance. LFB
understand that extended hose laying distances are proposed to be addressed
by providing an enhanced dry fire main system, similar to that provided for sub-
surface railway tunnel infrastructure. While there is no objection to this in
principle the technical details of this would need to be reviewed at QDR stage
in conjunction with the LFB. Equally, in terms of the of the radio communications
for firefighters while the applicant has confirmed that the scheme would have a
Distributed Antanae System so that there will be mobile communications
provisions in the tunnels, this would need to be confirmed under the QDR
appropriately.
513. Regarding Electric Powered Personal Vehicles (EPPVs) officers have sought
that the Accessibility Management Plan would secure the use of self-
propelled/transit wheelchairs to limit the use of lithium-ion power units within
the Tunnels. While this would be reviewed under the QDR process the
Accessibility Management Strategy, proposed to be secured under any
attached legal agreement, would secure an initial requirement to limit any
potentially fire issues in the future. This would also be similar to the construction
phase fire safety which would again require further consultation with the LFB at
QDR stage, prior to Building Regulations, noting that a sufficient fire risk
assessment to demonstrate compliance with The Order during construction
would be required from the applicant.
514. With specific respect to LFB’s view around compliance with planning policies
given the depth of the premises from the access level and the fact that
occupants other than persons of restricted mobility may experience difficulty in
evacuating upwards over a height in excess of 30m, LFB recommend that
consideration be given to providing additional evacuation lift capacity and this
should be taken into account when undertaking the evacuation lift capacity
assessment expected under London Plan 2021 Policy D5(B5). Officers have
proposed a requirement in the proposed Access Management Plan to review
the evacuation proposal against London Plan Policy D5 and as such adhering
to the comments received from LFB. This would be secured within the attached
legal agreement and would require submission of details for further review. For
absolutely clarity however, while the QDR process lies outside of the planning
process, officers have sought confirmation from the applicant that the above
matters falling outside the scope of planning would be reviewed at this QDR
stage and this reminder would be included within informatives attached to any
permission.
515. The proposed development would therefore meet the requirements of Policy
D5 and D12 of the London Plan.
144
The Public Sector Equality Duty (section 149 of the Equality Act 2010)
516. When considering the proposed development, the Public Sector Equality Duty
(PSED) requires City of London to consider how the determination of the
application will affect people who are protected under the Equality Act 2010,
including having due regard to the effects of the proposed development and
any potential disadvantages suffered by people because of their protected
characteristics.
517. The City, as a public authority must, in the exercise of its functions, have due
regard to the need to:
Eliminate discrimination, harassment, victimisation and any other conduct
that is prohibited by or under this Act;
Advance equality of opportunity between persons who share a relevant
protected characteristic and persons who do not share it;
Foster good relations between persons who share a relevant protected
characteristic and persons who do not share it.
518. The characteristics protected by the Equality Act are age, disability, gender,
reassignment, marital status, pregnancy and maternity, race, religion or beliefs,
sex and sexual orientation.
519. An Equalities Impact Assessment has been carried out in respect of the scheme
by the applicant which did not identify potential for discrimination or adverse
impact to any protected groups.
520. It has been considered that the physical design and layout of the scheme has
been designed to be accessible to all regardless of age, disability, whether you
are pregnant, race, sex, sexual orientation and gender reassignment and
marital status. This would be achieved through measures such as:
Pedestrian approaches to the entrances that are safe, segregated from
vehicle traffic;
The provision of step-free access to all parts of the building. Step-free
access for staff use of the roof terrace in Furnival Street;
Large passenger lifts with capacity to accommodate Type C mobility scooter
access to the retail floors of Furnival Street and the cultural exhibition
spaces in the tunnels;
Provision of a type C mobility scooter parking space and charging point for
staff at ground level;
Secured accessible cycle parking for staff at ground floor of Furnival Street;
Unisex wheelchair-accessible sanitary facilities for visitors upon arrival and
to serve the retail areas in Furnival Street, and within the tunnels, including
provision of a Changing Places toilet;
Provision of a mix of male, female and unisex toilets including facilities for
ambulant disabled users in Furnival Street and within the tunnels. Dedicated
sanitary facilities in close proximity to the bar;
145
Welfare facilities for visitors such as wheelchair-accessible baby changing
facilities across the site;
Provision of quiet spaces, a first aid room and seating within the final fit out
of the tunnels;
Wheelchair-accessible sanitary and refreshment facilities to serve the staff
areas;
Evacuation lifts for the safe and dignified evacuation of disabled users;
Interior design, wayfinding strategy, design of exhibition spaces, lighting,
acoustics and use of assistive technology to be detailed at the appropriate
design stage taking into consideration the good practice guidance of BS
8300:2018 and PAS 6463:2022;
The provision of resting points on routes longer than 50m from key points of
arrival to the site’s main entrance including accessible seating;
The commitment to provide and additional blue badge parking on Furnival
Street and the public realm improvement works (to be secured via Section
278 agreement).
521. Final detail of an Access Management Plan and Operational Management Plan
would be secured by condition in order to secure the access requirements of
all users are being met and to cover all aspects of the user experience from the
provision of pre-arrival information in accessible formats, to the management
of exhibition spaces (e.g. offering quiet visiting times) and staff training in
accessibility and inclusion and in evacuation procedures.
522. The applicant has made a commitment to provide social benefits through the
development that would promote equality and inclusion. Examples of such
benefits include:
Free school visits for schools around London;
Partnerships with universities, institutions, local communities and
underrepresented artists to co-curate the exhibition spaces
Training opportunities accessible to all
523. Conditions, informatives and Section 106 and 278 agreements would be
required to cover the accessibility management and operation of the exhibition
space and other matters such as the accessible parking, resting points and
inclusive procurements. An informative would be placed on the permission
reminding future occupiers of their duty under the Equality Act 2010.
524. A suitable programme of highway works and conditions relating to construction
and demolition management and logistics, noise and dust management are
recommended in order to minimise the impact of the scheme on nearby
occupiers and those with Protected Characteristics.
146
525. The proposed development has been assessed against policy GG1 of the New
London Plan and would be considered to support and promote the creation of
an inclusive London where all Londoners, regardless of their age, disability,
gender, gender identity, marital status, religion, race, sexual orientation, social
class, or whether they are pregnant or have children, can share in its prosperity,
culture and community, minimising the barriers, challenges and inequalities
they face.
526. For the reasons set out above officers consider that overall the proposal would
have a positive impact on Protected Characteristics. Any potential negative
impacts that could arise through construction and operation would be managed
by the recommended conditions.
Human Rights Act 1998
527. It is unlawful for the City, as a public authority, to act in a way which is
incompatible with a Convention right (being the rights set out in the European
Convention on Human Rights (“ECHR”)).
528. Insofar at the grant of planning permission will result in interference with the
right to private and family life (Article 8 of the ECHR) including by causing harm
to the amenity of those living in nearby residential properties, it is the view of
officers that such interference is necessary in order to secure the benefits of
the scheme and therefore necessary in the interests of the economic well-being
of the country, and proportionate. Although it is recognised that the
development would have some impact on the amenities of the nearby residents
and other adjoining occupiers, including by way of noise and disturbance during
construction, it is not considered that, subject to conditions, the proposal would
result in unacceptable impact on the existing use of nearby residential
properties to an extent that would warrant refusal of the application on those
grounds. It is the view of the officers that the provision of such a unique cultural
and visitor attraction meets Local Plan ambitions and Destination City
aspirations for an evening and weekend economy and in tandem with the wider
socio-economic benefits brought by the proposed development the Minor
Adverse impacts on nearby residential and commercial properties are
outweighed and that such impact is necessary in the interests of the economic
well-being of the country and is proportionate.
529. Insofar as the grant of planning permission will result in interference with
property rights (Article 1 Protocol 1) including by interference arising though
impact on the amenity of adjoining properties, it is the view of officers that such
interference is in the public interest and proportionate.
147
CIL and Obligations
530. The proposed development would require planning obligations to be secured in
a Section 106 agreement to mitigate the impact of the development to make it
acceptable in planning terms. The applicant would enter into a separate S106
agreement with the London Borough of Camden.
531. Contributions would be used to improve the City’s environment and facilities.
The proposal would also result in payment of the Community Infrastructure
Levy (CIL) to help fund the provision of infrastructure in the City of London.
532. These contributions would be in accordance with Supplementary Planning
Documents (SPDs) adopted by the Mayor of London and the City.
533. On the 1st of April 2019 the Mayoral CIL 2 (MCIL2) superseded the Mayor of
London’s CIL and associated Section 106 planning obligations charging
schedule. Therefore, the Mayor will be collecting funding for Crossrail 1 and
Crossrail 2 under the provisions of the Community Infrastructure Levy
regulations 2010 (as amended).
534. CIL contributions and City of London Planning obligations are set out below.
535. Evidence was requested from the applicant to demonstrated whether the
tunnels have been lawful use for six months over the last three years. No
evidence has been provided for the LPA to determine this and they are
therefore considered to be vacant for the purpose of calculating CIL.
MCIL2
Liability in accordance with the
Mayor of London’s policies
Contribution
(excl. indexation)
Forwarded to the
Mayor
City’s charge for
administration
and monitoring
MCIL2 payable
£702,793
£674,681
£28,112
City CIL and S106 Planning Obligations
Liability in accordance
with the City of London’s
policies
Contribution
(excl. indexation)
Available for
allocation
Retained for
administration
and monitoring
City CIL
£461,625
£438,544
£23,081
148
City Planning Obligations
Affordable Housing
£52,200
£51,678
£522
Local, Training, Skills and
Job Brokerage
£31,320
£31,007
£313
Carbon Reduction Shortfall
(as designed)
Not indexed
£123,975
(based on the
whole site)
£123,975
£0
Section 278 (Evaluation and
Design Fee)
Not indexed
£100,000
£100,000
£0
S106 Monitoring Charge
£4,086
£0
£4,086
Total liability in
accordance with the City
of London’s policies
£773,206
£745,204
£28,002
City’s Planning Obligations
536. The obligations set out below are required in accordance with the City’s
Planning Obligations SPD 2021. They are necessary to make the application
acceptable in planning terms, directly related to the development and fairly and
reasonably related in scale and kind to the development and meet the tests in
the CIL Regulations and government policy.
Heads of Terms
a) Highway Reparation and other Highways Obligations (Highways Schedule
of Condition Survey, site access, consents, licences etc)
b) Local Procurement Strategy (including inclusive procurement)
c) Employment and Skills Plan (demolition, construction and end use)
d) Delivery and Servicing Plan (including consolidation)
e) Travel Plan (Including Cycle Promotion Plan)
f) Construction Monitoring Cost (£30,935 First year of development and
£25,760 for subsequent years)
g) Carbon Offsetting (£123,975 - to be reviewed on completion and prior to
occupation of the development)
h) Utility Connection Requirements
i) Section 278 Agreement (CoL). Scope to consider but not be limited to:
149
provide a healthy streets scheme with consideration to providing
a shared surface, increased footpath, additional street furniture,
additional blue badge parking, and further public realm
improvements
improve sustainable transport to and across the area
provide additional greening
maintain the contra flow cycle lane
maintaining access for emergency vehicles
j) Management Plan (including free or discounted tickets for certain groups)
and Public Access and Events Management Plan (in relation to the
cultural/temporary exhibition space)
k) Cultural Implementation Strategy (to restrict demolition until a Cultural
Operator is secured)
l) Access Management Plan (for the operation of the site)
m) Waste Heat Transfer
n) Improving cycle infrastructure on public highway
537. Some financial contributions could be subject to proportional split with London
Borough of Camden.
538. Officers request to be instructed to continue to negotiate and agree the terms
of the proposed obligations and enter into the S278 agreement.
539. The London Borough of Camden has made provision of the following Heads of
Terms to be included in their S106 agreement in accordance with their Local
Plan/SPD:
a) Car free development
b) Construction Management Plan (CMP) and CMP implementation support
contribution of £30,513 and CMP impact bond of £32,000
c) Travel Plan and associated monitoring and measures contribution of
£11,348
d) Electric vehicle charging infrastructure (fast charger) contribution of
£20,000
e) Delivery and Servicing Plan
f) Highways works contribution of £20,000
g) Off-site cycle parking contribution for cycle parking stands of £4,800
h) Pedestrian, Cycling, and Environmental Improvements contribution of
£150,000
i) Micromobility Improvements contribution of £10,000
j) Restriction on coach bookings and picking up/dropping off of customers by
coach outside site’s entrance at 31-33 High Holborn.
k) Requirement to form a construction working group consisting of
representatives from the local community
150
l) Carbon offset payment estimated £123,951
m) Energy Efficiency and Renewable Energy Plan
n) Sustainability Plan (including BREEAM Excellent)
o) Measures to ensure future connection to a local energy network
p) Construction apprenticeships paid London Living Wage (29 in total) and
support fee of £1,700 per apprentice (£49,300)
q) Local Procurement Strategy (including Camden Local Procurement Code)
r) Employment and Training Plan (including work experience placements,
20% local recruitment target, and engaging with Camden schemes)
s) Operational Management Plan
540. The Heads of Terms secured by the City are mostly in alignment with the above
Heads of Terms sought by Camden, however there are inevitably some
differences due to the respective Local Plans, context of the parts of the
development falling on different sides of the LPAs boundary, and separate
assessments of the proposal. As such, some obligations are sought by one
authority and not the other.
541. The boroughs will be in consultation with each other both during the drafting of
the respective legal agreements and, where appropriate, in the process of
discharging relevant obligations to ensure that where any Heads of Terms
extend across the borough boundaries or are required by only one borough, the
obligations are consistent and enforceable.
542. Consideration may also be given to the boroughs being a party to the other
borough’s legal agreement to acknowledge that, where relevant, the obligations
are enforceable across the whole of the development site.
Monitoring and Administrative Costs
543. A 10-year repayment period would be required whereby any unallocated sums
would be returned to the developer 10 years after practical completion of the
development. Some funds may be set aside for future maintenance purposes.
544. The applicant will pay the City of London’s legal costs and the City Planning
Officer’s administration costs incurred in the negotiation, execution and
monitoring of the legal agreement and strategies.
151
Conclusions
545. The proposal has been assessed in accordance with the relevant statutory
duties and having regard to the Development Plan and other relevant policies
and guidance, SPDs and SPGs and relevant advice including the NPPF, the
draft Local Plan, local finance considerations, and considering all other material
considerations.
546. The application site straddles the City of London and London Borough of
Camden. For that reason, duplicate applications have been submitted to both
local authorities. Through the course of the application the two local authorities
worked together to address the matters raised by internal and external
consultees and public representations and conclude on planning
recommendations.
547. The application is intended to be considered by the Planning Committee of
London Borough of Camden on 11
th
of July 2024 and as such no resolution has
been granted. LB Camden will be determining an identical application which will
assess the considerations relevant to the development located within their
boundaries and against their policies.
548. The proposed development comprises the change of use of the existing deep
level tunnels to a visitor and cultural attraction (Use Class F1 (b) and (c)). The
attraction would offer cultural exhibition areas, to curate the history of Kingsway
Tunnels, used during and after London war times, by restoring and interpreting
their rich history in a historic exhibition space and a flexible gallery space where
modern and innovative content would be shaped by indented partnerships. The
proposal also involves the demolition and reconstruction of 38-39 Furnival
Street and the redevelopment of 40-41 Furnival Street to provide the principal
entrance to the cultural space at the ground level and ancillary spaces at the
upper levels, including a gift shop, staff accommodation and plant rooms to
serve the function of the tunnels. The reconstruction of the site at Furnival
Street would involve excavation for additional basement levels under the two
buildings and widening of the lift shaft at 38-39 Furnival Street for the provision
of the main passenger lifts. A secondary visitor and emergency entrance is
proposed at 31-33 High Holborn via Fulwood Place, located in the London
Borough of Camden. The creation of a deep level bar is proposed at the western
part of the tunnels, in LB Camden, which would be principally accessed via
Fulwood Place and would form an independent unit with its own operational
hours and staff.
549. The application received 57 letters of support from the public that expressed
their strong support for the proposed cultural use and the socio-economic
benefits it would bring to the local and London-wide area. Letters of support
have been received from Central District Alliance and the Fleet Quarter,
identifying the transformative nature of the scheme to an area that very much
152
needs this change. It is not standard for an application in the City to receive so
many letters of support.
550. A total of 24 objections to the scheme have been received from the public
raising concerns over the noise and disturbance caused by construction and
the increased footfall and traffic at operational stage that would impact the
amenity of nearby residential and commercial occupants, the harm to the
conservation area and the design of the new building on Furnival Street, impact
of the proposed delivery and servicing arrangements on local residents and
business, the physical incapacity of Furnival Street to accommodate the
proposed development, and daylight and sunlight impacts to the commercial
building at 10 Furnival Street, opposite of the application site. The areas of
consideration are normally raised by the public when an application involves
construction works near residential properties and a land use with the potential
to increase activity on site.
551. A total of 12 statutory consultees have responded with no objections raised for
the grand permission of the proposed development subject to conditions and
informatives being appended.
552. Whilst there would be a loss of 1,229 sqm office floorspace, building at 40-41
Furnival Street, officers conclude that this is necessary for the delivery of the
proposed scheme which is considered to fall within the ‘exceptional’ category
of complimentary uses, as identified in supporting text in Local Plan Policy
DM1.1, and as such it is acceptable in principle.. The existing offices would be
a poor competitor to other buildings in better locations given they are dated and
not of high-quality in terms of their accommodation and building design. The
scheme delivers 10,341 sqm of high-quality unique cultural use with access
provided at the northwest side of the City. The loss of the modest office has
been weighed against the exceptional re-use of the adjoining heritage asset,
the inherent requirement of 40-41 Furnival Street for access/ancillary space and
the wider economic benefits the cultural use would bring to the City as a whole.
Officers consider that the proposal would not have an adverse impact on the
overall stock of floorspace in the City or prejudice the City’s role as an
international business and professional centre. The cultural space will
contribute towards diversifying the City’s visitor infrastructure, adding vibrancy
and activity for seven days per week and contribute significantly to the
achievement of the City Corporation’s Destination City ambitions and align with
the City Corporation’s wider ambitions for a post-Covid City. The loss of office
floorspace at 40-41 Furnival Street is considered acceptable on that basis.
553. The proposal makes effective use of an existing unused infrastructure and
considers a most interesting way of restoring and reusing them with reference
to their rich history which has been left unknown to date. Officers consider this
to be a respectful way to bring the tunnels back to life and educate people on
153
their use at historic times. The application provisions a large heritage space to
be developed around the site's historic times with interactive ways of exploring
and learning to create stimulating experiences. It is acknowledged that any
other use would not be able to focus on the heritage and historic aspect of the
site as much as the current proposal does. The provision of a flexible exhibition
space adds to the cultural supply in the City and would create opportunities for
special exhibitions to take place to attract more diversified population.
554. The cultural use is supported on the basis of the City’s wider cultural aspirations
and the public benefits of the scheme. Such benefits include engaging with
schools by securing free school visits and training programmes, generating
employment on the site and through supply chains, tourism and spending
between £60m - £85m in the local area each year which would benefit the
economy and revitalisation of the local businesses, maximising opportunities
for local and inclusive procurements. The proposal gives the opportunity to
access and appreciate the interiors of such historically significant infrastructure
and commits to partnerships with universities and tech-institutions and co-
curation and co-creation programmes to curate the cultural spaces with the help
of local communities.
555. The site is located within the Chancery Lane conservation area. The building at
38-39 Furnival Street has been identified as a non-designated heritage asset
due to its connection to the historic Kingsway Tunnels and its rarity value. The
proposed development involves demolition in a conservation and
reconstruction of the primary facade of the No38-39.
556. Paragraph 209 of the NPPF states “The effect of an application on the
significance of a non-designated heritage asset should be taken into account in
determining the application. In weighing applications that directly or indirectly
affect non-designated heritage assets, a balanced judgement will be required
having regard to the scale of any harm or loss and the significance of the
heritage asset.” Paragraph 210 of the NPPF continuous to state that “Local
planning authorities should not permit the loss of the whole or part of a heritage
asset without taking all reasonable steps to ensure the new development will
proceed after the loss has occurred”. It is considered that the demolition of 38-
39 Furnival Street and reconstruction of the brick facade would result in loss of
part of the non-designated heritage asset but on balance this would not diminish
the overall significance of the heritage asset. Officers have taken into account
that the proposed works would improve the accessibility and visibility of this
currently unknown heritage asset to a wide public audience without distracting
from its historical and rarity value in line with London Plan Policy HC1, Local
Plan Policy CS12 and Emerging City Plan 2040 Policy S11. In line with
paragraph 210 of the NPPF, a Cultural Implementation Strategy would be
secured via Section 106, requiring a Cultural Operator to be secured prior to
any demolition works. Officers consider this as a necessary condition to ensure
154
the partial loss of the non-designated heritage asset would occur only when the
operation of the proposed cultural development would be secured.
557. The Greater London Archaeological Advisory Service (GLAAS) have
recommended two-stage pre-commencement archaeological conditions
requiring a Written Scheme of Investigation (WSI) and a Historic Building
Recording to be carried out prior to any demolition works. Subject to conditions
the proposal is acceptable in archaeological terms and accords with Local Plan
Policy DM12.4 and draft City Plan Policy HE2.
558. The architectural approach is to recreate the existing building portions in terms
of massing, height as currently stand at 38-41 Furnival Street. The proposed
facade treatment includes a primary frontage of 40-41 Furnival Street
expressing the new function of the building, while it reimages the existing brick
facade of 38-39 Furnival Street to celebrate the history of the site. The
distinctive sense of separate budlings with different characters would refine a
level of neighbourly architecture while adding a level of visual interest and
character connected to the unique cultural use of the buildings and the
subterrane tunnel network. The development is sensitive to townscape contexts
at macro and local scales. The proposal would optimise the use of land, whilst
significantly improving the buildings’ interface with their surroundings. The
proposals are in overall general conformity with Local Plan Strategic Policies
CS10 (Design), London Plan Policies D3/D8 and emerging City Plan 2040
Strategic Policy S8 (Design).
559. The proposed ground floor layout and design promotes a defined, active base
of human scale expression through increased levels of glazing and interaction
with the ground floor primary use of the cultural use main entrance making a
positive contribution to the street.
560. The proposed cultural use due to its unique experience and capacity would
generate trips towards the site with a high number of visitors travelling to the
area. The site is within the Central Activities Zone and highly sustainable with
very good access to transport infrastructure and able to support active travel.
However, there would be some impact to the pedestrian comfort due to a high
number of future visitors. An appropriate package of S278 works would be
agreed in order to facilitate the development and make the development
acceptable in planning terms. Works would include providing a welcoming
pedestrian environment while coping with the increased footfall in the local
area. Other mitigation measures, conditions and obligations have also been
considered to make the application acceptable such as a future agreement of
an Events Management Plan with highways matters to be agreed on a case-
by-case basis to control servicing, possible queuing, operations, and time
restrictions for deliveries. Vehicle movements would also be increased in the
area. Around eight deliveries are expected to be generated per day by the site.
155
Officers have worked closely with the applicant to identify how and when
deliveries can be facilitated. The main delivery point has been amended over
the course of the application due to the narrowness and the restricted access
of the site on Furnivall Street. The main delivery point would be from Holborn
away from residential properties and will be restricted in line with local traffic
orders and environmental health officer recommendations to protect the
amenity of local residents. Matters relating to cycle parking, car parking, taxi
drop off, and coach parking have been satisfactorily addressed.
561. The proposed buildings have been designed to ensure the site is accessible for
the greatest range of people. Step-free access is secured for the entirety of the
development. Visitors would only be able to access the ground level where the
principal entrance would be located, at 38-41 Furnival Street, the tunnels
exhibition spaces and the first and second levels where provision of a gift shop
would be made. The upper levels up to level four and the roof terrace would
only be accessible to staff. The staff accommodation area has been designed
with accessibility standards and offers end-of trip facilities and accessible
changing facilities and toilets. A public Changing Places facility would be
provided in the tunnels alongside a mix of toilets across general public
accessible areas. Details of the management and operation of the above
spaces would be required under conditions and an Access Management Plan
in the Section 106 agreement. Subject to further design details and an AMP, it
is considered that the proposal accords with the access related policies outlined
above. Overall, and subject to the imposition of conditions, the proposal would
accord with the access policies of the Local and London Plan.
562. It is noted that the majority of the objections have been around noise,
disturbance, impacts to residential amenity and traffic. This report has
considered these impacts, including any requisite mitigation which would be
secured by conditions.
563. The Environmental Health team were consulted and recommended a series of
conditions to control the noise levels generated by the operation of the cultural
use, the plant room at roof level and servicing. Negative impacts during
construction would be controlled as far as possible by the implementation of
Schemes of protective works for demolition and construction and a
Construction Logistics Plan and good site practices embodied therein. It is
recognised that there are inevitable, albeit temporary consequences of
development in a tight-knit urban environment. Post construction, compliance
with planning conditions would minimise any adverse impacts. The use of the
staff rooftop terrace would be restricted outside 8am-8pm to safeguard the
amenity of adjoining occupiers. Therefore it is considered the proposed
development complies with local plan policies regarding impact on amenity.
156
564. Negative impacts during construction would be controlled as far as possible by
the implementation of Schemes of protective works for demolition and
construction and a Construction Logistics Plan and good site practices
embodied therein. It is recognised that there are inevitable, albeit temporary
consequences of development in a tight-knit urban environment. Post
construction, compliance with planning conditions would minimise any adverse
impacts.
565. The safe and secure decontamination of the site has been secured by
conditions for submission of relevant details to the local authority prior to
commencement of works.
566. In terms of daylight sunlight impacts, the proposed buildings would not deviate
significant from the existing massing. The necessary assessment has been
undertaken demonstrate a moderate to hight level of BRE compliance. it is
considered that the impact of the proposed development is considered to be
acceptable with regards nearby dwellings, in accordance with the requirements
of London Plan policy D6, Local Plan Policy DM10.7 and Policy DE7 of the draft
City Plan 2040. Considering the site’s urban context, acceptable living
standards would be maintained.
567. It is important to acknowledge the significant environmental impact associated
with the proposed development. The City of London Climate Action Strategy
supports the delivery of a net zero, climate resilient City. Local Plan policy
dictates that all development is required; to demonstrate the highest feasible
and viable sustainability standards in the design, construction, operation and
“end of life” phases of development; to minimise emissions and contribute to a
City-wide reduction in emissions: to incorporate climate change adaption
measures and urban greening, and to promote biodiversity and overall
wellbeing. Development should also avoid demolition and reduce construction
emissions through the reuse of existing buildings and by following principles of
the circular economy.
568. The London Tunnels proposal offers a unique visitors attraction which would
bring an under-utilised piece of historic infrastructure into public use, whilst
retaining 90% (by area) of the existing buildings and structures, including the
entire tunnel network bringing with it public and environmental benefits.
569. Demolition of both buildings on Furnival Street is deemed acceptable, justified
by the practical constraints of the construction process, the requirements for
achieving greater access to the Tunnel network (for visitors and equipment) as
well as the improved servicing efficiencies which can achieved through the
size/layout of a new build.
157
570. The change of use of deep level tunnels, designed for emergency shelter and
secure telecommunication, to a cultural exhibition and event space offering the
potential for immersive audio-visual experiences is technically challenging and
requires an extensive amount of building services equipment to accommodate
the high visitor numbers targeted/anticipated, and to meet high cooling loads
particularly associated with audio-visual equipment.
571. The building operations and maintenance and replacement works over the
building’s lifespan (primarily attributed to servicing equipment) have a high
carbon intensity (emissions rate per m2). Embodied emissions associated with
MEP equipment alone are estimated to be 40% of WLC embodied emissions
with a further 40% of WLC emissions attributed to operational energy use. A
highly efficient cooling system with heat recovery has been designed to manage
over-heating within the tunnel network but the amount of waste heat expelled
to the atmosphere remains significant without a connection to a local area
network or neighbouring site, neither of which are currently proposed.
572. The total quantity of audio-visual equipment has a very significant impact on
overall energy use and cooling demand which in turn affect both operational
and embodied carbon emissions (due to the increase in quantity of cooling
equipment). Therefore, the special exhibitions and events component of the
proposal (and the type and frequency thereof) has a significant impact on the
sustainability of the development. The impact could be reduced through a
responsible Cultural Implementation Strategy and Management Plan.
573. The proposed development offers an increase in urban greening and
biodiversity, and an improved surface water run-off rate. Although these
contributions are relatively small, they are acceptable in policy terms due to the
limited area of the site which sits above ground.
574. The development proposal is currently targeting a BREEAM rating of ‘Very
Good’ which falls short of the City’s policy requirement of ‘Excellent.’ The pre-
assessment demonstrated good potential to achieve an Excellent rating. Given
this assessment and the wider environmental impact, the development is
therefore expected to make best efforts to achieve a minimum rating of
‘Excellent’. A condition has been recommended to secure requirements are
met.
575. In terms of fire safety, the proposal integrates a series of measures to control
fire and keep people in safety until they egress. A fire evacuation strategy and
fire-fighters emergency access and fire elimination equipment would be
strategically implemented on site. City’s District Surveyor has reviewed the
submitted Fire Statement and raised no objections. Whilst London Fire Brigade
raised questions about how the detailed design of the scheme would be able to
158
satisfy some of their concerns, it is considered that the exact design and
methodologies would be only available post planning and during the Qualitative
Design Review (QDR) process. The applicant has committed to consult LFB as
a key stakeholder at that stage. An informative has been recommended as a
reminder.
576. Therefore overall, it is considered that the proposed cultural use would not
prejudice the primary business function of the City; it would contribute to the
City’s aspirations for evening and weekend economy; it would generate local
spend between £60m - £85m each year and create new jobs; promote balance
and mix of uses in the immediate locality; and would not result in unacceptable
adverse impacts on the amenity of neighbouring properties.
577. The proposals are considered to be in accordance with the development plan
when taken as whole.
578. The Local Planning Authority must determine the application in accordance with
the development plan unless other material considerations indicate otherwise.
579. It is the view of officers that as the proposal complies with the Development
Plan when considered as a whole and as other material considerations also
weigh in favour of the scheme, planning permission should be granted as set
out in the recommendation and the schedules attached.
159
Appendix A - Background Papers
List if Application Documents:
Application Covering Letter (30/11/2023)
Application Form & Certificates (30/11/2023)
Community Infrastructure Levy Form (18/12/2023)
Site Location Plan 2 (Below Ground & Tunnels Complex) (30/11/2023)
Site Location Plan 3 (Site Boundaries) (15/12/2023)
Site Plan (30/11/2023)
Design and Access Statement (30/11/2023)
Accessibility Assessment (30/11/2023)
Planning Statement (30/11/2023)
Heritage Statement (30/11/2023)
Archaeological Desk Based Assessment (30/11/2023)
Cultural Plan (30/11/2023)
Statement of Community Involvement (30/11/2023)
Socio-Economic Assessment (30/11/2023)
Sunlight & Daylight Assessment (30/11/2023)
Air Quality Assessment (30/11/2023)
BREEAM Pre-Assessment Report (30/11/2023)
Circular Economy Statement (30/11/2023)
Construction Traffic Management Plan (30/11/2023)
Delivery & Servicing Plan (17/05/2024)
Energy Statement & Overheating Assessment (30/11/2023)
Fire Statement (30/11/2023)
Flood Risk Assessment & Outline Drainage Strategy (30/11/2023)
Framework Travel Plan (17/05/2024)
Geotech Basement Impact Assessment (30/11/2023)
Noise and Vibration Impact Assessment (30/11/2023)
Pre-demolition Audit (30/11/2023)
160
Security Report (30/11/2023)
Structural Report (30/11/2023)
Sustainability Statement (30/11/2023)
Transport Assessment (17/05/2024)
Waste Management Plan (05/05/2024)
Whole Life-Cycle Carbon Assessment (30/11/2023)
Health Impact Assessment (18/12/2023)
Adaptation to Climate Change Report (13/03/2024)
Loss of Office Policy Note (11/04/2024)
Lighting Strategy Report (12/04/2024)
Equality Impact Assessment (03/05/2024)
Flood Risk Evacuation Strategy (15/05/2024)
Supplementary Air Quality Response (06/03/24)
Daylight Sunlight Response 1 (05/03/2024)
Daylight Sunlight Response 2 (26/03/24)
WSP responses to Sustainability queries (22/04/24, 02/05/24 and 13/05/2024)
Cultural Plan responses, Email (14/05/2024)
Fire Statement Response to LFB letter (14/05/24)
Design Supplementary Clarification 01 Furnival Street (17/05/2024)
Design Supplementary Clarification 02 Accessibility (17/05/2024)
Design Supplementary Clarification 03 39 Furnival Street Fabric Retention
(17/05/2024).
3
rd
party reviews
3rd Party Review of Whole Life Carbon Assessment Report by Civic Engineers
(14/03/24)
Internal Consultee Responses
Memo, 29/12/23, Environmental Health Officer
Memo, 24/01/24, District Surveyors Office
161
Memo, 24/01/24, Lead Local Flood Authority
Memo, 23/02/24, Environmental Resilience Officer
Email, 18/04/24, Cleansing Team
Memo, 11/03/24, Air Quality Officer
Email, 16/05/24, City of London Police
Email, 17/05/24, COL Police - Counter Terrorism
Email, 22/05/24, Environmental Resilience Officer
Representations
Support
29/01/24, Mr Colin Matthews, Online
29/01/24, Mr Philip Nash, Online
29/01/24, Ms Susan Smith, Online
31/01/24, Mrs Robyn Brook, Online
31/01/24, Mr James Loxton, Online
01/02/24, Mr KENNETH GOLBY, Online
01/02/24, Mr George Harris, Online
01/02/24, Mr Max Tobias, Online
01/02/24, Mr peter conniff, Online
02/02/24, Mr William Morris, Online
06/02/24, Mr Stuart Perl, Online
14/02/24, Mr Andrew Raca, Online
18/02/24, Mr Andrew Raca, Online
20/02/24, Ms Wendy Lyons, Online
20/02/24, Mr Charles Parry, Online
20/02/24, Mr Charles Parry, Online
20/02/24, Miss Chelsea Cooper, Online
20/02/24, Mr Thomas Seabourne, Online
23/02/24, Miss Angela Dunning , Online
162
26/02/24, Mrs Sue Macdiarmid, Online
26/02/24, Mr Graham Wingham, Online
26/02/24, Ms Angela Epps, Online
26/02/24, Ms Caroline Gallagher , Online
27/02/24, Mr Neil Emberson, Online
27/02/24, Mr DEREK OWEN, Online
27/02/24, Mr Patrick Ralph, Online
27/02/24, Mrs Sandra Murphy, Online
27/02/24, Dr GABRIEL GOLDMAN, Online
27/02/24, Mr PAUL SCOTT, Online
27/02/24, Mr Jp Ralph, Online
27/02/24, Mr Stephen Luderman, Online
27/02/24, Justin Manley-Cooper, Online
27/02/24, Nick Finegold, Online
28/02/24, Mr Adam Fayed, Online
28/02/24, Mr Gregory Jones KC, Online
28/02/24, Mr David Brown, Online
28/02/24, Alex Hayes-Griffin, Online
28/02/24, Mr chris sullivan, Online
28/02/24, Mr Daniel van Vuuren, Online
28/02/24, Mr Luis Esguevillas, Online
28/02/24, Mr win man, Online
29/02/24, Mr David EH Yeoh, Online
29/02/24, Mr Guy Brook, Online
29/02/24, Miss Heidi Bryant, Online
29/02/24, Ms Helen McDowell, Online
01/03/24, Mr Michael Brown, Online
01/03/24, Dr Geoff Ferreira, Online
06/03/24, Mr Adam Pollock, Online
163
14/03/24, Mr Lawrence Yew, Online
14/03/24, Mr Maggie Lai, Online
14/03/24, Dr Lai Meng Looi, Online
17/03/24, Mr Alistair Sommerlad, Online
11/04/24, Ms Maria Nieves Garcia Somoza, Online
02/05/24, Mr James Hacking, Online
21/05/24, Central District Alliance
23/05/24, Fleet Street Quarter
Objections
27/12/23, Mrs G Birri, Email, Objection
28/12/23, Ms Lidia Zazzera, Online
30/12/23, Lord John Krebs, Online
03/01/24, Leyi Wang, Email
04/01/24, Mrs Nina Keay, Online
04/01/24, Lisa Zazzera, Email
08/01/24, Walter Scott, Email
08/01/24, Mr James Keay, Online
08/01/24, Mr Brian Cotsen, Online
08/01/24, Brian Cotsen, Email
09/01/24, LEYI WANG, Online
09/01/24, Liz Speirs, Email,
10/01/24, Miss Meihan Dong, Online
10/01/24, Chloe Nash, Email
11/01/24, C Murphy, Online
11/01/24, Anonymous, Email
13/01/24, Mr Jack Watkins , Online
14/01/24, Professor Susan V. Scott, Email
30/01/24, Furnival Management Limited, Email
04/02/24, Miss Lisa Dickenson, Online
164
16/02/24 - 16:44, Chancery Exchange, Email
20/04/24, Mr & Mrs Birri, Email
27/04/24, Furnival Management Limited, Email
13/05/24, Coralie Murphy, Online
Neutral
29/01/24 - 15:15, Mr Oscar Li, Online
23/03/24 - 15:39, Mr Stephan Fels, Online
24/04/24 - 12:47, Mr Andrew Green, Online
External consultees
02/01/24, Historic England
04/01/24, Historic England (GLAAS)
09/01/24, Transport For London (Infrastructure Protection)
24/01/24, Westminster City Council
29/02/24, Thames Water
07/03/24, Conservation Area Advisory Committee (CAAC)
13/03/24, Environment Agency
19/04/24, Transport For London (Spatial Planning)
22/04/24, London Fire Brigade
165
Appendix B
Relevant Local Plan Policies
CS1 Provide additional offices
To ensure the City of London provides additional office development of the highest
quality to meet demand from long term employment growth and strengthen the
beneficial cluster of activities found in and near the City that contribute to London's
role as the world's leading international financial and business centre.
CS2 Facilitate utilities infrastructure
To co-ordinate and facilitate infrastructure planning and delivery to ensure that the
functioning and growth of the City's business, resident, student and visitor
communities is not limited by provision of utilities and telecommunications
infrastructure.
CS3 Ensure security from crime/terrorism
To ensure that the City is secure from crime, disorder and terrorism, has safety
systems of transport and is designed and managed to satisfactorily accommodate
large numbers of people, thereby increasing public and corporate confidence in the
City's role as the world's leading international financial and business centre.
CS4 Seek planning contributions
To manage the impact of development, seeking appropriate developer contributions.
CS10 Promote high quality environment
To promote a high standard and sustainable design of buildings, streets and spaces,
having regard to their surroundings and the character of the City and creating an
inclusive and attractive environment.
CS11 Encourage art, heritage and culture
To maintain and enhance the City's contribution to London's world-class cultural status
and to enable the City's communities to access a range of arts, heritage and cultural
experiences, in accordance with the City Corporation's Destination Strategy.
CS12 Conserve or enhance heritage assets
To conserve or enhance the significance of the City's heritage assets and their
settings, and provide an attractive environment for the City's communities and visitors.
CS13 Protect/enhance significant views
166
To protect and enhance significant City and London views of important buildings,
townscape and skylines, making a substantial contribution to protecting the overall
heritage of the City's landmarks.
CS14 Tall buildings in suitable places
To allow tall buildings of world class architecture and sustainable design in suitable
locations and to ensure that they take full account of the character of their
surroundings, enhance the skyline and provide a high quality public realm at ground
level.
CS15 Creation of sustainable development
To enable City businesses and residents to make sustainable choices in their daily
activities creating a more sustainable City, adapted to the changing climate.
CS16 Improving transport and travel
To build on the City's strategic central London position and good transport
infrastructure to further improve the sustainability and efficiency of travel in, to, from
and through the City.
CS17 Minimising and managing waste
To support City businesses, residents and visitors in making sustainable choices
regarding the minimisation, transport and management of their waste, capitalising on
the City's riverside location for sustainable waste transfer and eliminating reliance on
landfill for municipal solid waste (MSW).
CS18 Minimise flood risk
To ensure that the City remains at low risk from all types of flooding.
CS19 Improve open space and biodiversity
To encourage healthy lifestyles for all the City's communities through improved access
to open space and facilities, increasing the amount and quality of open spaces and
green infrastructure, while enhancing biodiversity.
CS20 Improve retail facilities
To improve the quantity and quality of retailing and the retail environment, promoting
the development of the five Principal Shopping Centres and the linkages between
them.
CS21 Protect and provide housing
To protect existing housing and amenity and provide additional housing in the City,
concentrated in or near identified residential areas, as shown in Figure X, to meet the
City's needs, securing suitable, accessible and affordable housing and supported
housing.
167
CS22 Maximise community facilities
To maximise opportunities for the City's residential and working communities to
access suitable health, social and educational facilities and opportunities, while
fostering cohesive communities and healthy lifestyles.
DM1.1 Protection of office accommodation
To refuse the loss of existing (B1) office accommodation to other uses where the
building or its site is considered to be suitable for long-term viable office use and there
are strong economic reasons why the loss would be inappropriate. Losses would be
inappropriate for any of the following reasons: prejudicing the primary business
function of the City;
jeopardising the future assembly and delivery of large office development sites;
removing existing stock for which there is demand in the office market or long
term viable need;
introducing uses that adversely affect the existing beneficial mix of commercial
uses.
DM1.3 Small and medium business units
To promote small and medium sized businesses in the City by encouraging:
a) new accommodation suitable for small and medium sized businesses or
occupiers;
b) office designs which are flexible and adaptable to allow for sub-division to create
small and medium sized business units;
c) continued use of existing small and medium sized units which meet occupier
needs.
DM1.5 Mixed uses in commercial areas
To encourage a mix of commercial uses within office developments which contribute
to the City's economy and character and provide support services for its businesses,
workers and residents.
DM2.1 Infrastructure provision
1) Developers will be required to demonstrate, in conjunction with utility providers,
that there will be adequate utility infrastructure capacity, both on and off the site, to
serve the development during construction and operation. Development should not
lead to capacity or reliability problems in the surrounding area. Capacity projections
must take account of climate change impacts which may influence future infrastructure
demand.
2) Utility infrastructure and connections must be designed into and integrated with the
development wherever possible. As a minimum, developers should identify and plan
for:
168
a) electricity supply to serve the construction phase and the intended use for the
site, and identify, in conjunction with electricity providers, Temporary Building
Supply(TBS) for the construction phase and the estimated load capacity of the
building and the substations and routes for supply;
b) reasonable gas and water supply considering the need to conserve natural
resources;
c) heating and cooling demand and the viability of its provision via decentralised
energy (DE) networks. Designs must incorporate access to existing DE networks
where feasible and viable;
d) telecommunications network demand, including wired and wireless
infrastructure, planning for dual entry provision, where possible, through communal
entry chambers and flexibility to address future technological improvements;
e) separate surface water and foul drainage requirements within the proposed
building or site, including provision of Sustainable Drainage Systems (SuDS),
rainwater harvesting and grey-water recycling, minimising discharge to the
combined sewer network.
3) In planning for utility infrastructure developers and utility providers must provide
entry and connection points within the development which relate to the City's
established utility infrastructure networks, utilising pipe subway routes wherever
feasible. Sharing of routes with other nearby developments and the provision of new
pipe subway facilities adjacent to buildings will be encouraged.
4) Infrastructure provision must be completed prior to occupation of the development.
Where potential capacity problems are identified and no improvements are
programmed by the utility company, the City Corporation will require the developer to
facilitate appropriate improvements, which may require the provision of space within
new developments for on-site infrastructure or off-site infrastructure upgrades.
DM3.2 Security measures
To ensure that security measures are included in new developments, applied to
existing buildings and their curtilage, by requiring:
a) building-related security measures, including those related to the servicing of the
building, to be located within the development's boundaries;
b) measures to be integrated with those of adjacent buildings and the public realm;
c) that security is considered at the concept design or early developed design
phases of all development proposals to avoid the need to retro-fit measures that
impact on the public realm;
169
d) developers to seek recommendations from the City of London Police
Architectural Liaison Officer at the design stage. New development should meet
Secured by Design principles;
e) the provision of service management plans for all large development,
demonstrating that vehicles seeking access to the building can do so without
waiting on the public highway;
f) an assessment of the environmental impact of security measures, particularly
addressing visual impact and impact on pedestrian flows.
DM3.3 Crowded places
On all major developments, applicants will be required to satisfy principles and
standards that address the issues of crowded places and counter-terrorism, by:
a) conducting a full risk assessment;
b) keeping access points to the development to a minimum;
c) ensuring that public realm and pedestrian permeability associated with a building
or site is not adversely impacted, and that design considers the application of
Hostile Vehicle Mitigation measures at an early stage;
d) ensuring early consultation with the City of London Police on risk mitigation
measures;
e) providing necessary measures that relate to the appropriate level of crowding in
a site, place or wider area.
DM3.4 Traffic management
To require developers to reach agreement with the City Corporation and TfL on the
design and implementation of traffic management and highways security measures,
including addressing the management of service vehicles, by:
a) consulting the City Corporation on all matters relating to servicing;
b) restricting motor vehicle access, where required;
c) implementing public realm enhancement and pedestrianisation schemes, where
appropriate;
d) using traffic calming, where feasible, to limit the opportunity for hostile vehicle
approach.
DM3.5 Night-time entertainment
1) Proposals for new night-time entertainment and related uses and the extension of
existing premises will only be permitted where it can be demonstrated that, either
individually or cumulatively, there is no unacceptable impact on:
170
a) the amenity of residents and other noise-sensitive uses;
b) environmental amenity, taking account of the potential for noise, disturbance
and odours arising from the operation of the premises, customers arriving at and
leaving the premises and the servicing of the premises.
2) Applicants will be required to submit Management Statements detailing how these
issues will be addressed during the operation of the premises.
DM10.1 New development
To require all developments, including alterations and extensions to existing buildings,
to be of a high standard of design and to avoid harm to the townscape and public
realm, by ensuring that:
a) the bulk and massing of schemes are appropriate in relation to their
surroundings and have due regard to the general scale, height, building lines,
character, historic interest and significance, urban grain and materials of the
locality and relate well to the character of streets, squares, lanes, alleys and
passageways;
b) all development is of a high standard of design and architectural detail with
elevations that have an appropriate depth and quality of modelling;
c) appropriate, high quality and durable materials are used;
d) the design and materials avoid unacceptable wind impacts at street level or
intrusive solar glare impacts on the surrounding townscape and public realm;
e) development has attractive and visually interesting street level elevations,
providing active frontages wherever possible to maintain or enhance the vitality of
the City's streets;
f) the design of the roof is visually integrated into the overall design of the building
when seen from both street level views and higher level viewpoints;
g) plant and building services equipment are fully screened from view and
integrated in to the design of the building. Installations that would adversely affect
the character, appearance or amenities of the buildings or area will be resisted;
h) servicing entrances are designed to minimise their effects on the appearance of
the building and street scene and are fully integrated into the building's design;
i) there is provision of appropriate hard and soft landscaping, including appropriate
boundary treatments;
j) the external illumination of buildings is carefully designed to ensure visual
sensitivity, minimal energy use and light pollution, and the discreet integration of
light fittings into the building design;
k) there is provision of amenity space, where appropriate;
171
l) there is the highest standard of accessible and inclusive design.
DM10.2 Design of green roofs and walls
1) To encourage the installation of green roofs on all appropriate developments. On
each building the maximum practicable coverage of green roof should be achieved.
Extensive green roofs are preferred and their design should aim to maximise the roof's
environmental benefits, including biodiversity, run-off attenuation and building
insulation.
2) To encourage the installation of green walls in appropriate locations, and to ensure
that they are satisfactorily maintained.
DM10.3 Roof gardens and terraces
1) To encourage high quality roof gardens and terraces where they do not:
a) immediately overlook residential premises;
b) adversely affect rooflines or roof profiles;
c) result in the loss of historic or locally distinctive roof forms, features or coverings;
d) impact on identified views.
2) Public access will be sought where feasible in new development.
DM10.4 Environmental enhancement
The City Corporation will work in partnership with developers, Transport for London
and other organisations to design and implement schemes for the enhancement of
highways, the public realm and other spaces. Enhancement schemes should be of a
high standard of design, sustainability, surface treatment and landscaping, having
regard to:
a) the predominant use of the space, surrounding buildings and adjacent spaces;
b) connections between spaces and the provision of pleasant walking routes;
c) the use of natural materials, avoiding an excessive range and harmonising with
the surroundings of the scheme and materials used throughout the City;
d) the inclusion of trees and soft landscaping and the promotion of biodiversity,
where feasible linking up existing green spaces and routes to provide green
corridors;
e) the City's heritage, retaining and identifying features that contribute positively to
the character and appearance of the City;
f) sustainable drainage, where feasible, co-ordinating the design with adjacent
buildings in order to implement rainwater recycling;
172
g) the need to provide accessible and inclusive design, ensuring that streets and
walkways remain uncluttered;
h) the need for pedestrian priority and enhanced permeability, minimising the
conflict between pedestrians and cyclists;
i) the need to resist the loss of routes and spaces that enhance the City's function,
character and historic interest;
j) the use of high quality street furniture to enhance and delineate the public realm;
k) lighting which should be sensitively co-ordinated with the design of the scheme.
DM10.7 Daylight and sunlight
1) To resist development which would reduce noticeably the daylight and sunlight
available to nearby dwellings and open spaces to unacceptable levels, taking account
of the Building Research Establishment's guidelines.
2) The design of new developments should allow for the lighting needs of intended
occupiers and provide acceptable levels of daylight and sunlight.
DM10.8 Access and inclusive design
To achieve an environment that meets the highest standards of accessibility and
inclusive design in all developments (both new and refurbished), open spaces and
streets, ensuring that the City of London is:
a) inclusive and safe for of all who wish to use it, regardless of disability, age,
gender, ethnicity, faith or economic circumstance;
b) convenient and welcoming with no disabling barriers, ensuring that everyone
can experience independence without undue effort, separation or special
treatment;
c) responsive to the needs of all users who visit, work or live in the City, whilst
recognising that one solution might not work for all.
DM11.1 Protection of Visitor, Arts and Cultural Facilities
1) To resist the loss of existing visitor, arts and cultural facilities unless:
a) replacement facilities are provided on-site or within the vicinity which meet the
needs of the City's communities; or
b) they can be delivered from other facilities without leading to or increasing any
shortfall in provision, and it has been demonstrated that there is no demand for
another similar use on the site; or
c) it has been demonstrated that there is no realistic prospect of the premises being
used for a similar purpose in the foreseeable future.
173
2) Proposals resulting in the loss of visitor, arts and cultural facilities must be
accompanied by evidence of the lack of need for those facilities. Loss of facilities will
only be permitted where it has been demonstrated that the existing floorspace has
been actively marketed as a visitor, arts or cultural facility at reasonable terms.
DM11.2 Public Art
To enhance the City's public realm and distinctive identity by:
a) protecting existing works of art and other objects of cultural significance and
encouraging the provision of additional works in appropriate locations;
b) ensuring that financial provision is made for the future maintenance of new
public art;
c) requiring the appropriate reinstatement or re-siting of art works and other objects
of cultural significance when buildings are redeveloped.
DM12.1 Change affecting heritage assets
1. To sustain and enhance heritage assets, their settings and significance.
2. Development proposals, including proposals for telecommunications infrastructure,
that have an effect upon heritage assets, including their settings, should be
accompanied by supporting information to assess and evaluate the significance of
heritage assets and the degree of impact caused by the development.
3. The loss of routes and spaces that contribute to the character and historic interest
of the City will be resisted.
4. Development will be required to respect the significance, character, scale and
amenities of surrounding heritage assets and spaces and their settings.
5. Proposals for sustainable development, including the incorporation of climate
change adaptation measures, must be sensitive to heritage assets.
DM12.2 Development in conservation areas
1. Development in conservation areas will only be permitted if it preserves and
enhances the character or appearance of the conservation area.
2. The loss of heritage assets that make a positive contribution to the character or
appearance of a conservation area will be resisted.
3. Where permission is granted for the demolition of a building in a conservation area,
conditions will be imposed preventing demolition commencing prior to the approval of
detailed plans of any replacement building, and ensuring that the developer has
secured the implementation of the construction of the replacement building.
DM12.3 Listed buildings
1. To resist the demolition of listed buildings.
174
2. To grant consent for the alteration or change of use of a listed building only where
this would not detract from its special architectural or historic interest, character and
significance or its setting.
DM12.4 Archaeology
1. To require planning applications which involve excavation or ground works on sites
of archaeological potential to be accompanied by an archaeological assessment and
evaluation of the site, including the impact of the proposed development.
2. To preserve, protect, safeguard and enhance archaeological monuments, remains
and their settings in development, and to seek a public display and interpretation,
where appropriate.
3. To require proper investigation and recording of archaeological remains as an
integral part of a development programme, and publication and archiving of results to
advance understanding.
DM15.1 Sustainability requirements
1. Sustainability Statements must be submitted with all planning applications in order
to ensure that sustainability is integrated into designs for all development.
2. For major development (including new development and refurbishment) the
Sustainability Statement should include as a minimum:
a) BREEAM or Code for Sustainable Homes pre-assessment;
b) an energy statement in line with London Plan requirements;
c) demonstration of climate change resilience measures.
3. BREEAM or Code for Sustainable Homes assessments should demonstrate
sustainability in aspects which are of particular significance in the City's high density
urban environment. Developers should aim to achieve the maximum possible credits
to address the City's priorities.
4. Innovative sustainability solutions will be encouraged to ensure that the City's
buildings remain at the forefront of sustainable building design. Details should be
included in the Sustainability Statement.
5. Planning conditions will be used to ensure that Local Plan assessment targets are
met.
DM15.2 Energy and CO2 emissions
1. Development design must take account of location, building orientation, internal
layouts and landscaping to reduce likely energy consumption.
2. For all major development energy assessments must be submitted with the
application demonstrating:
175
a) energy efficiency - showing the maximum improvement over current Building
Regulations to achieve the required Fabric Energy Efficiency Standards;
b) carbon compliance levels required to meet national targets for zero carbon
development using low and zero carbon technologies, where feasible;
c) where on-site carbon emission reduction is unviable, offsetting of residual CO2
emissions through "allowable solutions" for the lifetime of the building to achieve
national targets for zero-carbon homes and non-domestic buildings. Achievement
of zero carbon buildings in advance of national target dates will be encouraged;
d) anticipated residual power loads and routes for supply.
DM15.3 Low and zero carbon technologies
1. For development with a peak heat demand of 100 kilowatts or more developers
should investigate the feasibility and viability of connecting to existing decentralised
energy networks. This should include investigation of the potential for extensions of
existing heating and cooling networks to serve the development and development of
new networks where existing networks are not available. Connection routes should be
designed into the development where feasible and connection infrastructure should
be incorporated wherever it is viable.
2. Where connection to offsite decentralised energy networks is not feasible,
installation of on-site CCHP and the potential to create new localised decentralised
energy infrastructure through the export of excess heat must be considered
3. Where connection is not feasible or viable, all development with a peak heat
demand of 100 kilowatts or more should be designed to enable connection to potential
future decentralised energy networks.
4. Other low and zero carbon technologies must be evaluated. Non combustion based
technologies should be prioritised in order to avoid adverse impacts on air quality.
DM15.4 Offsetting carbon emissions
1. All feasible and viable on-site or near-site options for carbon emission reduction
must be applied before consideration of offsetting. Any remaining carbon emissions
calculated for the lifetime of the building that cannot be mitigated on-site will need to
be offset using "allowable solutions".
2. Where carbon targets cannot be met on-site the City Corporation will require carbon
abatement elsewhere or a financial contribution, negotiated through a S106 planning
obligation to be made to an approved carbon offsetting scheme.
3. Offsetting may also be applied to other resources including water resources and
rainwater run-off to meet sustainability targets off-site where on-site compliance is not
feasible.
DM15.5 Climate change resilience
176
1. Developers will be required to demonstrate through Sustainability Statements that
all major developments are resilient to the predicted climate conditions during the
building's lifetime.
2. Building designs should minimise any contribution to the urban heat island effect
caused by heat retention and waste heat expulsion in the built environment.
DM15.6 Air quality
1. Developers will be required to consider the impact of their proposals on air quality
and, where appropriate, provide an Air Quality Impact Assessment.
2. Development that would result in deterioration of the City's nitrogen dioxide or
PM10 pollution levels will be resisted.
3. Major developments will be required to maximise credits for the pollution section of
the BREEAM or Code for Sustainable Homes assessment relating to on-site
emissions of oxides of nitrogen (NOx).
4. Developers will be encouraged to install non-combustion low and zero carbon
energy technology. A detailed air quality impact assessment will be required for
combustion based low and zero carbon technologies, such as CHP plant and biomass
or biofuel boilers, and necessary mitigation must be approved by the City Corporation.
5. Construction and deconstruction and the transport of construction materials and
waste must be carried out in such a way as to minimise air quality impacts.
6. Air intake points should be located away from existing and potential pollution
sources (e.g. busy roads and combustion flues). All combustion flues should terminate
above the roof height of the tallest building in the development in order to ensure
maximum dispersion of pollutants.
DM15.7 Noise and light pollution
1. Developers will be required to consider the impact of their developments on the
noise environment and where appropriate provide a noise assessment. The layout,
orientation, design and use of buildings should ensure that operational noise does not
adversely affect neighbours, particularly noise-sensitive land uses such as housing,
hospitals, schools and quiet open spaces.
2. Any potential noise conflict between existing activities and new development should
be minimised. Where the avoidance of noise conflicts is impractical, mitigation
measures such as noise attenuation and restrictions on operating hours will be
implemented through appropriate planning conditions.
3. Noise and vibration from deconstruction and construction activities must be
minimised and mitigation measures put in place to limit noise disturbance in the vicinity
of the development.
177
4. Developers will be required to demonstrate that there will be no increase in
background noise levels associated with new plant and equipment.
5. Internal and external lighting should be designed to reduce energy consumption,
avoid spillage of light beyond where it is needed and protect the amenity of light-
sensitive uses such as housing, hospitals and areas of importance for nature
conservation.
DM15.8 Contaminated land and water quality
Where development involves ground works or the creation of open spaces, developers
will be expected to carry out a detailed site investigation to establish whether the site
is contaminated and to determine the potential for pollution of the water environment
or harm to human health and non-human receptors. Suitable mitigation must be
identified to remediate any contaminated land and prevent potential adverse impacts
of the development on human and non-human receptors, land or water quality.
DM16.1 Transport impacts of development
1. Development proposals that are likely to have effects on transport must be
accompanied by an assessment of the transport implications during both construction
and operation, in particular addressing impacts on:
a) road dangers;
b) pedestrian environment and movement;
c) cycling infrastructure provision;
d) public transport;
e) the street network.
2. Transport Assessments and Travel Plans should be used to demonstrate
adherence to the City Corporation's transportation standards.
DM16.2 Pedestrian movement
1. Pedestrian movement must be facilitated by provision of suitable pedestrian routes
through and around new developments, by maintaining pedestrian routes at ground
level, and the upper level walkway network around the Barbican and London Wall.
2. The loss of a pedestrian route will normally only be permitted where an alternative
public pedestrian route of at least an equivalent standard is provided having regard
to:
a) the extent to which the route provides for current and all reasonably foreseeable
future demands placed upon it, including at peak periods;
b) the shortest practicable routes between relevant points.
178
3. Routes of historic importance should be safeguarded as part of the City's
characteristic pattern of lanes, alleys and courts, including the route's historic
alignment and width.
4. The replacement of a route over which pedestrians have rights, with one to which
the public have access only with permission will not normally be acceptable.
5. Public access across private land will be encouraged where it enhances the
connectivity, legibility and capacity of the City's street network. Spaces should be
designed so that signage is not necessary and it is clear to the public that access is
allowed.
6. The creation of new pedestrian rights of way will be encouraged where this would
improve movement and contribute to the character of an area, taking into
consideration pedestrian routes and movement in neighbouring areas and boroughs,
where relevant.
DM16.3 Cycle parking
1. On-site cycle parking must be provided in accordance with the local standards set
out in Table 16.2 or, for other land uses, with the standards of the London Plan.
Applicants will be encouraged to exceed the standards set out in Table 16.2.
2. On-street cycle parking in suitable locations will be encouraged to meet the needs
of cyclists.
DM16.4 Encouraging active travel
1. Ancillary facilities must be provided within new and refurbished buildings to support
active transport modes such as walking, cycling and running. All commercial
development should make sufficient provision for showers, changing areas and
lockers/storage to cater for employees wishing to engage in active travel.
2. Where facilities are to be shared with a number of activities they should be
conveniently located to serve all proposed activities.
DM16.5 Parking and servicing standards
1. Developments in the City should be car-free except for designated Blue Badge
spaces. Where other car parking is exceptionally provided it must not exceed London
Plan's standards.
2. Designated parking must be provided for Blue Badge holders within developments
in conformity with London Plan requirements and must be marked out and reserved
at all times for their use. Disabled parking spaces must be at least 2.4m wide and at
least 4.8m long and with reserved areas at least 1.2m wide, marked out between the
parking spaces and at the rear of the parking spaces.
3. Except for dwelling houses (use class C3), whenever any car parking spaces (other
than designated Blue Badge parking) are provided, motor cycle parking must be
179
provided at a ratio of 10 motor cycle parking spaces per 1 car parking space. At least
50% of motor cycle parking spaces must be at least 2.3m long and at least 0.9m
wide and all motor cycle parking spaces must be at least 2.0m long and at least 0.8m
wide.
4. On site servicing areas should be provided to allow all goods and refuse collection
vehicles likely to service the development at the same time to be conveniently loaded
and unloaded. Such servicing areas should provide sufficient space or facilities for all
vehicles to enter and exit the site in a forward gear. Headroom of at least 5m where
skips are to be lifted and 4.75m for all other vehicle circulation areas should be
provided.
5. Coach parking facilities for hotels (use class C1) will not be permitted.
6. All off-street car parking spaces and servicing areas must be equipped with the
facility to conveniently recharge electric vehicles.
7. Taxi ranks are encouraged at key locations, such as stations, hotels and shopping
centres. The provision of taxi ranks should be designed to occupy the minimum
practicable space, using a combined entry and exit point to avoid obstruction to other
transport modes.
DM17.1 Provision for waste
1. Waste facilities must be integrated into the design of buildings, wherever feasible,
and allow for the separate storage and collection of recyclable materials, including
compostable material.
2. On-site waste management, through techniques such as recyclate sorting or
energy recovery, which minimises the need for waste transfer, should be incorporated
wherever possible.
DM17.2 Designing out construction waste
New development should be designed to minimise the impact of deconstruction and
construction waste on the environment through:
a) reuse of existing structures;
b) building design which minimises wastage and makes use of recycled materials;
c) recycling of deconstruction waste for reuse on site where feasible;
d) transport of waste and construction materials by rail or river wherever
practicable;
e) application of current best practice with regard to air quality, dust, hazardous
waste, waste handling and waste management .
DM18.1 Development in Flood Risk Area
180
1. Where development is proposed within the City Flood Risk Area evidence must be
presented to demonstrate that:
a) the site is suitable for the intended use (see table 18.1), in accordance with
Environment Agency and Lead Local Flood Authority advice;
b) the benefits of the development outweigh the flood risk to future occupants;
c) the development will be safe for occupants and visitors and will not compromise
the safety of other premises or increase the risk of flooding elsewhere.
2. Development proposals, including change of use, must be accompanied by a site-
specific flood risk assessment for:
a) all sites within the City Flood Risk Area as shown on the Policies Map; and
b) all major development elsewhere in the City.
3. Site specific flood risk assessments must address the risk of flooding from all
sources and take account of the City of London Strategic Flood Risk Assessment.
Necessary mitigation measures must be designed into and integrated with the
development and may be required to provide protection from flooding for properties
beyond the site boundaries, where feasible and viable.
4. Where development is within the City Flood Risk Area, the most vulnerable uses
must be located in those parts of the development which are at least risk. Safe access
and egress routes must be identified.
5. For minor development outside the City Flood Risk Area, an appropriate flood risk
statement may be included in the Design and Access Statement.
6. Flood resistant and resilient designs which reduce the impact of flooding and
enable efficient recovery and business continuity will be encouraged.
DM18.2 Sustainable drainage systems
1. The design of the surface water drainage system should be integrated into the
design of proposed buildings or landscaping, where feasible and practical, and should
follow the SuDS management train (Fig T) and London Plan drainage hierarchy.
2. SuDS designs must take account of the City's archaeological heritage, complex
underground utilities, transport infrastructure and other underground structures,
incorporating suitable SuDS elements for the City's high density urban situation.
3. SuDS should be designed, where possible, to maximise contributions to water
resource efficiency, biodiversity enhancement and the provision of multifunctional
open spaces.
DM19.1 Additional open space
181
1. Major commercial and residential developments should provide new and enhanced
open space where possible. Where on-site provision is not feasible, new or enhanced
open space should be provided near the site, or elsewhere in the City.
2. New open space should:
a) be publicly accessible where feasible; this may be achieved through a legal
agreement;
b) provide a high quality environment;
c) incorporate soft landscaping and Sustainable Drainage Systems, where
practicable;
d) have regard to biodiversity and the creation of green corridors;
e) have regard to acoustic design to minimise noise and create tranquil spaces.
3. The use of vacant development sites to provide open space for a temporary period
will be encouraged where feasible and appropriate.
DM19.2 Biodiversity and urban greening
Developments should promote biodiversity and contribute to urban greening by
incorporating:
a) green roofs and walls, soft landscaping and trees;
b) features for wildlife, such as nesting boxes and beehives;
c) a planting mix which encourages biodiversity;
d) planting which will be resilient to a range of climate conditions;
e) maintenance of habitats within Sites of Importance for Nature Conservation.
DM21.3 Residential environment
1. The amenity of existing residents within identified residential areas will be protected
by:
a) resisting other uses which would cause undue noise disturbance, fumes and smells
and vehicle or pedestrian movements likely to cause disturbance;
b) requiring new development near existing dwellings to demonstrate adequate
mitigation measures to address detrimental impact.
2. Noise-generating uses should be sited away from residential uses, where possible.
Where residential and other uses are located within the same development or area,
adequate noise mitigation measures must be provided and, where required, planning
conditions will be imposed to protect residential amenity.
182
3. All development proposals should be designed to avoid overlooking and seek to
protect the privacy, day lighting and sun lighting levels to adjacent residential
accommodation.
4. All new residential development proposals must demonstrate how potential
adverse noise impacts on and between dwellings will be mitigated by housing layout,
design and materials.
5. The cumulative impact of individual developments on the amenity of existing
residents will be considered.
London Plan Policies
Policy GG1: Building Strong and Inclusive Communities
Policy GG2 :Making the Best Use of Land
Policy GG3: Creating a Healthy City
Policy GG5: Growing a Good Economy
Policy GG6: Increasing Efficiency and Resilience
Policy SD4: The Central Activities Zone (CAZ)
Policy SD5: Offices, and Other Strategic Functions and Residential Development
in the CAZ
Policy D1: London’s Form, Character and Capacity for Growth
Policy D2: Infrastructure Requirements for Sustainable Densities
Policy D3: Optimising Site Capacity through the Design-led approach
Policy D4: Delivering Good Design
Policy D5: Inclusive Design
Policy D8: Public Realm
Policy D10: Basement Development
Policy D11: Safety, Security and Resilience to Emergency
Policy D12: Fire Safety
Policy D14: Noise
Policy S6: Public Toilets
Policy E1: Offices
Policy E10: Visitor Infrastructure
183
Policy E11: Skills and Opportunities for All
Policy HC1: Heritage Conservation and Growth
Policy HC2: World Heritage Sites
Policy HC3: Strategic and Local Views
Policy HC4 London View Management Framework
Policy HC5: Supporting London’s Culture and Creative Industries
Policy G5: Urban Greening
Policy G6: Biodiversity and Access to Nature
Policy G7: Trees and Woodlands
Policy SI1: Improving Air Quality
Policy SI2: Minimising Greenhouse Gas Emissions
Policy SI3: Energy Infrastructure
Policy SI4: Managing Heat Risk
Policy SI5: Water Infrastructure
Policy SI7: Reducing Waste and Supporting the Circular Economy
Policy SI8: Waste Capacity and Net Waste Self-sufficiency
Policy SI13: Sustainable Drainage
Policy T1: Strategic Approach to Transport
Policy T2: Healthy Streets
Policy T3: Transport Capacity, Connectivity and Safeguarding
Policy T4: Assessing and Mitigating Transport Impacts
Policy T5: Cycling
Policy T6: Car Parking
Policy T7: Deliveries, Servicing and Construction
Policy T9: Funding Transport Infrastructure through Planning
Relevant GLA Supplementary Planning Guidance (SPG):
Accessible London: Achieving an Inclusive Environment SPG (October 2014);
184
Control of Dust and Emissions during Construction and Demolition SPG
(September 2014);
Sustainable Design and Construction (September 2014);
Social Infrastructure (May 2015);
Culture and Night-Time Economy SPG (November 2017);
London Environment Strategy (May 2018);
Cultural Strategy (2018);
Mayoral CIL 2 Charging Schedule (April 2019);
Central Activities Zone (March 2016);
Mayor’s Transport Strategy (2018) .
Relevant City Corporation Guidance and Supplementary Planning Documents
(SPDs)
Air Quality SPD (July 2017);
Archaeology and Development Guidance SPD (July 2017);
City of London Lighting SPD (October 2023);
City Transport Strategy (May 2019);
City Waste Strategy 2013-2020 (January 2014);
Protected Views SPD (January 2012);
Preventing Suicides in High Rise Buildings and Structures Planning Advice
Note (April 2022)
Planning Obligations SPD (July 2014);
Open Space Strategy (2016);
Office Use SPD (2015);
City Public Realm (2016);
Cultural Strategy 2018 2022 (2018);
Chancery Lane Conservation Area, Character Summary & Management Strategy
SPD (February 2016);
Fleet Street Area, Healthy Streets Plan (2023).
185
Relevant Draft City Plan 2040 Policies
Strategic Policy S1: Healthy and Inclusive City
Policy HL1: Inclusive Buildings and Spaces
Policy HL2: Air Quality
Policy HL3: Noise
Policy HL4: Contaminated Land and Water Quality
Policy HL6: Public toilets
Policy HL9: Health Impact Assessments
Strategic Policy S2: Safe and Secure City
Policy SA1: Publicly Accessible Locations
Policy SA2: Dispersal Routes
Policy SA3: Designing in Security
Strategic Policy S3: Housing
Policy HS3: Residential Environment
Strategic Policy S4: Offices
Policy OF1: Office Development
Policy OF2: Protection of Existing Office Floorspace
Strategic Policy S5: Retail
Policy RE2: Active frontages
Strategic Policy S6: Culture and Visitors
Policy CV2: Provision of Arts, Culture and Leisure Facilities
Policy CV3: Provision of Visitor Facilities
Policy CV5: Evening and Nigh-Time Economy
Policy CV6: Public Art
Strategic Policy S7: Infrastructure and Utilities
Policy IN1: Infrastructure Provision and Connection
Policy IN2: Infrastructure Capacity
Policy IN3: Pipe Subways
186
Strategic Policy S8: Design
Policy DE1: Sustainable Design
Policy DE2: Design Quality
Policy DE3: Public Realm
Policy DE4: Terraces and viewing galleries
Policy DE7: Daylight and Sunlight
Policy DE8: Lighting
Strategic Policy S9: Transport and Servicing
Policy VT1: The Impacts of Development on Transport
Policy VT2: Freight and Servicing
Policy VT3: Vehicle Parking
Strategic Policy S10: Active Travel and Healthy Streets
Policy AT1: Pedestrian Movement, Permeability and Wayfinding
Policy AT2: Active Travel Including Cycling
Policy AT3: Cycle Parking
Strategic Policy S11: Historic Environment
Policy HE1: Managing Change to the Historic Environment
Policy HE2: Ancient Monuments and Archaeology
Strategic Policy S13: Protected Views
Strategic Policy S14: Open spaces and Green Infrastructure
Policy OS1: Protection and Provision of Open Spaces
Policy OS2: Urban greening
Policy OS3: Biodiversity
Policy OS4: Biodiversity Net Gain
Policy OS5: Trees
Strategic Policy S15: Climate Resilience and Flood Risk
Policy CR1: Overheating and Urban Heat Island Effect
Policy CR2: Flood Risk
187
Policy CR3: Sustainable Drainage Systems (SuDS)
Strategic Policy S16: Circular Economy and Waste
Policy CE1: Sustainable Waste Facilities and Transport
Strategic Policy S26: Planning Contributions
188
SCHEDULE
APPLICATION: 23/01322/FULMAJ
38-41 Furnival Street & 31-33 High Holborn
Change of use of existing deep level tunnels (Sui Generis) to visitor and cultural
attraction (Use Class F1(b)(c)), including bar (Sui Generis); demolition and
reconstruction of existing building at 38-39 Furnival Street; redevelopment of
40-41 Furnival Street, for the principal visitor attraction pedestrian entrance at
ground floor, with ancillary retail at first and second floor levels and ancillary
offices at third and fourth levels, excavation of additional basement levels at 40-
41 Furnival Street and 38-39 Furnival Street, and widening of lift shaft at 38-39
Furnival Street; creation of new, pedestrian entrance at 31-33 High Holborn, to
provide secondary visitor attraction entrance (including principal bar entrance),
deepening of lift shaft at 31-33 High Holborn; provision of ancillary cycle
parking, substation, servicing and plant, and other associated works (Duplicate
application submitted to the London Borough of Camden as the site area
extends across the borough boundary). Re-consultation: Due to amended
details.
CONDITIONS
1. The development hereby permitted shall be begun before the expiration of three
years from the date of this permission.
REASON: To ensure compliance with the terms of Section 91 of the Town and
Country Planning Act 1990.
Use Class
2. The entirety of the site, save for the bar, herby approved shall be used for Visitor
and Cultural Attraction (Use Class F1 (b)(c)), including any ancillary spaces,
and for no other purpose (including any other purpose within Class F of the
Schedule to the Town and Country Planning (Use Classes) Order 1987 (as
amended by the Town and Country Planning (Use
Classes)(Amendment)(England) Regulations 2020) or in any provision
equivalent to that Class in any statutory instrument revoking and re-enacting
that Order with or without modification.
REASON: To ensure City of London's contribution to London's world-class
cultural offer in accordance with the following policy of the draft City Plan 2040:
S6.
Floor Areas
3. The development shall provide (all figures GIA and excluding plant):
189
- 10,341sq.m Visitor and Cultural Attraction (Class F1(b)(c));
- 284 sq.m Bar Use (Sui Generis);
REASON: To ensure the development is carried out in accordance with the
approved plans.
Operation hours
4. The permanent Visitor and Cultural Attraction (Use Class F1(b)(c)) hereby
permitted shall not be open to customers between the hours of 8pm on one day
and 10am on the following day.
REASON: To safeguard the amenity of the adjoining premises and the area
generally in accordance with the following policies of the Local Plan: DM15.7,
DM21.3.
Design and Heritage
5. Before any works thereby affected are begun the following details shall be
submitted to and approved in writing by the Local Planning Authority and all
development pursuant to this permission shall be carried out in accordance with
the approved details:
a) particulars and samples of the materials to be used on all external
faces of the building including details of compliance with the approved
Circular Economy Strategy;
b) construction of 1:1 sample material and facade panels of agreed
sections of the facades;
c) detailed drawings of a scale no less than 1:20, in plan, section and
elevation, of agreed typical bays;
d) details of all new ground floor elevations including all entrances, service
doors, crane, soffits, and information boards;
e) Details of new entrance;
f) details of all new flanking elevations;
g) irrespective of approved drawings, details of plant screening including
the 5
th
elevation;
h) details of terrace including all elevations, hard and soft landscaping,
entrances, fenestration, planters, seating, lighting, soffit, drainage, irrigation
and any infrastructure required
i) details of railings, balustrades, ramps, screens, handrails etc, bounding
or within the site;
j) details of the integration of window cleaning equipment and the
garaging thereof, plant, flues, and other excrescences at roof level including
within the plant room;
k) details of the integration of M&E and building services into the external
envelope;
190
l) details of external ducts, vents, louvres and extracts;
m) details of signage for all aspects of the building;
n) Details of access to the roof for cleaning and maintenance, including
details of mansafe equipment.
REASON: To ensure that the Local Planning Authority may be satisfied with
the detail of the proposed development and to ensure a satisfactory external
appearance in accordance with the following policies of the Local Plan:
DM3.2, DM10.1, DM10.5, DM12.2 and emerging policies SE1, DE2, DE6 and
HE1 of the Draft City Plan 2036.
6. Prior to the commencement of relevant works, a method statement shall be
submitted to and approved by the local planning authority setting out the
methodology for the dismantlement, storing and reconstructing the brick façade
of No.38-39 Furnival Street including the concrete grill. The development shall
be carried out in accordance with the approved details.
REASON: To ensure that the Local Planning Authority may be satisfied with the
detail of the proposed development and to ensure a satisfactory external
appearance in accordance with the following policies of the Local Plan: DM10.1,
DM12.2, DM12.3.
Archaeology
7. No demolition or development shall take place until a stage 1 written scheme
of investigation (WSI) has been submitted to and approved by the local planning
authority in writing. For land that is included within the WSI, no demolition or
development shall take place other than in accordance with the agreed WSI,
and the programme and methodology of site evaluation and the nomination of
a competent person(s) or organisation to undertake they're great works.
If heritage assets of archaeological interest are identified by stage 1 then for
those parts of the site would have archaeological interest a state 2 WSI shall
be submitted to and approved by the local planning authority in writing. For land
that is included within the stage 2 WSI, no demolition/development shall take
place other than in accordance with the agreed stage 2 WSI with cell include:
A. the statement off significance and the research objectives, the
programme and methodology of site investigation and recording and the
nomination of a competent person(s) or organisation to undertake the agreed
works
B. where appropriate, details of a programme for delivering related positive
public benefits
C. the programme for post investigation assessment and subsequent
analysis, publication & dissemination and deposition of resulting material. This
part of the condition shall not be discharged until these elements have been
fulfilled in accordance with the programme set out in the stage 2 WSI.
191
No demolition shall take place until a written scheme of historic building
investigation (WSI) has been submitted to and approved by the local planning
authority in writing. For buildings that are included within the WSI, no
demolition or development shall take place other than in accordance with the
agreed WSI, which shall include this statement of significance and research
objectives, and
a. the programme and methodology of historic building investigation and
recording and the nomination of a competent person(s) or organisation to
undertake the agreed works
b. the programme for post-investigation assessment and subsequent
analysis, publication & dissemination and deposition of resulting material. This
part of the conditions shall not be discharged until these elements have been
fulfilled in accordance with the programme set out in the WSI.
REASON: To safeguard the archaeological interest on this site and the
preservation of archaeological remains following archaeological investigation
in accordance with the following policy of the Local Plan: DM12.4.
Public Access and Inclusivity
8. Before any construction work hereby permitted are begun, details of the
proposed lifts shall be submitted to and approved in writing by the local planning
authority. The development shall then be implemented in accordance with the
approved details and be retained as such in perpetuity.
REASON: To ensure that the development will be accessible for people with
disabilities in accordance with the following policy of the Local Plan: DM10.8.
These details are required prior to construction work commencing in order that
any changes to satisfy this condition are incorporated into the development
before the design is too advanced to make changes.
9. Prior to the commencement of works including demolition, a site condition
survey of the adjacent highways and other land at the perimeter of the site shall
be carried out and details must be submitted to and approved in writing by the
local planning authority. Proposed finished floor levels at basement and
threshold ground floor (threshold review) levels in relation to the existing
Ordnance Datum levels of the adjoining streets and open spaces, must be
submitted and agreed with the Highways Authority. The development shall be
carried out in accordance with the approved levels unless otherwise agreed in
writing by the local planning authority.
REASON: To ensure continuity between the level of existing streets and the
finished floor levels in the proposed building and to ensure a satisfactory
treatment at ground level in accordance with the following policies of the Local
Plan: DM10.8, DM16.2. These details are required prior to commencement in
order that a record is made of the conditions prior to changes caused by the
192
development and that any changes to satisfy this condition are incorporated
into the development before the design is too advanced to make changes.
10. Before any construction work hereby permitted are begun, a scheme indicating
the provision to be made for disabled people to gain access to all areas shall
be submitted to and approved in writing by the Local Planning Authority. The
agreed scheme shall be implemented in accordance with the approved details
before the development hereby permitted is brought into use.
REASON: To ensure that the development will be accessible for people with
disabilities in accordance with the following policy of the Local Plan: DM10.8.
These details are required prior to construction work commencing in order that
any changes to satisfy this condition are incorporated into the development
before the design is too advanced to make changes.
11. The threshold of the private public realm and public route entrances shall be at
the same level as the rear of the adjoining footway.
REASON: To maintain a level passage for pedestrians in accordance with the
following policies of the Local Plan: DM10.8, DM16.2.
12. Prior to the occupation of the building, the applicant is required to submit to the
Local Planning Authority for approval of a wayfinding strategy. The developer
is to consider the implementation or removal of legible London signage within
the site and surrounding locations including transport nodes and tube stations.
The applicant shall have agreed terms and extent of the works with TfL, prior
to submission.
REASON: In the interests of visual amenity and satisfactory pedestrian
circulation of the site, in accordance with the following policies of the Local Plan:
DM10.1, DM19.2.
13. Prior to the occupation of the building, a Signage and Wayfinding Strategy,
highlighting and signposting destinations, accessible routes and facilities, cycle
parking, cultural exhibition areas and any other relevant facilities shall be
submitted to and approved in writing by the Local Planning Authority. The
strategy should include details of navigation on the site and should be designed
with reference to guidance in PAS 6463: Design for the Mind and following the
principle of ‘two senses’.
REASON: To support inclusion, public access, legibility and wayfinding in
accordance with the following policies of the Local Plan: CS10, DM10.1,
DM10.4, DM10.8, CS11, DM16.2 and DM16.4.
Construction
14. Demolition works shall not begin until a Deconstruction Logistics Plan to
manage all freight vehicle movements to and from the site during
193
deconstruction of the existing building(s) has been submitted to and approved
in writing by the Local Planning Authority. The Deconstruction Logistics Plan
shall be completed in accordance with the Mayor of London's Construction
Logistics Plan Guidance dated July 2017, and shall specifically address the
safety of vulnerable road users through compliance with the Construction
Logistics and Community Safety (CLOCS) Standard. The Plan must
demonstrate how Work Related Road Risk is to be managed. The demolition
shall not be carried out otherwise than in accordance with the approved
Deconstruction Logistics Plan or any approved amendments thereto as may be
agreed in writing by the Local Planning Authority.
REASON: To ensure that demolition works do not have an adverse impact on
public safety and the transport network in accordance with London Plan Policy
6.14 and the following policies of the Local Plan: DM15.6, DM16.1. These
details are required prior to demolition work commencing in order that the
impact on the transport network is minimised from the time that demolition
starts.
15. Construction works shall not begin until a Construction Logistics Plan (CLP)
has been submitted to and approved in writing by the Local Planning Authority,
and in consultation with TfL. The CLP aims to manage all freight vehicle
movements to and from the site during construction of the development. The
plan must be in line with TfL’s Construction Logistic Guidance, and shall
specifically address the safety of vulnerable road users through compliance
with the Construction Logistics and Community Safety (CLOCS) Standard. The
development shall not be carried out otherwise than in accordance with the
approved CLP. Any amendments thereto must be agreed in writing by the
Local Planning Authority.
REASON: To ensure that construction works do not have an adverse impact
on public safety and the transport network in accordance with London Plan
Policy 6.14 and the following policies of the Local Plan: DM15.6, DM16.1.
These details are required prior to construction work commencing in order that
the impact on the transport network is minimised from the time that construction
starts.
Cycle Parking
16. Details of the all long stay cycle parking and facilities linked to the cycle stores
shall be submitted to and approved in writing by the Local Planning Authority,
prior to the occupation of the building hereby permitted. Details shall include
permanently installed pedal cycle racks sufficient to accommodate a minimum
of 14 spaces including adaptable spaces with a range of cycle space types split
across the two bike stores. The cycle parking spaces shall be designed in line
with London Cycle Design Standards and shall be implemented prior to
occupation of the building. All doors on the access to the parking area shall be
194
automated, push button or pressure pad operated. The cycle parking spaces
and facilities shall be thereafter operated in accordance with the approved
details for the life of the building.
REASON: To ensure provision is made for cycle parking and that the Local
Planning Authority may be satisfied that the scheme provides a sustainable
transport strategy and does not have an adverse impact on the transport
network in accordance with the following policies of the Local Plan: DM16.1,
DM 16.3, and emerging policy AT3 of the Draft City Plan 2040.
17. A minimum of 5% of the long stay cycle spaces shall be accessible for larger
cycles, including adapted cycles for disabled people.
REASON: To ensure that satisfactory provision is made for people with
disabilities in accordance with Local Plan policy DMI0.8, London Plan policy TS
cycling, emerging policy AT3 of the Draft City Plan 2040.
18. Details of mobility scooter storage within the ground floor bike store, to include
fire-guarding as required, and accessible charging points at a minimum height
of 400mm above floor level.
REASON: To ensure that the development will be accessible for people with
disabilities in accordance with the following policy of the Local Plan: DM10.8.
Section 153
19. No doors, gates or windows at ground floor level shall open over the public
highway.
REASON: In the interests of public safety and to comply with section 153 of the
Highways Act 1980.
Refuse/ Recycling
20. The refuse/ recycling collection and storage facilities shown on the drawings
hereby approved shall be provided and maintained throughout the life of the
building for the use of all the occupiers.
REASON: To ensure the satisfactory servicing of the building in accordance
with the following policy of the Local Plan: DM17.1.
21. On a daily basis, and outside of the opening hours for the exhibition spaces and
ancillary areas hereby approved, the on-site FM team will transfer the bins from
the main waste storage areas to a waste presentation area on Furnival Street.
The waste management contractor appointed by the on-site FM team will
collect the bins from the waste presentation area.
REASON: To ensure the satisfactory servicing of the building in accordance
with the following policy of the Local Plan: DM17.1.
195
TfL (Infrastructure Protection)
22. The development hereby permitted shall not commence until the following
documents, in consultation with TfL Infrastructure Protection, have been
submitted to and approved in writing by the local planning authority, which:
a) provide details on the use of scaffold/tall plant i.e cranes and lifting
equipment;
b) accommodate ground movement impact on all identified LU assets
arising from the development construction. A Ground Movement
Assessment (GMA) should be submitted to TfL IP for approval;
c) mitigate the effects of noise and vibration arising from the adjoining
operations within the railway structures and tunnels;
d) no works to commence near or on the boundary with London Underground
assets until any party wall agreements required with TfL Engineering, TfL
Property or TfL Legal have been agreed and signed by all parties. As shown on
Title No. LN170205, London Underground own the Fulwood Place Vent Shaft
and other assets located at 31-33 High Holborn;
e) demonstrate that the Fulwood Place Vent Shaft and its ancillary
equipment/facilities will not be impacted by the development.
f) demonstrate that no ventilation or exhaust gases are discharged into TfL /
LUL assets or airspace.
g) demonstrate that TfL access to the vent shaft from Fulwood Place is not
impeded or altered.
REASON: To ensure that the development does not impact on existing London
Underground transport infrastructure, in accordance with London Plan 2021,
draft London Plan policy T3 and ‘Land for Industry and Transport’
Supplementary Planning Guidance 2012.
Air Quality
23. Prior to the installation of any generator. A report shall be submitted to show
what alternatives have been considered including a secondary electrical power
supply, battery backup or alternatively fuelled generators such as gas fired or
hydrogen. The details of the proposed generator shall be submitted for
approval. Where it is not possible to deploy alternatives, any diesel generators
must be the latest Euro standard available. The generator shall be used solely
on brief intermittent and exceptional occasions when required in response to a
life-threatening emergency and for the testing necessary to meet that purpose
and shall not be used at any other time.
REASON: In accordance with the following policy of the Local Plan: DM15.6
and to maintain local air quality and ensure that exhaust does not contribute to
local air pollution, particularly nitrogen dioxide and particulates PM10, in
196
accordance with the City of London Air Quality Strategy 2019 and the London
Plan Policies SI1 and SD4 D.
24. Unless otherwise agreed in writing by the local planning authority all
combustion flues must terminate at least 1m above the highest roof in the
development in order to ensure maximum dispersion of pollutants, and must be
located away from ventilation intakes and accessible roof gardens and terraces.
REASON: In order to ensure that the proposed development does not have a
detrimental impact on occupiers of residential premises in the area and to
maintain local air quality and ensure that exhaust does not contribute to local
air pollution, particularly nitrogen dioxide and particulates PM10 and 2.5, in
accordance with the City of London Air Quality Strategy 2019, Local Plan Policy
DM15.6 and London Plan policy SI1.
25. Prior to the commencement of the development, the developer/ construction
contractor shall sign up to the Non-Road Mobile Machinery Register. The
development shall be carried out in accordance with the Mayor of London
Control of Dust and Emissions during Construction and Demolition SPG July
2014 (Or any subsequent iterations) to ensure appropriate plant is used and
that the emissions standards detailed in the SPG are met. An inventory of all
NRMM used on site shall be maintained and provided to the Local Planning
Authority upon request to demonstrate compliance with the regulations.
REASON: To reduce the emissions of construction and demolition in
accordance with the Mayor of London Control of Dust and Emissions during
Construction and Demolition SPG July 2014 (or any updates thereof), Local
Plan Policy DM15.6 and London Plan Policy SI1D. Compliance is required to
be prior to commencement due to the potential impact at the beginning of the
construction.
26. An Indoor Air Quality report should be submitted and approved in writing by the
Local Planning Authority. The report should detail the air pollution environment
within the deep level tunnels, and the requirement(s) to ensure suitable air
quality is maintained for the proposed usage.
REASON: In order to ensure the proposed development reduces exposure to
poor air quality in accordance with the following policies: Local Plan policy
DM15.6, London Plan policy SI1.
Environmental Health
27. Before the development hereby permitted shall commence, unless otherwise
agreed with the Local Planning Authority, the following works shall be
undertaken in accordance with the requirements of DEFRA and the
Environment Agency’s Land Contamination Risk Management (LCRM)
guidance and be submitted to City of London for approval with due
197
consideration given to impact of development works (including remediation) on
off-site receptors, sustainable development, and future foreseeable events
within the development lifespan (e.g., climate change and extreme weather
events):
a) a preliminary risk assessment (PRA) shall be completed to identify the
potential for contamination at the site, define the conceptual site model (CSM),
and to identify and assess potential contaminant linkages associated with the
proposed development.
b) an intrusive site investigation shall be carried out followed by an
appropriate level of risk assessment to establish if the site is affected by
contamination and to determine the potential for harm to human health and non-
human receptors and pollution of controlled waters and the wider environment
(e.g., groundwater dependent terrestrial ecosystems and statutory ecological
receptors) associated with the development. The method and extent of this site
investigation shall be based on the findings of the preliminary risk assessment
(PRA), formulated in accordance with relevant British Standards, and be agreed
in writing with the Local Planning Authority prior to commencement of the work.
c) A remediation strategy to include details of measures to prevent
identified unacceptable risk to receptors from gross contamination (e.g. non
aqueous phase liquid, asbestos containing material), soil contamination,
pollution of controlled waters, and to bring the site to a condition suitable for the
intended use including provisions for long term monitoring where required, shall
then be submitted to and approved in writing by the Local Planning Authority
before the development commences . The remediation scheme must ensure
that the site will not qualify as contaminated land under Part 2A of the
Environmental Protection Act 1990 in relation to the intended use of the land
after remediation and that the site is suitable for its intended use. The
development shall proceed in strict accordance with the measures approved.
REASON: To ensure that risks from land contamination to the future users of
the land and neighbouring land are minimised, together with those to controlled
waters, to prevent pollution of the water environment, property and ecological
systems, and to ensure that the development can be carried out safely without
unacceptable risks to workers, neighbours and other offsite receptors in
accordance with the Local Plan DM15.8. These details are required prior to
commencement in order that any changes to satisfy this condition are
incorporated into the development before the design is too advanced to make
changes.
28. Prior to occupation and unless otherwise agreed with the Local Planning
Authority, a verification report produced in accordance with LCRM and other
associated guidance detailing the remediation measures completed and final
condition of the site must be submitted to and approved in writing by the Local
Planning Authority. The developer must include a statement to confirm that the
198
site development is safe, suitable for its intended use, and would not be
considered under Part 2A of the Environmental Protection Act 1990.
REASON: To ensure that the development is safe and suitable for its intended
use for the future users of the land, neighbouring land, and that risks to
controlled waters, property and ecological systems are minimised, in
accordance with the Local Plan DM15.8. These details are required prior to
occupation in order that appropriate evidence of the remedial works is agreed
and accepted by the Local Planning Authority prior to any potential exposure of
occupiers or harm to the environment from land contamination.
29. Should unexpected contamination be identified during development hereby
approved, the Local Planning Authority must be notified in writing within five
working days. An investigation and risk assessment must be undertaken in
accordance with the requirements of DEFRA and the Environment Agency’s
Land Contamination Risk Management.
Where remediation is necessary a detailed remediation scheme to bring the
site to a condition suitable for the intended use must be submitted to and
approved in writing by the Local Planning Authority. Unless otherwise agreed
in writing by the Local Planning Authority the remediation scheme must ensure
that the site will not qualify as contaminated land under Part 2A of the
Environmental Protection Act 1990 in relation to the intended use of the land
after remediation.
Following completion of measures identified in the approved remediation
scheme a verification report must be submitted to and approved in writing of
the Local Planning Authority.
REASON: To ensure that risks from land contamination to the future users of
the land and neighbouring land are minimised, together with those to controlled
waters, property and ecological systems, and to ensure that the development
can be carried out safely without unacceptable risks to workers, neighbours and
other offsite receptors in accordance with the Local Plan DM15.8. These details
are required prior to commencement in order that any changes to satisfy this
condition are incorporated into the development before the design is too
advanced to make changes.
30. No part of the roof areas except those shown as roof terraces on the drawings
hereby approved shall be used or accessed by occupiers of the building, other
than in the case of emergency or for maintenance purposes.
REASON: To safeguard the amenity of the adjoining premises and the area
generally in accordance with the following policies of the Local Plan: DM15.7,
DM21.3.
31. No live or recorded music that can be heard outside the premises shall be
played.
199
REASON: To safeguard the amenity of the adjoining premises and the area
generally in accordance with the following policies of the Local Plan: DM15.7,
DM21.3.
32. No servicing of the premises shall be carried out between the hours of 23:00
on one day and 07:00 on the following day from Monday to Saturday and
between 23:00 on Saturday and 07:00 on the following Monday and on Bank
Holidays. Servicing includes the loading and unloading of goods from vehicles
and putting rubbish outside the building.
REASON: To avoid obstruction of the surrounding streets and to safeguard the
amenity of the occupiers of adjacent premises, in accordance with the following
policies of the Local Plan: DM15.7, DM16.2, DM21.3.
33. The roof terrace on level 4 hereby permitted shall not be used or accessed
between the hours of 20:00 on one day and 08:00 on the following day and not
at any time on Sundays or Bank Holidays, other than in the case of emergency.
REASON: To safeguard the amenity of the adjoining premises and the area
generally in accordance with the following policies of the Local Plan: DM15.7,
DM21.3.
34. No amplified or other music shall be played on the roof terraces.
REASON: To safeguard the amenity of the adjoining premises and the area
generally in accordance with the following policies of the Local Plan: DM15.7,
DM21.3.
35. There shall be no promoted events on the premises. A promoted event for this
purpose, is an event involving music and dancing where the musical
entertainment is provided at any time by a disc jockey or disc jockeys one or
some of whom are not employees of the premises licence holder and the event
is promoted to the general public.
REASON: To safeguard the amenity of the adjoining premises and the area
generally in accordance with the following policies of the Local Plan: DM15.7,
DM21.3.
36. (a) The level of noise emitted from any new plant shall be lower than the existing
background level by at least 10 dBA. Noise levels shall be determined at one
metre from the window of the nearest noise sensitive premises. The
background noise level shall be expressed as the lowest LA90 (10 minutes)
during which plant is or may be in operation.
(b) Following installation but before the new plant comes into operation
measurements of noise from the new plant must be taken and a report
demonstrating that the plant as installed meets the design requirements shall
be submitted to and approved in writing by the Local Planning Authority.
200
(c) All constituent parts of the new plant shall be maintained and replaced in
whole or in part as often is required to ensure compliance with the noise levels
approved by the Local Planning Authority.
REASON: To protect the amenities of neighbouring residential/commercial
occupiers in accordance with the following policies of the Local Plan: DM15.7,
DM21.3.
37. There shall be no demolition on the site until a scheme for protecting nearby
residents and commercial occupiers from noise, dust and other environmental
effects has been submitted to and approved in writing by the Local Planning
Authority. The scheme shall be based on the Department of Markets and
Consumer Protection's Code of Practice for Deconstruction and Construction
Sites and arrangements for liaison and monitoring (including any agreed
monitoring contribution) set out therein. A staged scheme of protective works
may be submitted in respect of individual stages of the demolition process but
no works in any individual stage shall be commenced until the related scheme
of protective works has been submitted to and approved in writing by the Local
Planning Authority. The demolition shall not be carried out other than in
accordance with the approved scheme (including payment of any agreed
monitoring contribution).
REASON: In the interests of public safety and to ensure a minimal effect on the
amenities of neighbouring premises and the transport network in accordance
with the following policies of the Local Plan: DM15.6, DM15.7, DM21.3. These
details are required prior to demolition in order that the impact on amenities is
minimised from the time that development starts.
38. There shall be no construction on the site until a scheme for protecting nearby
residents and commercial occupiers from noise, dust and other environmental
effects during construction has been submitted to and approved in writing by
the Local Planning Authority. The scheme shall be based on the Department of
Markets and Consumer Protection's Code of Practice for Deconstruction and
Construction Sites and arrangements for liaison and monitoring (including any
agreed monitoring contribution) set out therein. A staged scheme of protective
works may be submitted in respect of individual stages of the construction
process but no works in any individual stage shall be commenced until the
related scheme of protective works has been submitted to and approved in
writing by the Local Planning Authority. The development shall not be carried
out other than in accordance with the approved scheme (including payment of
any agreed monitoring contribution).
REASON: In the interests of public safety and to ensure a minimal effect on the
amenities of neighbouring premises and the transport network in accordance
with the following policies of the Local Plan: DM15.6, DM15.7, DM21.3. These
details are required prior to demolition in order that the impact on amenities is
minimised from the time that the construction starts.
201
39. Before any mechanical plant is used on the premises it shall be mounted in a
way which will minimise transmission of structure borne sound or vibration to
any other part of the building in accordance with a scheme to be submitted to
and approved in writing by the Local Planning Authority.
REASON: In order to protect the amenities of commercial occupiers in the
building in accordance following policy of the Local Plan: DM15.7.
40. Before any piling or construction of basements is commenced a scheme for the
provision of sewer vents within the building shall be submitted to and approved
in writing by the local planning authority. Unless otherwise agreed in writing by
the local planning authority the agreed scheme for the provision of sewer vents
shall be implemented and brought into operation before the development is
occupied and shall be so maintained for the life of the building.
REASON: To vent sewerage odour from (or substantially from) the
development hereby permitted and mitigate any adverse air pollution or
environmental conditions in order to protect the amenity of the area in
accordance with the following policy of the Local Plan: DM10.1. These details
are required prior to piling or construction work commencing in order that any
changes to satisfy this condition are incorporated into the development before
the design is too advanced to make changes.
41. Prior to the commencement of development the developer/construction
contractor shall sign up to the Non-Road Mobile Machinery Register. The
development shall be carried out in accordance with the NRMM Regulations
and the inventory of all NRMM used on site shall be maintained and provided
to the Local Planning Authority upon request to demonstrate compliance with
the regulations.
REASON: To reduce the emissions of construction and demolition in
accordance with the Mayor of London Control of Dust and Emissions during
Construction and Demolition SPG July 2014. Compliance is required to be prior
to commencement due to the potential impact at the beginning of the
construction.
42. All parts of the ventilation and extraction equipment including the odour control
systems installed shall be cleaned, serviced and maintained in accordance with
Section 5 of ‘Control of Odour & Noise from Commercial Kitchen Extract
Systems’ dated September 2018 by EMAQ+ (or any subsequent updated
version). A record of all such cleaning, servicing and maintenance shall be
maintained and kept on site and upon request provided to the Local Planning
Authority to demonstrate compliance.
REASON: To protect the occupiers of existing and adjoining premises and
public amenity in accordance with Policies DM 10.1, DM 15.7 and DM 21.3.
202
Lighting Strategy
43. Prior to the commencement of the relevant works, a full Lighting Strategy and
a Technical Lighting Design shall be submitted to and approved in writing by
the Local Planning Authority, which should include full details of:
a. all luminaires both decorative, functional or ambient (including
associated infrastructure);
b. lighting layouts;
c. a lighting control methodology;
d. proposed operational timings and associated design and management
measures to reduce the impact on the local environment and residential
amenity including light pollution, light spill, and potential harm to local ecologies;
e. all external, semi-external and public-facing parts of the building and of
any internal lighting in relation spaces and terraces so far that it creates visual
or actual physical impact on the lit context to show how the facade and/or the
lighting has been designed to help reduce glare, excessive visual brightness,
and light trespass;
f. the impact on the public realm, including typical illuminance levels,
uniformity, colour appearance and colour rendering.
All works and management measures pursuant to this consent shall be carried
out and maintained in accordance with the approved details and Lighting
Strategy.
REASON: To ensure that the Local Planning Authority may be satisfied with the
detail of the proposed development and to ensure a satisfactory external
appearance in accordance with the following policies of the Local Plan: DM10.1,
15.7 and emerging policy DE8 of the Draft City Plan 2040.
Thames Water
44. No piling shall take place until a PILING METHOD STATEMENT (detailing the
depth and type of piling to be undertaken and the methodology by which such
piling will be carried out, including measures to prevent and minimise the
potential for damage to subsurface sewerage infrastructure, and the
programme for the works) has been submitted to and approved in writing by the
local planning authority in consultation with Thames Water. Any piling must be
undertaken in accordance with the terms of the approved piling method
statement.
REASON: The proposed works will be in close proximity to underground
sewerage utility infrastructure. Piling has the potential to significantly impact /
cause failure of local underground sewerage utility infrastructure. Please read
our guide ‘working near our assets’ to ensure your workings will be in line with
the necessary processes you need to follow if you’re considering working above
or near our pipes or other structures.
203
45. No construction shall take place within 5m of the water main. Information
detailing how the developer intends to divert the asset / align the development,
so as to prevent the potential for damage to subsurface potable water
infrastructure, must be submitted to and approved in writing by the local
planning authority in consultation with Thames Water. Any construction must
be undertaken in accordance with the terms of the approved information.
Unrestricted access must be available at all times for the maintenance and
repair of the asset during and after the construction works.
REASON: The proposed works will be in close proximity to underground
strategic water main, utility infrastructure. The works has the potential to impact
on local underground water utility infrastructure.
46. No piling shall take place until a piling method statement (detailing the depth
and type of piling to be undertaken and the methodology by which such piling
will be carried out, including measures to prevent and minimise the potential for
damage to subsurface water infrastructure, and the programme for the works)
has been submitted to and approved in writing by the local planning authority
in consultation with Thames Water. Any piling must be undertaken in
accordance with the terms of the approved piling method statement.
REASON: The proposed works will be in close proximity to underground water
utility infrastructure. Piling has the potential to impact on local underground
water utility infrastructure.
Carbon and Energy
47. Prior to the commencement of the development, (excluding demolition), an
update to the approved detailed Whole Life-Cycle Carbon assessment shall be
submitted to and approved in writing by the Local Planning Authority. The
assessment must be based on a highest use scenario, full fit-out, (including
fixtures and equipment, specifically audio-visual equipment) and “best guess”
frequency of operation (special exhibitions and events). The assessment
should include details of measures to reduce carbon emissions throughout the
whole life-cycle of the development and provide calculations in line with the
Mayor of London's guidance on Whole Life-Cycle Carbon Assessments, and
the development shall be carried out in accordance with the approved details
and operated and managed in accordance with the approved assessment for
the life-cycle of the development.
REASON: To ensure that the Local Planning Authority may be satisfied with the
detail of the proposed development so that it maximises the reduction of carbon
emissions of the development throughout the whole life cycle of the
development in accordance with the following policies in the Development Plan
and draft Development Plans: London Plan: D3, SI 2, SI 7 - Local Plan: CS 17,
DM 15.2, DM 17.2 - Draft City Plan 2036: CE 1. These details are required prior
204
to demolition (as specified above) and construction work commencing in order
to be able to account for embodied carbon emissions resulting from the
demolition and construction phase (including recycling and reuse of materials)
of the development.
48. Once the as-built design has been completed (upon commencement of RIBA
Stage 6) and prior to the development being occupied (or if earlier, prior to the
development being handed over to a new owner or proposed occupier,) the
post-construction Whole Life-Cycle Carbon (WLC) Assessment (to be
completed in accordance with and in line with the criteria set out in in the GLA's
WLC Assessment Guidance) shall be submitted to the Local Planning Authority
. The post-construction assessment should provide an update of the information
submitted at planning submission stage (RIBA Stage 2/3), including the WLC
carbon emission figures for all life-cycle modules based on the actual materials,
products and systems used. The assessment should be submitted along with
any supporting evidence as per the guidance and should be received three
months post as-built design completion, unless otherwise agreed.
REASON: To ensure whole life-cycle carbon emissions are calculated and
reduced and to demonstrate compliance with Policy SI 2 of the London Plan.
49. The development shall be designed to allow for connection into a district
heating network if this becomes available during the lifetime of the
development. This is to include a strategy with relevant plan drawings for:
equipment, allocation of plant space and a protected route for connection in
and out of the site. This is in addition to the requirement to find a beneficial use
for the waste heat produced through the development’s operations.
REASON: To minimise carbon emissions by enabling the building to be
connected to a district heating and cooling network if one becomes available
during the life of the building in accordance with the following policies of the
Local Plan: DM15.1, DM15.2, DM15.3, DM15.3, DM15.4.
50. Prior to the commencement of development, excluding demolition, an updated
Energy Assessment confirming the detailed design stage highest use scenario
full fit-out, (including fixtures and equipment, specifically audio-visual
equipment) and “best guess” frequency of operation (special exhibitions and
events) is to be submitted to and approved in writing by the Local Planning
Authority. The development shall be carried out in accordance with the
approved Energy Assessment and the carbon reduction measures contained
with the approved Energy Assessment shall remain in place for the lifetime of
the development.
REASON: To demonstrate that carbon emissions have been minimised and
that the development is sustainable in accordance with the following policy of
the Local Plan: CS15, DM15.1, DM15.2. These details are required prior to
205
demolition and construction work commencing in order to be able to account
for the carbon emissions associated with the proposed fit-out.
Circular Economy
51. (a) Prior to demolition of the development an updated pre-demolition audit in
accordance with section 4.6 of the GLA’s adopted Circular Economy Statement
guidance shall be submitted to and approved in writing by the Local Planning
Authority, that demonstrates that the development is designed to meet the
relevant targets set out in the GLA Circular Economy Statement Guidance. The
development shall be carried out in accordance with the approved details and
operated & managed in accordance with the approved details throughout the
lifecycle of the development.
b) Prior to the commencement of the development (excluding demolition), after
RIBA Stage 4, an update to the approved detailed Circular Economy Statement
to reaffirm the proposed strategy, to include a site waste management plan and
details of the proposed demountable partition design, shall be submitted to and
approved in writing the Local Planning Authority, that demonstrates that the
Statement has been prepared in accordance with the GLA Circular Economy
Guidance and that the development is designed to meet the relevant targets
set out in the GLA Circular Economy Guidance. The end-of-life strategy of the
statement should include the approach to storing detailed building information
relating to the structure and materials of the new building elements and of the
interventions in order to distinguish the historic from the new fabric. The
development shall be carried out in accordance with the approved details and
operated & managed in accordance with the approved details throughout the
lifecycle of the development.
REASON : To ensure that the Local Planning Authority may be satisfied with
the detail of the proposed development so that it reduces the demand for
redevelopment, encourages re-use and reduces waste in accordance with the
following policies in the Development Plans and draft Development Plans:
London Plan; D3, SI 7, SI 8 - Local Plan; CS 17, DM 17.2 - Draft City Plan 2036;
S16, CEW 1. These details are required prior to construction work commencing
in order to establish the extent of recycling and minimised waste from the time
that construction start.
52. No later than 3 months after completion of the building, a post-construction
Circular Economy Statement shall be submitted to and approved in writing by
the local planning authority to demonstrate that the targets and actual outcomes
achieved are in compliance with or exceed the proposed targets stated in the
approved Circular Economy Statement for the development.
REASON: To ensure that circular economy principles have been applied and
Circular Economy targets and commitments have been achieved to
demonstrate compliance with Policy SI 7 of the London Plan.
206
Greening and Biodiversity
53. Within 6 months of completion of the development, details of the final
landscaping design and an Ecological Management Plan, to include plant and
habitat species (with information on coverage and biodiversity improvement),
scaled drawings identifying measures and maintenance strategies, shall be
submitted to the Local Planning Authority. Landscaping and biodiversity
measures shall be maintained in accordance with the submission documents
to ensure the approved standard is preserved for the lifetime of the
development.
REASON: To support the environmental sustainability of the development and
provide a habitat that will encourage biodiversity in accordance with the
following policies of the Local Plan: DM18.2, DM19.2, and Draft City Plan: S14,
OS2 whilst ensuring these benefits are maintained in the long term.
Water Management
54. Before any construction works hereby permitted are begun the following details
shall be submitted to and approved in writing by the Local Planning Authority in
conjunction with the Lead Local Flood Authority and all development pursuant
to this permission shall be carried out in accordance with the approved details:
(a) Fully detailed design and layout drawings for the proposed SuDS
components including but not limited to: attenuation systems, blue roofs,
rainwater pipework, flow control devices, design for system exceedance,
design for ongoing maintenance; surface water flow rates shall be restricted to
no greater than 1.5 l/s from each outfall and from no more than one distinct
outfall, provision should be made for an attenuation volume capacity capable
of achieving this, which should be no less than 25m3;
(b) Full details of measures to be taken to prevent flooding (of the site or caused
by the site)during the course of the construction works.
Before the shell and core is complete the following details shall be submitted to
and approved in writing by the Local Planning Authority in conjunction with the
Lead Local Flood Authority and all development pursuant to this permission
shall be carried out in accordance with the approved details:
(a) A Lifetime Maintenance Plan for the SuDS system to include:
- A full description of how the system would work, it's aims and objectives and
the flow control arrangements;
- A Maintenance Inspection Checklist/Log;
- A Maintenance Schedule of Work itemising the tasks to be undertaken, such
as the frequency required and the costs incurred to maintain the system.
207
REASON: To improve sustainability, reduce flood risk and reduce water runoff
rates in accordance with the following policy of the Local Plan: DM18.1, DM18.2
and DM18.3.
Climate Resilience
55. Prior to the commencement of the development, excluding demolition, a
Climate Change Resilience Sustainability Statement (CCRSS) shall be
submitted to and approved in writing by the Local Planning Authority, that
demonstrates that the development is resilient and adaptable to predicted
climate conditions during the lifetime of the development. The CCRSS shall
include details of the climate risks that the development faces (including flood,
heat stress, water stress, natural capital, pests and diseases) and the climate
resilience solutions for addressing such risks. The CCRSS will demonstrate that
the potential for resilience and adaptation measures (including but not limited
to solar shading to prevent solar gain; high thermal mass of building fabric to
moderate temperature fluctuations; cool roofs to prevent overheating; urban
greening; rainwater attenuation and drainage; flood risk mitigation; biodiversity
protection; passive ventilation and heat recovery and air quality assessment to
ensure building services do not contribute to worsening photochemical smog)
has been considered and appropriate measures incorporated in the design of
the building. The CCRSS shall also demonstrate how the development will be
operated and managed to ensure the identified measures are maintained for
the life of the development. The development shall be carried out in accordance
with the approved CCRSS and operated and managed in accordance with the
approved CCRSS for the life of the development.
REASON: To comply with Local Plan Policy DM 15.5 Climate change resilience
and adaptation.
56. Within 6 months of completion details of climate change resilience measures
must be submitted to the Local Planning Authority demonstrating the measures
that have been incorporated to ensure that the development is resilient to the
predicted weather patterns during the lifetime of the building. This should
include details of the climate risks that the site faces (flood, heat stress, water
stress, natural capital, pests and diseases) and the climate resilience solutions
that have been implemented.
REASON: To comply with Local Plan Policy DM 15.5 Climate change resilience
and adaptation.
BREEAM
57. A post construction BREEAM assessment demonstrating that a target rating of
at least 'Excellent' has been achieved (or such other target rating as the local
planning authority may agree provided that it is satisfied all reasonable
208
endeavours have been used to achieve an 'Excellent' rating) shall be submitted
as soon as practicable after practical completion.
REASON: To demonstrate that carbon emissions have been minimised and
that the development is sustainable in accordance with the following policy of
the Local Plan: CS15, DM15.1, DM15.2.
Security
58. Prior to occupation, security measures must be provided within the
development, having being developed in consultation with City Police, such as
CCTV, lighting, entrances and improvements to secure access.
REASON: To ensure safety and security in accordance with Local Plan policies
CS3 and DM3.2.
Suicide Prevention Measures
59. Prior to the occupation of the roof terrace, details of suicide prevention
measures to prevent jumping or falling from the development shall be submitted
to and approved in writing by the Local Planning Authority. All development
pursuant to this permission shall be carried out in accordance with the approved
details and maintained for the life of the building.
REASON: To ensure that the Local Planning Authority may be satisfied with the
detail of the proposed development and to ensure adequate safety measures
are in place in accordance with Local Plan Policy CS3 and emerging draft City
Plan 2036 Policy DE2 and DE5.
Telecommunications equipment
60. Unless otherwise approved by the LPA no plant or telecommunications
equipment shall be installed on the exterior of the building, including any plant
or telecommunications equipment permitted by the Town & Country Planning
(General Permitted Development) Order 2015 or in any provisions in any
statutory instrument revoking and re-enacting that Order with or without
modification.
REASON: , To ensure a satisfactory external appearance in accordance with
the following policy of the Local Plan: DM10.1.
Approved Plans
61. The development shall not be carried out other than in accordance with the
following approved drawings and particulars or as approved under conditions
of this planning permission:
Site Location Plan 01820-WEA-XX-ST-PD-A-0003 Rev 00
209
Demolition: PD-A-0150 Rev 00, PD-A-0151 Rev 00, PD-A-0152 Rev 01, PD-A-
0349 Rev 00, PD-A-0350 Rev 00, PD-A-0351 Rev 00, PD-A-0352 Rev 00, and
PD-A-0353 Rev 00.
Proposed Furnival Street:
PROPOSED B3 PLAN 01-B3-PD-A-1097 Rev 00;
PROPOSED B2 PLAN 01-B2-PD-A-1098 Rev 00;
PROPOSED B1 PLAN 01-B1-PD-A-1099 Rev 02;
PROPOSED L00 PLAN 01-00-PD-A-1100 Rev 04;
PROPOSED L01 PLAN 01-01-PD-A-1101 Rev 00;
PROPOSED L02 PLAN 01-02-PD-A-1102 Rev 01;
PROPOSED L03 PLAN 01-03-PD-A-1103 Rev 00;
PROPOSED L04 PLAN 01-04-PD-A-1104 Rev 00;
PROPOSED L05 PLAN 01-05-PD-A-1105 Rev 00;
PROPOSED ROOF PLAN 01-RF-PD-A-1106 Rev 00;
OVERALL PROPOSED WEST ELEVATION 01-W-PD-A-2100 Rev 01;
PROPOSED WEST ELEVATION 01-W-PD-A-2104 Rev 01;
PROPOSED NORTH ELEVATION 01-N-PD-A-2101 Rev 00;
PROPOSED SOUTH ELEVATION 01-S-PD-A-2102 Rev 01;
PROPOSED EAST ELEVATION 01-E-PD-A-2103 Rev 01;
WEST FAÇADE SETTING OUT 01-ZZ-PD-A-3050 Rev 00;
GA BUILDING SECTION AA 01-AA-PD-A-3100 Rev 01;
GA BUILDING SECTION BB 01-BB-PD-A-3101 Rev 01;
GA BUILDING SECTION CC 01-CC-PD-A-3102 Rev 01;
GA SHAFT SECTION AA 01-AA-PD-A-3103 Rev 01;
GA SHAFT SECTION CC 01-CC-PD-A-3105 Rev 01;
CENTRAL LIFT DETAIL 01-ZZ-A-4150 Rev 00;
STAFF BIKE STORE (Ground floor plan) 01-00-A-4151 Rev 02;
FAÇADE TYPE 01 - GLASS BRICK LOWER 01-ZZ-PD-A-5101 Rev 01;
FAÇADE TYPE 01B - GLASS BRICK UPPER 01-ZZ-PD-A-5107 Rev 01;
FAÇADE TYPE 02 - REINSTATED BRICK 01-ZZ-PD-A-5102 Rev 01;
FAÇADE TYPE 03 - GROUND FLOOR EXIT 01-ZZ-PD-A-5103 Rev 01;
FACADE TYPE 03B - GROUND FLOOR ENTRANCE 01-ZZ-PD-A-5108
Rev01;
FAÇADE TYPE 04 - L04 TERRACE 01-ZZ-PD-A-5104 Rev 01;
FAÇADE TYPE 05 - PLANT SCREEN 01-ZZ-PD-A-5105 Rev 01;
FAÇADE TYPE 06 - PARTY WALL 01-ZZ-PD-A-5106 Rev 00;
Plan showing extend of Section 278 works 70106185-TP-SK-1 P02;
Proposed Tunnels GAs:
PROPOSED LMINUS 01 PLAN 03-M1-PD-A-0099 Rev 00;
PROPOSED LPLUS 01 PLAN 03-01-PD-A-1001 Rev 00;
PROPOSED LPLUS 02 PLAN 03-02-PD-A-1002 Rev 00;
210
PROPOSED LPLUS 03 PLAN 03-03-PD-A-1003 Rev 00;
PROPOSED SECTOR A PLAN 03-ZZ-PD-A-1010 Rev 01;
PROPOSED SECTOR B PLAN 03-ZZ-PD-A-1011 Rev 01;
PROPOSED SECTOR C & D PLAN 03-ZZ-PD-A-1012 Rev 01;
PROPOSED SECTOR B PLAN 03-ZZ-PD-A-1013 Rev 01;
PROPOSED - CROSS SECTIONS 03-ZZ-PD-A-3300 Rev 00.
REASON: To ensure that the development of this site is in compliance with
details and particulars which have been approved by the Local Planning
Authority.
INFORMATIVES
1. In dealing with this application the City has implemented the requirements of
the National Planning Policy Framework to work with the applicant in a positive
and proactive manner based on seeking solutions to problems arising in dealing
with planning applications in the following ways:
- detailed advice in the form of statutory policies in the Local Plan,
Supplementary Planning documents, and other written guidance has been
made available;
- a full pre application advice service has been offered;
where appropriate the City has been available to provide guidance on
how outstanding planning concerns may be addressed.
2. This approval relates only to the details listed above and must not be construed
as approval of any other details shown on the approved drawings.
3. Access for people with disabilities is a material consideration in the
determination of planning applications. The City of London Corporation has
published design standards giving advice on access for people with disabilities
and setting out the minimum standards it expects to see adopted in the City
buildings. These can be obtained from the City's Access Adviser, Chief
Planning Officer and District Surveyor. Further advice on improving access for
people with disabilities can be obtained from the City's Access Adviser. Your
attention is drawn to the Disability Discrimination provisions of the Equality Act
2010 to ensure that disabled people are not significantly disadvantaged.
Service providers, etc., should make "reasonable adjustments" to facilitate
access to their premises and the City asks all applicants for planning permission
to ensure that physical barriers to access premises are minimised in any works
carried out.
211
4. Service providers are required to have regard to obligations under the Equality
Act 2010. In the exercise of their functions, due regard needs to be given to:
elimination of discrimination, harassment and victimisation and any other
conduct that is prohibited by or under this Act;
advancement of equality of opportunity between persons who share a
relevant protected characteristic and persons who do not share it;
fostering good relations between persons who share a relevant
protected characteristic and persons who do not share it
The relevant protected characteristics are age, disability, gender reassignment,
pregnancy and maternity, race, religion or belief, sex and sexual orientation.
Public authorities also need to have due regard to the need to eliminate
unlawful discrimination against someone because of their marriage or civil
partnership status.
5. The developer should be aware that, in creating a roof terrace, and therefore
access to the roof, users of the roof could be exposed to emissions of air
pollutants from any chimneys that extract on the roof e.g. from gas boilers /
generators / CHP. In order to minimise risk, as a rule of thumb, we would
suggest a design that places a minimum of 3 metres from the point of efflux of
any chimney serving combustion plant, to any person using the roof terrace.
This distance should allow the gases to disperse adequately at that height,
minimising the risk to health.
6. Generators and combustion plant
Please be aware that backup/emergency generators may require permitting
under the MCP directive and require a permit by the appropriate deadline.
Further advice can be obtained from here: Medium combustion plant and
specified generators: environmental permits - GOV.UK (www.gov.uk)
7. Environmental Agency: Water Resources
Increased water efficiency for all new developments potentially enables more
growth with the same water resources. Developers can highlight positive
corporate social responsibility messages and the use of technology to help sell
their homes. For the homeowner lower water usage also reduces water and
energy bills.
We endorse the use of water efficiency measures especially in new
developments. Use of technology that ensures efficient use of natural resources
could support the environmental benefits of future proposals and could help
attract investment to the area. Therefore, water efficient technology, fixtures
and fittings should be considered as part of new developments.
212
We recommend that all new non-residential development of 1000sqm gross
floor area or more should meet the BREEAM ‘excellent’ standards for water
consumption.
8. Thames Water
Waste
“A Groundwater Risk Management Permit from Thames Water will be required
for discharging groundwater into a public sewer. Any discharge made without
a permit is deemed illegal and may result in prosecution under the provisions
of the Water Industry Act 1991. We would expect the developer to demonstrate
what measures he will undertake to minimise groundwater discharges into the
public sewer. Permit enquiries should be directed to Thames Water’s Risk
Management Team by telephoning 020 3577 9483 or by emailing
[email protected]. Application forms should be completed on
line via www.thameswater.co.uk. Please refer to the Wholesale; Business
customers; Groundwater discharges section.
Water
Thames Water will aim to provide customers with a minimum pressure of 10m
head (approx 1 bar) and a flow rate of 9 litres/minute at the point where it leaves
Thames Waters pipes. The developer should take account of this minimum
pressure in the design of the proposed development.
9. This permission must in no way be deemed to be an approval for the display of
advertisement matter indicated on the drawing(s) which must form the subject
of a separate application under the Advertisement Regulations.
10. This permission must in no way be deemed to prejudice any rights of light which
may be enjoyed by the adjoining owners or occupiers under Common Law.
11. WilkinsonEyre Architects should be retained for the detailed construction stage
of the project.
12. This permission is granted having regard to planning considerations only and
is without prejudice to the position of the City of London Corporation or
Transport for London as Highway Authority; and work must not be commenced
until the consent of the Highway Authority has been obtained.
13. Improvement or other works to the public highway shown on the submitted
drawings require separate approval from the local highway authority and the
planning permission hereby granted does not authorise these works.
213
14. The correct street number or number and name must be displayed prominently
on the premises in accordance with regulations made under Section 12 of the
London Building Acts (Amendment) Act 1939. Names and numbers must be
agreed with the Department of the Built Environment prior to their use including
use for marketing.
15. The landowners, managing operators and tenants are required to adhere to the
actions of the Considerate Lighting Charter as set in the City of London
Appendix A of the City of London Lighting Supplementary Planning Document
17/11/2022
16. The Crime Prevention Design Advisor for the City of London Police and the
Counter-Terrorism Security Advisor should be consulted with regard to
guidance on all aspects of security, means of crime prevention in new
development and on current crime trends.
17. The grant of approval under the Town and Country Planning Acts does not
overcome the need to also obtain any licences and consents which may be
required by other legislation. The London Fire Brigade should form a key
stakeholder at detailed design stage including Qualitative Design Review
(QDR) process, fire precautions and certification stages.
Archaeology
18. The Written Scheme of Investigation will need to be prepared and implemented
by a suitably professionally accredited heritage practice in accordance with
Historic England’s Guidelines for Archaeological Projects in Greater London.
The pre-commencement conditions are necessary to safeguard the
archaeological interest on this site. Approval of the WSI before works begin on
site provides clarity on what investigations are required, and their timing in
relation to the development programme.
Evaluation: An archaeological field evaluation involves exploratory fieldwork to
determine if significant remains are present on a site and if so to define their
character, extend, quality and preservation. Field evaluation may involve one
or more techniques depending on the nature of the site and its archaeological
potential. It will normally include excavation of trial trenches.
Historic Building Recording: Historic building recording is an investigation to
establish the character, history, dating, form and development of a historic
building or structure which normally takes place as a condition of planning
permission before any alteration or demolition takes place. The outcome will be
an archive and a report which may be published. You can find more information
on archaeology and planning in Greater London on GLAAS website.
214
19. The Directorate of the Built Environment (District Surveyor) should be consulted
on means of escape and constructional details under the Building Regulations
and London Building Acts.